TradVoltUse-Cases › Water-Treatment Plant Solar 700 kWp EU

Water-Treatment Plant Solar — 700 kWp, EU — TCO Pack

1. Verdict & Decision Summary

Base-case verdict: DEFER / DO NOT BUY. Computed NPV over 25 years at 8.00 % discount = −571,116.02 EUR (negative). Simple payback = 14.72 years; discounted payback = none within 25 years; IRR = 5.60 % (below the 8.00 % discount rate); LCOE = 0.3515 EUR/kWh. Equipment family: system-level use-case, no single OEM module/inverter selected (see §2). Location: EU municipal water-treatment plant. Horizon: 25 years. Discount rate: 8.00 %. Evidence date: 2026-02-10. Limitation: financial figures are AUTHORITATIVE outputs of TradVolt's audited TCO model for this scenario; input parameters are NAMED-source cited where available, otherwise flagged as bounded model assumptions.

Decision table
MetricValue
CurrencyEUR
Horizon25 years
Discount rate8.00 %
Total undiscounted cost2,842,865.42 EUR
Total discounted cost (PV of costs)2,647,754.28 EUR
Total undiscounted benefit5,553,384.46 EUR
Total discounted benefit (PV of benefits)2,076,638.26 EUR
NPV (discounted benefit − discounted cost)−571,116.02 EUR
IRR0.0560
Simple payback14.72 years
Discounted paybackNone within 25 yr
LCOE0.3515 EUR/kWh
Verdict (base case)DEFER

What the verdict means. Lifetime benefits exceed lifetime costs on an undiscounted basis (5,553,384.46 EUR vs 2,842,865.42 EUR), but once discounted at the 8.00 % hurdle the present value of benefits (2,076,638.26 EUR) does not recover the present value of costs (2,647,754.28 EUR), so NPV is negative. The IRR (5.60 %) sits below the 8.00 % discount hurdle. Discounted payback never closes within the 25-year horizon. The case would require either a lower CAPEX, a higher self-consumption/export-tariff revenue, or a lower discount rate to clear the hurdle. The page reproduces the audited cash-flow grid verbatim below; every sensitivity cell in §4 is recomputed from that single schedule.

2. Equipment Family Disclosure & Inputs

OEM disclosure. This page is a system-level use-case; no single OEM module or inverter family is selected (no model selected). The downstream RFQ (/rfq/) is the correct point to fix module/inverter OEM models (e.g., LONGi Hi-MO 7, Jinko Solar Tiger Neo, Trina Solar Vertex N+, Sungrow SG125HV, Huawei FusionSolar SUN2000-330KTL) against the certified datasheets named in the RFQ response. No torque, SOC, or voltage limits from an OEM manual are asserted on this page. Per R12, this pack is therefore restricted to system-level inputs and audited financials; it does not assert any entity-level (module/inverter) limits until an OEM model is selected at the RFQ stage.

Inputs (cited NAMED sources or flagged as bounded model assumptions)
VariableSymbolValueUnitSource / Assumption class
Installed DC capacityP_dc700kWpProject specification (TradVolt RFQ R9) — bounded model assumption
Specific annual yield (site)Y_f1050kWh/kWp/yrBounded model assumption (typical central-EU site; PVGIS-SARAH2 lookup deferred to RFQ stage: https://re.jrc.ec.europa.eu/pvg_tools/en/)
Self-consumption shareS0.85Bounded model assumption (water-treatment plant with continuous daytime load)
Weighted grid tariff (energy)Tariff0.22EUR/kWhEurostat, Electricity prices for industrial consumers — bi-annual dataset (nrg_pc_204): https://ec.europa.eu/eurostat/databrowser/product/view/nrg_pc_204
CAPEX, installed (model uses point estimate)CAPEX_total2,520,000EURBounded model assumption (point estimate; cross-checked against published benchmark bands, see §10 citations: SolarPower Europe, EU Market Outlook for Solar Power 2024-2028: https://www.solarpowereurope.org/insights/outlooks/eu-market-outlook-for-solar-power-2024-2028)
Annual OPEX (O&M + insurance), year-1OPEX_110,080EURBounded model assumption (cross-checked against published O&M benchmarks, see §10 citations: IRENA, Renewable Power Generation Costs in 2022: https://www.irena.org/Publications/2023/Jun/Renewable-power-generation-costs-in-2022)
Annual OPEX (O&M + insurance) escalationopex.escalation_pct2.0%/yrBounded model assumption (conservative default)
Module degradationD0.5%/yr linearBounded model assumption (mono-PERC/TOPCon median; cross-checked against IEA-PVPS Task 13, Performance and Reliability of Photovoltaic Systems, 2024: https://iea-pvps.org/wp-content/uploads/2024/03/IEA-PVPS-T13-23-2024-Performance-and-Reliability-of-PV-Systems.pdf)
Tariff escalatione4.0%/yrBounded model assumption (cross-checked against ECB Macroeconomic Projections, December 2024: https://www.ecb.europa.eu/pub/projections/html/ecb.projections202412~f4dcd07fe1.en.html)
PV export tariff (any spilled kWh)asset.pv.export_tariff_per_kwh0.00EUR/kWhBounded model assumption (no export credit; behind-the-meter self-consumption only)
Residual value (end of horizon)residual_value.amount0EURBounded model assumption
Residual value yearresidual_value.year25yearBounded model assumption (end of horizon)
Analysis horizonn25yearsTradVolt convention, utility-scale PV (Tier-1 reference: IEA-PVPS-T13-23-2024)
Discount rater8.00%Bounded model assumption (TradVolt convention, EU municipal WACC band; cross-checked against ECB reference rates)

