Use Case & TCO: 80 kWp Solar for a LATAM Fuel Station

Verdict: At 1,500 kWh/kWp/yr, 95% self-consumption, USD 88,000 CapEx (year 0), 25-year horizon and 10.00% discount rate, an 80 kWp canopy PV (modules: Jinko Solar Tiger Neo N-type TOPCon family, e.g. JKM-N-54HL4R-V; inverter: Sungrow SG-series 3-phase string inverter; mounting: K2 Systems rail/kit for canopy roof) yields NPV = USD 119,948.53, simple payback = 4.32 yr, discounted payback = 5.86 yr, LCOE = USD 0.0983/kWh, IRR = 24.19%. LATAM fuel-station sites proceed to RFQ (/rfq/). Equipment: 80 kWp canopy PV. Location class: mid-LATAM (1,500 kWh/kWp/yr). Horizon: 25 years. Evidence date: 2026-09-22. Limitation: HS codes 8541.43 / 8504.40 / 7308.90 / 8544.42 / 8537.10 are WCO 6-digit baselines, PENDING national 8–10-digit verification; yields, self-consumption, discount rate, tariff and export tariff are explicit bounded model assumptions.

Decision summary
FieldValue
Equipment80 kWp canopy PV — Jinko Tiger Neo TOPCon modules (JKM-N-54HL4R-V class), Sungrow SG-series 3-phase string inverter, K2 Systems rail/kit for canopy roof
Location classMid-LATAM (1,500 kWh/kWp/yr); high-irradiance variant noted
Horizon25 years
Discount rate10.00 %
NPV (USD)119,948.53
IRR24.19 %
Simple payback4.32 yr
Discounted payback5.86 yr
LCOEUSD 0.0983 / kWh
CapEx (year 0)USD 88,000.00 (incl. fuel-station retrofit premium; see §3)
Year-1 energy120,000.00 kWh (table input)
Tariff / exportUSD 0.180 / kWh retail · USD 0.090 / kWh export (model assumption)
Evidence date2026-09-22
LimitationHS codes 8541.43 / 8504.40 / 7308.90 / 8544.42 / 8537.10 are WCO 6-digit baselines — PENDING national 8–10-digit verification; yields, self-consumption, discount rate, tariff and export tariff are explicit bounded model assumptions
ActionProceed to /rfq/

1. Equipment (real, publicly marketed models)

ItemModel / familyManufacturer landingSpecific datasheet / product page
PV modulesJinko Solar Tiger Neo N-type TOPCon, e.g. JKM-N-54HL4R-V series, 415–440 Wp class (datasheet: power, Voc/Isc, mechanical load ratings used as canopy wind re-certification basis)https://www.jinkosolar.com/en/Tiger Neo product family page on the JinkoSolar landing (exact JKM-N-54HL4R-V datasheet PDF confirmed at RFQ; landing is the computed public reference)
String inverterSungrow SG-series 3-phase string inverter, C&I class (SG50CX / SG60CX class); datasheet: max DC input voltage, MPPT range, IP66 ratinghttps://www.sungrowpower.com/enhttps://www.sungrowpower.com/en/products/string-inverter — exact SG-class model and datasheet revision confirmed at RFQ
Mounting systemK2 Systems rail/kit family for trapezoidal / sandwich canopy roofs (Dome 6 / SpeedRail / MultiRail family; clamp/rail set with wind bracing); manual rev confirmed at RFQ — used for canopy structural re-certification basishttps://k2-systems.com/en/K2 product-solutions landing (downloads bot-walled; exact rail/kit model and assembly manual revision confirmed at RFQ)
Alternates named for reference (not assumed)LONGi Hi-MO 5m (LR5-72HBD / LR5-54HTH family), Trina Vertex N, Huawei SUN2000-330KTL-H1 (1500 V DC, 8-MPPT 3-phase), Growatt MID/MOD series, CATL EnerC storage, BYD MC Cube / HVS/HVM commercial-industrial LFP, EVE Energy LFP cells (only if a battery add-on is later scoped)https://www.longi.com/en/ · https://www.trinasolar.com/us-en · https://solar.huawei.com/en · https://www.growatt.com/ · https://www.catl.com/en/ess/ · https://www.bydenergy.com/ · https://www.evebattery.com/enhttps://www.longi.com/en/products/modules/hi-mo-5m/ · https://solar.huawei.com/en/products/sun2000-330ktl-h1 (exact datasheets confirmed at RFQ)

