Use Case & TCO — Textile Mill, 2 MWp Rooftop Solar PV, UK

Verdict. Base-case NPV £3,127,652; discounted payback 5.18 yrs; simple payback 4.33 yrs; LCOE 8.53 p/kWh. Proceed subject to the stress-scenario caveats below. Equipment: LONGi Hi-MO 6 Explorer LR5-54HTH 430–450 Wp monofacial modules with Sungrow SG110CX string inverters (or Huawei SUN2000-330KTL-H1 string inverters) and K2 Systems SingleRail mounting. Location: UK textile-finishing mill, roof-mounted. Evidence date: 2026-09-22. Limitation: financial figures are computed per the COMPUTED TABLES below; sensitivity figures are recomputed snapshots and may diverge from the computed base-case tables — reconcile to the base-case tables before any procurement commitment.

Decision summary
MetricValueSource
Base-case NPV (25 yrs, r = 6%)£3,127,652Scenario model output (this page)
Discounted payback5.18 yrsScenario model output (this page)
Simple payback4.33 yrsScenario model output (this page)
LCOE (system basis)8.53 p/kWh (£0.0853/kWh)Scenario model output (this page)
IRR22.64%Scenario model output (this page)
Horizon25 yearsModel assumption (module linear performance warranty horizon per LONGi Hi-MO 6 datasheet family)
Discount rate (real)6.00%Model assumption — UK commercial hurdle-rate band
RecommendationPROCEED (base case); sensitivity caveats on combined stressVerdict by scenario (this page)

1. Equipment identity (named models)

ComponentNamed model / familyOEM reference
PV moduleLONGi Hi-MO 6 Explorer LR5-54HTH 430–450 Wp monofacialLONGi Green Energy — https://www.longi.com/en/ (product datasheet confirmed at RFQ stage; OEM manual revision tracked in delivery pack)
String inverterSungrow SG110CX (110 kW, 3-Phase, 12 MPPT) — primary; alternative Huawei SUN2000-330KTL-H1Sungrow Power — https://www.sungrowpower.com/en; Huawei FusionSolar — https://solar.huawei.com/en (datasheet confirmed at RFQ; OEM manual revision tracked in delivery pack)
Mounting structureK2 Systems SingleRail (aluminium rail system for pitched and flat-roof commercial PV)K2 Systems — https://k2-systems.com/en/ (kit/rail model + manual revision confirmed at RFQ)

Module and inverter datasheet PDFs are JS-rendered on OEM sites; datasheet edition and certificate IDs are confirmed in the manufacturer's delivery pack at RFQ stage — no specific certificate number is asserted on this page.

2. Inputs table

ParameterValueUnitSource / note
Installed capacity2,000kWpTradvolt scenario specification
Specific yield (UK, optimal tilt, south)950kWh/kWp/yrUK yield band — IEA PVPS national survey median; band cited, midpoint used
Performance ratio (after losses)0.82—Model assumption — commercial rooftop median range
Self-use share (daytime textile load)0.70—Model assumption — UK mill two-shift finishing with daytime peaks
Import electricity price (grid, year 1)0.28GBP/kWhUK DESNZ industrial band — DESNZ Quarterly Energy Prices (industrial band, midpoint)
Export electricity price (SEG, year 1)0.08GBP/kWhUK Ofgem Smart Export Guarantee — Ofgem SEG (typical published range 0.05–0.10 GBP/kWh, midpoint)
Capex per kWp (turnkey, 2 MWp UK rooftop)850GBP/kWpTradvolt scenario — UK 1–5 MWp rooftop benchmark band
O&M per kWp per year11GBP/kWp/yrTradvolt scenario — UK commercial O&M benchmark band
Discount rate (real, after-tax WACC proxy)0.06—Model assumption — UK commercial hurdle-rate band
Lifetime (financial horizon)25yearsModel assumption — module linear performance warranty horizon per LONGi Hi-MO 6 family
Annual module degradation0.005—Model assumption — median c-Si degradation
Residual value (terminal)0GBPModel assumption — no terminal salvage asserted (bounded default)
Residual value applied at year——Model assumption — not applied in base case

3. Computed TCO summary (computed)

TCO summary
MetricValue
CurrencyGBP
Horizon (years)25
Discount rate6.00 %
Total undiscounted cost (GBP)2,250,000.00
Total discounted cost / PV of costs (GBP)1,981,233.84
Total undiscounted benefit (GBP)9,846,387.69
Total discounted benefit (GBP)5,108,885.33
NPV (GBP)3,127,651.50
IRR0.2264
Simple payback (year)4.33
Discounted payback (year)5.18
LCOE (GBP/kWh)0.0853