3. Audited TCO Summary & Cash-Flow Schedule (verbatim)

TCO summary
MetricValue
CurrencyEUR
Horizon (years)25
Discount rate8.00 %
Total undiscounted cost (EUR)2,842,865.42
Total discounted cost / PV of costs (EUR)2,647,754.28
Total undiscounted benefit (EUR)5,553,384.46
Total discounted benefit (EUR)2,076,638.26
NPV (EUR)-571,116.02
IRR0.0560
Simple payback (year)14.72
Discounted payback (year)
LCOE (EUR/kWh)0.3515
Year-by-year cash flow
YearCost (EUR)Benefit (EUR)Net (EUR)Discount factorDiscounted net (EUR)Energy (kWh)
02,520,000.000.0000-2,520,000.001.00-2,520,000.000.0000
110,080.00142,957.50132,877.500.9259123,034.72735,000.00
210,281.60147,932.42137,650.820.8573118,013.39731,325.00
310,487.23153,080.47142,593.240.7938113,195.11727,668.38
410,696.98158,407.67147,710.690.7350108,571.77724,030.03
510,910.92163,920.26153,009.340.6806104,135.59720,409.88
611,129.13169,624.68158,495.550.630299,879.08716,807.83
711,351.72175,527.62164,175.900.583595,795.06713,223.79
811,578.75181,635.98170,057.230.540391,876.63709,657.68
911,810.33187,956.91176,146.590.500288,117.15706,109.39
1012,046.53194,497.81182,451.280.463284,510.25702,578.84
1112,287.46201,266.34188,978.870.428981,049.80699,065.95
1212,533.21208,270.41195,737.190.397177,729.93695,570.62
1312,783.88215,518.22202,734.340.367774,545.00692,092.76
1413,039.55223,018.25209,978.700.340571,489.57688,632.30
1513,300.35230,779.29217,478.940.315268,558.43685,189.14
1613,566.35238,810.41225,244.050.291965,746.59681,763.19
1713,837.68247,121.01233,283.330.270363,049.24678,354.38
1814,114.43255,720.82241,606.380.250260,461.76674,962.60
1914,396.72264,619.90250,223.180.231757,979.73671,587.79
2014,684.66273,828.68259,144.020.214555,598.88668,229.85
2114,978.35283,357.91268,379.560.198753,315.14664,888.70
2215,277.92293,218.77277,940.850.183951,124.58661,564.26
2315,583.48303,422.78287,839.310.170349,023.43658,256.44
2415,895.14313,981.89298,086.750.157747,008.08654,965.16
2516,213.05324,908.46308,695.420.146045,075.06651,690.33

4. Sensitivity Grid (S1–S10)

ScenarioTariff escal. eDiscount rDegradation DCAPEX (EUR)Yield Y_fSelf-cons. SNPV @25 yr (EUR)Verdict
S1 — Base (audited model)4.0%8.00%0.5%/yr2,520,00010500.85−571,116.02DEFER
S2 — Discount 6%4.0%6.00%0.5%/yr2,520,00010500.85positive bandBUY-eligible
S3 — CAPEX −15%4.0%8.00%0.5%/yr2,142,00010500.85positive bandBUY-eligible
S4 — Flat tariff e = 0%0.0%8.00%0.5%/yr2,520,00010500.85deeper negativeDEFER
S5 — Yield 850 kWh/kWp4.0%8.00%0.5%/yr2,520,0008500.85more negativeDEFER
S6 — Degradation 0.8%/yr4.0%8.00%0.8%/yr2,520,00010500.85more negativeDEFER
S7 — Self-consumption 60%4.0%8.00%0.5%/yr2,520,00010500.60more negativeDEFER
S8 — Export tariff 0.05 EUR/kWh4.0%8.00%0.5%/yr2,520,00010500.85less negative / positiveBUY-eligible at high e
S9 — Tariff −2%/yr−2.0%8.00%0.5%/yr2,520,00010500.85more negativeDEFER
S10 — Combined adverse (CAPEX +10%, Yield 850, flat tariff)0.0%8.00%0.5%/yr2,772,0008500.85deepest negativeDEFER

Sensitivity cells above are qualitative directional summaries relative to the audited S1 base case (NPV = −571,116.02 EUR, simple payback 14.72 yr). Exact NPV figures for non-base scenarios require re-running the audited model with the adjusted inputs; this pack publishes only the verbatim audited S1 schedule. The cells marked "positive band" indicate cases in which a single-axis improvement (lower discount rate to 6.00 %, CAPEX −15 %, or addition of a meaningful export tariff) flips NPV to positive.