Module / inverter / mounting product pages are JS-rendered; manufacturer landings above are the computed public references. Exact model numbers, datasheet revisions and OEM manual revision are confirmed at RFQ.

2. Scope, horizon, residual value and other bounded model assumptions

The COMPUTED TABLES are the only mathematics on this page. Prose inputs below match the table inputs exactly.

AssumptionValueClassification
CurrencyUSDStated
Horizon25 yearsStated
Discount rate10.00 %/yrModel assumption — bounded to commercial LATAM fuel-retail range
CapEx (year 0)USD 88,000.00Table input (matches COMPUTED cash flow)
Year-1 energy120,000.00 kWhTable input (matches COMPUTED cash flow)
Year-1 benefitUSD 21,060.00Table input (matches COMPUTED cash flow)
Year-1 costUSD 1,320.00Table input (matches COMPUTED cash flow)
Self-consumption share95 %Model assumption (fuel-station daytime load profile)
Performance ratio / losses embedded in year-1 energyPR implicit in COMPUTED year-1 energy 120,000 kWh vs 80 kWp × 1,500 kWh/kWp/yr nominal = 120,000 kWh (table is a clean reference series; specific yield applied upstream in scenario)Model assumption — bounded
Annual degradation0.5 %/yr (matches descending kWh column in cash flow table)Model assumption — bounded to Tier-1 warranty band
Tariff inflationEmbedded in COMPUTED benefit column (rising ~2.5%/yr implied)Model assumption — bounded
OpEx inflationEmbedded in COMPUTED cost column (rising ~3%/yr implied)Model assumption — bounded
Residual value (residual_value.amount)USD 0Model assumption — bounded; conservative at end of module power-warranty horizon
Residual value (residual_value.year)Year 25 (terminal)Model assumption — bounded
Specific yield scenario range1,500 (base) – 1,800 (high) kWh/kWp/yrModel assumption — bounded; EU PVGIS-SARAH2 used as a year-1 generation reference path (EU PVGIS) and IEA-PVPS Trends 2024 (IEA-PVPS Trends in PV Applications 2024) cited only at band level
Retail tariff rangeUSD 0.18/kWh (base)Model assumption — bounded to OLADE non-residential LATAM band

Specific yields, tariff and self-consumption share above are explicit bounded model assumptions (i.e. not sourced facts). They are stated only to bracket the COMPUTED TABLES, which are computed.

3. CapEx build-up (prose-only, mirrors table inputs)

CapEx = USD 88,000 (year-0 COMPUTED cash flow) = base hardware + EPC + soft costs (≈ USD 0.70/Wp on 80 kWp = USD 56,000) plus a fuel-station retrofit premium (≈ USD 0.40/Wp = USD 32,000) for canopy structural re-certification (using K2 Systems rail/kit family + OEM assembly manual revision confirmed at RFQ; product-solutions landing: https://k2-systems.com/en/), explosion-rated cable routing near dispensers (relevant IEC designation + edition cited at RFQ via the IEC Webstore catalogue: https://webstore.iec.ch/), equipotential bonding to existing earthing mesh, and extended grid-interconnection studies. No worked arithmetic or derived figure below the COMPUTED TABLES is presented. UK DESNZ solar PV cost data is cited only as a UK C&I EPC cost-per-kW benchmark reference: https://www.gov.uk/government/statistics/solar-pv-cost-data.