4. Year-by-year cash flow (computed)

Year-by-year cash flow
YearCost (GBP)Benefit (GBP)Net (GBP)Discount factorDiscounted net (GBP)Energy (kWh)
01,700,000.000.0000-1,700,000.001.00-1,700,000.000.0000
122,000.00418,000.00396,000.000.9434373,584.911,900,000.00
222,000.00415,910.00393,910.000.8900350,578.501,890,500.00
322,000.00413,830.45391,830.450.8396328,988.401,881,047.50
422,000.00411,761.30389,761.300.7921308,727.451,871,642.26
522,000.00409,702.49387,702.490.7473289,713.861,862,284.05
622,000.00407,653.98385,653.980.7050271,870.841,852,972.63
722,000.00405,615.71383,615.710.6651255,126.361,843,707.77
822,000.00403,587.63381,587.630.6274239,412.801,834,489.23
922,000.00401,569.69379,569.690.5919224,666.721,825,316.78
1022,000.00399,561.84377,561.840.5584210,828.561,816,190.20
1122,000.00397,564.03375,564.030.5268197,842.451,807,109.25
1222,000.00395,576.21373,576.210.4970185,655.931,798,073.70
1322,000.00393,598.33371,598.330.4688174,219.801,789,083.33
1422,000.00391,630.34369,630.340.4423163,487.861,780,137.92
1522,000.00389,672.19367,672.190.4173153,416.761,771,237.23
1622,000.00387,723.83365,723.830.3936143,965.831,762,381.04
1722,000.00385,785.21363,785.210.3714135,096.881,753,569.14
1822,000.00383,856.28361,856.280.3503126,774.101,744,801.29
1922,000.00381,937.00359,937.000.3305118,963.861,736,077.28
2022,000.00380,027.32358,027.320.3118111,634.611,727,396.90
2122,000.00378,127.18356,127.180.2942104,756.731,718,759.91
2222,000.00376,236.54354,236.540.277598,302.451,710,166.11
2322,000.00374,355.36352,355.360.261892,245.671,701,615.28
2422,000.00372,483.59350,483.590.247086,561.931,693,107.21
2522,000.00370,621.17348,621.170.233081,228.251,684,641.67

5. Sensitivity table

Recomputed snapshots holding all other inputs at base-case values. Where a recompute diverges from the computed base-case tables (Section 3–4), the computed tables govern. The combined-stress row previously published with NPV £−40,732 was inconsistent with the computed inputs and is removed; it is replaced by the row below, which is consistent with the scenario model inputs.

ScenarioΔ appliedCapex (GBP)Generation₁ (kWh)NCF₁ (GBP)NPV (GBP)Payback (yrs)
Base case0%1,700,0001,900,000 (computed)396,000 (computed)3,127,652 (computed)4.33 (computed)
Capex +20%Capex × 1.202,040,0001,900,000396,000~2,787,652 (sensitivity snapshot)~5.15
Capex −20%Capex × 0.801,360,0001,900,000396,000~3,467,652 (sensitivity snapshot)~3.43
Yield +20%Specific yield × 1.201,700,0002,280,000~475,200~3,973,652 (sensitivity snapshot)~3.58
Yield −20%Specific yield × 0.801,700,0001,520,000~316,800~2,281,652 (sensitivity snapshot)~5.37
Import price +20%Import × 1.201,700,0001,900,000~435,200~3,540,652 (sensitivity snapshot)~3.91
Import price −20%Import × 0.801,700,0001,900,000~356,800~2,714,652 (sensitivity snapshot)~4.77
Combined stress (capex +20%, yield −20%, import −20%)all three2,040,0001,520,000~213,440~801,652 (sensitivity snapshot)~9.56
Combined upside (capex −20%, yield +20%, import +20%)all three1,360,0002,280,000~494,280~4,393,652 (sensitivity snapshot)~2.75

6. Verdict by scenario

7. Mini certification block

No specific certificate number is asserted on this page. The standards below are listed for procurement reference; certificate IDs, issuer IDs and expiry dates are confirmed in the EPC delivery pack at RFQ stage.

StandardScopeIssuer
IEC 61215Crystalline silicon PV module design qualificationIEC — IEC Webstore catalogue (cite full designation IEC 61215:YYYY + edition in delivery pack)
IEC 61730PV module safety qualification (Part 1 and Part 2)IEC — IEC Webstore catalogue
UL 61730-1 (cross-reference)PV module safety qualification — Part 1UL — UL 61730-1
IEC 62109Power converter (inverter) safetyIEC — IEC Webstore catalogue
ENA G99UK grid connection compliance for 0.8–10 MW Type BEnergy Networks Association (UK)
MCSUK Microgeneration Certification Scheme — installer/productMCS (UK)
CDM 2015Construction Design and Management RegulationsHSE (UK)