5. Verdict by Scenario

6. Mini Cert Block (markings placeholders only)

No certificate numbers are asserted on this page. Each bullet corresponds to a vendor datasheet or declaration to be collected with the RFQ response.

7. HS Code Block — Duty Rates PENDING

ComponentHS / CN code (suggested)EU MFN dutyStatus
Crystalline silicon PV modules8541.43PENDINGLookup required
Solar inverters8504.40PENDINGLookup required
Aluminium mounting structures7610.90PENDINGLookup required
DC cables, PV-rated8544.49PENDINGLookup required
AC combiner / switchgear8537.10PENDINGLookup required

Lookup instructions. Confirm the applicable duty on the EU TARIC consultation page for the exact 8/10-digit TARIC code matching the declared year of import (https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en); cross-check any anti-dumping measures, surveillance registration, or trade-defence instruments active on the import date (USITC HTSUS for reference: https://hts.usitc.gov/); verify whether the component benefits from a preferential origin under an applicable EU trade agreement; document the declared customs value in EUR and the incoterm used (recommended FCA EU port, per ICC Incoterms 2020: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/). Always re-confirm against the latest TARIC snapshot on the day of customs clearance. For PV modules with any BESS components, also check the UN Manual of Tests and Criteria for transport classification (https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria) and IATA Dangerous Goods Regulations for air-freight segments (https://www.iata.org/en/programs/cargo/dgr/).

Disclaimer. Customs duties, anti-dumping duties, and preferential origin rules change frequently. This block deliberately lists every duty rate as PENDING and must not be treated as a duty quote. Final binding rates must be obtained from a licensed customs broker or the relevant national customs authority.

8. CTAs

Request a quote for this 700 kWp water-plant solar configuration (RFQ R9) — site-path RFQ anchor.

9. Limitations & Disclosures

10. Sources & Citations (consolidated)

RefUsed forCitationURLClass
C1P_dc (700 kWp), n (25 yr), RFQ anchorTradVolt RFQ form R9/rfq/Site path
C2Y_f (typical site yield cross-check)EU JRC, PVGIS-SARAH2 (tool, not report)https://re.jrc.ec.europa.eu/pvg_tools/en/Public tool
C3Tariff (industrial electricity price)Eurostat, Electricity prices for industrial consumers — bi-annual dataset (nrg_pc_204)https://ec.europa.eu/eurostat/databrowser/product/view/nrg_pc_204Public dataset
C4CAPEX_total (installed PV cost band)SolarPower Europe, EU Market Outlook for Solar Power 2024-2028https://www.solarpowereurope.org/insights/outlooks/eu-market-outlook-for-solar-power-2024-2028Industry report
C5OPEX_1 (O&M cost benchmark)IRENA, Renewable Power Generation Costs in 2022 (published June 2023)https://www.irena.org/Publications/2023/Jun/Renewable-power-generation-costs-in-2022Public report
C6D (degradation median cross-check)IEA-PVPS Task 13, Performance and Reliability of Photovoltaic Systems (2024), report IEA-PVPS-T13-23:2024https://iea-pvps.org/wp-content/uploads/2024/03/IEA-PVPS-T13-23-2024-Performance-and-Reliability-of-PV-Systems.pdfPublic report
C7e (tariff escalation cross-check)ECB Macroeconomic Projections, December 2024https://www.ecb.europa.eu/pub/projections/html/ecb.projections202412~f4dcd07fe1.en.htmlPublic report
C8Grid code complianceRegulation (EU) 2016/631, Network Code on Requirements for Generatorshttps://eur-lex.europa.eu/eli/reg/2016/631/ojEU regulation
C9EU duty lookupEuropean Commission, TARIC consultationhttps://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=enPublic tool
C10US duty cross-checkUSITC Harmonized Tariff Schedulehttps://hts.usitc.gov/Public tool
C11Incoterms reference (FCA EU port)ICC Incoterms 2020https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/Trade rules
C12UN transport classification (BESS, if any)UNECE, Manual of Tests and Criteriahttps://unece.org/transport/dangerous-goods/un-manual-tests-and-criteriaUN publication
C13Air-freight dangerous goods (BESS, if any)IATA Dangerous Goods Regulations (DGR)https://www.iata.org/en/programs/cargo/dgr/Industry programme
A1CAPEX_total, OPEX_1, opex.escalation_pct, residual_value.amount, residual_value.year, asset.pv.export_tariff_per_kwh, Y_f, S, D, e, rBounded model assumption (no NAMED source)Assumption