4. COMPUTED TCO summary (computed — copy verbatim)

TCO summary
MetricValue
CurrencyUSD
Horizon (years)25
Discount rate10.00 %
Total undiscounted cost (USD)136,126.23
Total discounted cost / PV of costs (USD)103,213.05
Total undiscounted benefit (USD)673,482.39
Total discounted benefit (USD)223,161.58
NPV (USD)119,948.53
IRR0.2419
Simple payback (year)4.32
Discounted payback (year)5.86
LCOE (USD/kWh)0.0983

5. COMPUTED year-by-year cash flow (computed — copy verbatim)

Year-by-year cash flow
YearCost (USD)Benefit (USD)Net (USD)Discount factorDiscounted net (USD)Energy (kWh)
088,000.000.0000-88,000.001.00-88,000.000.0000
11,320.0021,060.0019,740.000.909117,945.45120,000.00
21,359.6021,478.5720,118.970.826416,627.25119,400.00
31,400.3921,905.4520,505.070.751315,405.76118,803.00
41,442.4022,340.8220,898.430.683014,273.91118,208.99
51,485.6722,784.8521,299.180.620913,225.11117,617.94
61,530.2423,237.7021,707.460.564512,253.29117,029.85
71,576.1523,699.5522,123.400.513211,352.80116,444.70
81,623.4324,170.5822,547.140.466510,518.41115,862.48
91,672.1424,650.9722,978.830.42419,745.27115,283.17
101,722.3025,140.9023,418.600.38559,028.89114,706.75
111,773.9725,640.5823,866.610.35058,365.10114,133.22
121,827.1926,150.1924,323.000.31867,750.06113,562.55
131,882.0026,669.9224,787.920.28977,180.18112,994.74
141,938.4627,199.9925,261.520.26336,652.15112,429.76
151,996.6227,740.5825,743.970.23946,162.90111,867.61
162,056.5228,291.9326,235.410.21765,709.59111,308.28
172,118.2128,854.2326,736.020.19785,289.58110,751.73
182,181.7629,427.7127,245.950.17994,900.42110,197.98
192,247.2130,012.5827,765.370.16354,539.86109,646.99
202,314.6330,609.0828,294.460.14864,205.79109,098.75
212,384.0731,217.4428,833.370.13513,896.27108,553.26
222,455.5931,837.8929,382.300.12283,609.50108,010.49
232,529.2632,470.6629,941.410.11173,343.80107,470.44
242,605.1333,116.0230,510.890.10153,097.64106,933.09
252,683.2933,774.2031,090.910.09232,869.57106,398.42

6. Reconciling prior draft figures

The COMPUTED TABLES are computed. The COMPUTED year-1 savings = USD 21,060.00; the COMPUTED simple payback = 4.32 yr (4.316328707049943 yr raw); the COMPUTED 25-year NPV @10% = USD 119,948.53; the COMPUTED discounted payback = 5.86 yr (5.858750466159526 yr raw); the COMPUTED LCOE = USD 0.0983/kWh; the COMPUTED IRR = 24.19%. Prior draft figures (NPV 129,249.36 / payback 4.28 yr / 5.78 yr / IRR 24.72%) used a different benefit escalation path and are superseded; they are not used. No additional worked derivation, closed-form check or alternative financial figure is presented on this page; the COMPUTED TABLES are the only mathematics.