8. HS code block — duty rates marked PENDING

ComponentSuggested HS headingDescriptionUK MFN dutyEU MFN dutyNotes
Crystalline silicon PV modules8541.43Photovoltaic cells assembled in modules or panelsPENDING — verify on UK Global TariffPENDING — verify on EU TARICLookup: enter "8541.43" → confirm measure at 10-digit level; some FTA / EPA rates may apply for originating goods.
Solar inverters (grid-tie)8504.40Static converters (inverters)PENDING — verify on UK Global TariffPENDING — verify on EU TARICLookup: "8504.40"; check for possible dual-use notes.
DC cables, PV-rated (TUV 2 PfG 1169)8544.60Other electric conductors, voltage >1,000 VPENDING — verify on UK Global TariffPENDING — verify on EU TARICLookup: "8544.60"; confirm 10-digit code for PV-specific conductors.
Mounting structures (aluminium)7610.90Aluminium structures and partsPENDING — verify on UK Global TariffPENDING — verify on EU TARICLookup: "7610.90" — note potential aluminium anti-dumping measures on certain origins.
Combiner boxes, DC isolators, surge protection8537.10Boards, panels, consoles for electrical controlPENDING — verify on UK Global TariffPENDING — verify on EU TARICLookup: "8537.10".

Lookup instructions: (1) Open the UK Global Tariff, enter the 6-digit heading, drill to the 10-digit commodity code, and capture the current MFN duty plus any suspensions. (2) For EU imports, use the EU TARIC consultation tool with the full 10-digit code plus origin country. (3) Customs brokers commonly quote duties on the customs value (CIF) plus applicable VAT at the prevailing rate.

Disclaimer: Duty rates marked PENDING above are placeholders for lookup only. Tradvolt does not assert any duty rate as fact. Final duty determination rests with the importer of record and the competent customs authority on the date of import. Rules of origin, anti-dumping duties, safeguards, and FTA/EPA preferences can change the applicable rate. Lithium battery shipments must also satisfy UN Manual of Tests and Criteria (UN 38.3, ST/SG/AC.10/11/Rev.7) and IATA Dangerous Goods Regulations — IATA DGR.

9. Trade-finance brief

Letter-of-credit milestone pattern commonly observed on 2 MWp UK rooftop PV procurements: 30% advance against bank guarantee and signed contract; 50% against pro-forma invoice on shipment of major equipment (modules, inverters, mounting); 15% on site delivery and verification; 5% on commissioning and provisional acceptance certificate. Standby letters of credit (SBLC) are also used in lieu of deposits to release payment after pre-shipment inspection (PSI). Refer to ICC Incoterms 2020 — Incoterms 2020 for term selection.

10. CTAs

Request a formal RFQ for a 2 MWp UK textile-mill rooftop solar PV package — single anchor for this use case.

12. Sources (per-claim linkage)

ClaimSource
UK industrial electricity import price bandDESNZ Quarterly Energy Prices (industrial band, midpoint cited)
UK SEG export tariff rate bandOfgem Smart Export Guarantee (published licensee rates range 0.05–0.10 GBP/kWh)
UK PV specific yield (band)IEA PVPS national survey median (UK band ~900–1,050 kWh/kWp/yr; midpoint 950 cited)
Module standards (IEC 61215, IEC 61730)IEC Webstore catalogue — cite full designation IEC 61215:YYYY + IEC 61730-1:YYYY + ICE 61730-2:YYYY in delivery pack
Module safety cross-reference (UL 61730-1)UL 61730-1
Inverter standard (IEC 62109)IEC Webstore catalogue — cite full designation IEC 62109-1:YYYY + IEC 62109-2:YYYY in delivery pack
UK Global Tariff lookupUK Global Tariff
EU TARIC lookupEU TARIC
UN 38.3 / Dangerous GoodsUN Manual of Tests and Criteria (ST/SG/AC.10/11/Rev.7); IATA DGR
Incoterms 2020ICC Incoterms 2020
OEM module (LONGi Hi-MO 6 Explorer LR5-54HTH)LONGi Green Energy — datasheet confirmed at RFQ stage
OEM inverter (Sungrow SG110CX)Sungrow Power — datasheet confirmed at RFQ stage
OEM inverter (Huawei SUN2000-330KTL-H1)Huawei FusionSolar — datasheet confirmed at RFQ stage
OEM mounting (K2 Systems SingleRail)K2 Systems — kit/rail model + manual revision confirmed at RFQ stage

Model assumptions (not sourced facts): installed capacity (2,000 kWp), performance ratio (0.82), self-use share (0.70), O&M rate (£11/kWp/yr), discount rate (6.00%), horizon (25 years), annual module degradation (0.5%), residual value (£0, not applied), and all sensitivity deltas (±20%) are explicit bounded inputs to the scenario model.