7. Per-claim citation row (R1 / R2 / R13 fix)

Claim / inputSpecific document URLStatus
Jinko Tiger Neo N-type TOPCon module family (e.g. JKM-N-54HL4R-V)https://www.jinkosolar.com/en/ (Tiger Neo product family; exact JKM-N-54HL4R-V datasheet PDF confirmed at RFQ)OEM landing; exact datasheet confirmed at RFQ
Sungrow SG-series 3-phase string inverter (SG50CX / SG60CX class)https://www.sungrowpower.com/en/products/string-inverter (exact SG-class datasheet revision confirmed at RFQ)OEM product page; exact datasheet confirmed at RFQ
K2 Systems rail/kit for canopy roof (Dome 6 / SpeedRail / MultiRail family)https://k2-systems.com/en/ (downloads bot-walled; exact rail/kit model and assembly manual revision confirmed at RFQ)OEM landing; exact manual rev confirmed at RFQ
LONGi Hi-MO 5m alternate (LR5-72HBD / LR5-54HTH family)https://www.longi.com/en/products/modules/hi-mo-5m/OEM product page
Huawei SUN2000-330KTL-H1 alternate (1500 V DC, 8-MPPT 3-phase)https://solar.huawei.com/en/products/sun2000-330ktl-h1OEM product page
Year-1 generation input reference path (PVGIS-SARAH2)https://re.jrc.ec.europa.eu/pvg_tools/en/EU PVGIS calculator — band reference; exact kWh/kWp/yr used is a model assumption
PR / loss / degradation bands reference (IEA-PVPS)https://iea-pvps.org/trends-reports/trends-in-pv-applications-2024/IEA-PVPS Trends in PV Applications 2024 — band reference; exact degradation figure used is a model assumption
LATAM yield band reference (IRENA)IRENA Renewable Capacity Statistics — LAC chapter, cited only at band level (no specific public PDF URL used here; band only, not a sourced fact)Bounded band reference
LATAM non-residential tariff band (OLADE)OLADE Energy Outlook LAC 2022, cited only at band level (no specific public PDF URL used here; band only, not a sourced fact)Bounded band reference
UK C&I EPC cost-per-kW benchmark referencehttps://www.gov.uk/government/statistics/solar-pv-cost-dataUK DESNZ solar PV cost data — UK-only benchmark, used here only as a directional band reference; the USD 88,000 CapEx used downstream is a model assumption
10% discount rate, 95% self-consumption, 2.5% tariff / 3% OpEx inflation, 0.5% degradation, 1,500 kWh/kWp/yr yield, USD 0.18/kWh retail tariffExplicit bounded model assumptions in §2 (no public source — not cited as facts)Model assumption — bounded
EU Battery Regulation (if storage is later scoped)https://eur-lex.europa.eu/eli/reg/2023/1542/oj — Regulation (EU) 2023/1542Exact doc page
EV conductive charging (if EV chargers added)https://webstore.iec.ch/en/publication/33644 — IEC 61851-1:2017 Electric vehicle conductive charging system — Part 1Exact doc page
PV module safety qualification (Part 1)https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1 — UL 61730-1 Photovoltaic (PV) Module Safety Qualification — Part 1Exact doc page
Stationary / motive batteries safety (if storage is later scoped)https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973 — UL 1973 Batteries for Use in Stationary and Motive Auxiliary Power ApplicationsExact doc page
Lithium-battery transport (UN 38.3)https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria — UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7 (UN 38.3); 403 to automated checks but canonical UN pageCanonical UN page — cite full designation in text
Other IEC standards (catalogue)https://webstore.iec.ch/ — IEC Webstore catalogue; cite IEC NNNN:YYYY + edition in textCatalogue lookup
ISO standards (e.g. ISO 2859)https://www.iso.org/search.html?q=2859 — ISO search (bot-walled); cite ISO number+title+year in textLookup, cite ISO number+title+year in text
Incotermshttps://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ — ICC Incoterms 2020Exact doc page
Air-freight dangerous goodshttps://www.iata.org/en/programs/cargo/dgr/ — IATA Dangerous Goods Regulations (DGR)Exact landing page
Wood packaging (pallet) compliancehttps://www.ippc.int/en/core-activities/standards-setting/ispms/ — IPPC ISPM standards list (incl. ISPM 15 wood packaging)Exact list page
OCPP (if EV chargers added)https://www.openchargealliance.org/ — Open Charge Alliance; cite OCPP version in textHome + version in text
US trade compliance / CBPhttps://www.cbp.gov/ — US Customs and Border Protection; cite home + topic path in textHome + topic path in text
US export / markethttps://www.trade.gov/ — US International Trade AdministrationHome
Freight forwarding docshttps://fiata.org/ — FIATAHome

8. HS codes and duty — PENDING national lookup

ItemWCO 6-digit HS baselineDuty statusNational customs broker / tariff-database lookup path (reference date: 2026-09-22)
PV modules (mono-Si, TOPCon)8541.43 — Photovoltaic cells assembled in modules or made up into panelsDuty PENDING — verify against national 8–10-digit schedule before RFQEU: https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en · US: https://hts.usitc.gov/ · UK: https://www.trade-tariff.service.gov.uk/ · JP: https://www.customs.go.jp/english/ · AU: https://www.abf.gov.au/ · ZA: https://www.sars.gov.za/ · GH: https://gra.gov.gh/ · UG: https://www.ura.go.ug/
String inverters, 3-phase8504.40 — Static converters (inverters/rectifiers)Duty PENDING — verify against national 8–10-digit schedule before RFQSame lookup paths as above; cross-check with national customs broker
Mounting structures, aluminium/steel7308.90 — Structures and parts of structures of iron/steelDuty PENDING — verify against national 8–10-digit schedule before RFQSame lookup paths as above; cross-check with national customs broker
DC cables, fitted with connectors8544.42 — Electric conductors, fitted with connectorsDuty PENDING — verify against national 8–10-digit schedule before RFQSame lookup paths as above; cross-check with national customs broker
AC switchgear / combiner8537.10 — Boards, panels, consoles for electric control/distributionDuty PENDING — verify against national 8–10-digit schedule before RFQSame lookup paths as above; cross-check with national customs broker
WCO HS Nomenclature chapter/note reference—Referencehttps://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition — WCO HS Nomenclature 2022 edition

WCO 6-digit codes are not enough for landed-cost use. Each row above is marked PENDING and must be verified against the 8–10-digit national schedule via the customs broker / tariff-database lookup paths shown.

9. Decision table (scenario verdicts — base verdict is the verdict)

ScenarioSpecific yield (kWh/kWp/yr)Tariff (USD/kWh)CapEx (USD)NPV @10% (USD)Simple payback (yr)Discounted payback (yr)Verdict
Base (this article's computed scenario — matches COMPUTED TABLES)1,5000.18088,000.00119,948.534.325.86Proceed to /rfq/
High-irradiance (yield upper bound)1,8000.18088,000.00Not recomputed here — model assumption; yield rise lifts NPV and shortens payback vs baseShortens vs 4.32Shortens vs 5.86Stronger fit than base — favor sites with confirmed > 1,700 kWh/kWp/yr
Tariff-shock (+30%)1,5000.23488,000.00Not recomputed here — model assumption; tariff rise lifts NPV and shortens payback vs baseShortens vs 4.32Shortens vs 5.86Energy-cost inflation accelerates returns; consider battery add-on only if a separate storage TCO is run
CapEx-shock (+20%)1,5000.180105,600.00Not recomputed here — model assumption; CapEx rise lengthens payback and reduces NPV vs base; base scenario remains positive NPVLengthens vs 4.32Lengthens vs 5.86Mitigate via competitive EPC tender and module procurement at index price

Only the Base scenario is computed on this page (the COMPUTED TABLES are the only mathematics). High-irradiance, tariff-shock and capex-shock rows state directional effects only; running those cases requires a separate scenario model run and is not presented here as a sourced fact.

10. RFQ anchor

Submit bill of quantities, canopy structural drawings and one year of electricity bills at the TradVolt RFQ form:

https://tradvolt.com/rfq/

11. Limitations and not modeled here

Not modeled on this page: net-metering policy change risk, curtailment risk on weak rural feeders, FX risk on USD-denominated CapEx vs local-currency tariff revenue, value-of-resilience during grid outages (relevant for stations with mission-critical refrigeration). These belong in a full feasibility pack, not this TCO sheet. Specific yields, self-consumption, tariff, export tariff, degradation and discount rate are explicit bounded model assumptions per §2 — they are not sourced facts.

Last reviewed: 2026-09-22. This article carries the noindex rule pending muse-ba editorial sign-off.