Site-acceptance SOP used by TradVolt to commission the fire-suppression subsystem on a vertical-rack LFP energy-storage system (Huawei LUNA2000-215 Series cabinet) being delivered China → Brazil. The FSS hardware reference architecture used to set acceptance limits is the Sungrow PowerTitan2.0 20-ft containerised ESS (liquid-cooled, 5 MWh class). This SOP governs the on-site steps, the document set to file, and the customs position for the equipment and parts.
PENDING — manual.
| Decision | Value | Source / caveat |
|---|---|---|
| In-scope ESS family | Huawei LUNA2000-215 Series (vertical-rack LFP) | Huawei product page (landing, model series confirmed at RFQ) |
| FSS reference architecture | Sungrow PowerTitan2.0 (2.5 MW / 5 MWh, 1500 V DC, liquid-cooled, 20-ft) | Sungrow product page |
| Delivery term | CIF Santos (Incoterms® 2020) | ICC Incoterms® 2020 rules page |
| Brazilian HS / duty lookup path | Siscomex Portal Único + Siscomex consulta tratamento (NCM) | Brazilian Siscomex portal pages |
| AQL sampling basis | ISO 2859-1 (sampling procedures by attributes) | ISO catalogue query page (cite designation in text) |
This SOP applies to a Huawei LUNA2000-215 Series vertical-rack LFP ESS cabinet fitted with a fixed fire-suppression subsystem (FSS). The FSS hardware reference architecture used to set acceptance limits is the Sungrow PowerTitan2.0 20-ft containerised ESS (5 MWh class, 1500 V DC, liquid-cooled). Shipment is on the China → Brazil corridor under CIF Santos (Incoterms® 2020); TradVolt owns commissioning at destination.
| Step # | Action | Owner | Input doc | Output doc | Done-when |
|---|---|---|---|---|---|
| 1 | Confirm chemistry (LFP), topology (vertical, Huawei LUNA2000-215), FSS in scope. | Project Manager (PM) | Sales contract | Scope memo (PDF) | Scope memo signed by PM and Site Lead. |
| 2 | Pull Huawei LUNA2000-215 service manual (revision recorded), FSS datasheet, FSS agent certification. | Site Lead | OEM service manual | Doc index sheet | All three documents present; manual revision noted. |
| 3 | Receive goods on site; pre-energise visual inspection. | Logistics Coordinator | Packing list, Bill of Lading | Goods Receipt Note (GRN) | GRN countersigned; no transit damage above threshold. |
| 4 | Mechanical & electrical pre-checks: torque, bus-bar torque, grounding, insulation resistance. | Commissioning Engineer | Huawei LUNA2000-215 service manual | Pre-check sheet (values) | Every torque and insulation value recorded against the manual's tolerance table. |
| 5 | FSS loop integrity test (detectors, actuators, abort/hold). | FSS Specialist | FSS component datasheet, Huawei service manual | FSS loop test sheet | Each loop passes continuity test; abort/hold operate as specified. |
| 6 | Pre-energise interlock verification (BMS ↔ FSS ↔ HVAC ↔ DC contactor). | Commissioning Engineer | Huawei service manual | Interlock matrix (filled) | All interlocks observed; DC contactor sequence matches manual. |
| 7 | AQL sampling inspection per ISO 2859-1 on critical safety items. | QC Inspector | AQL plan (linked) | AQL inspection report | Lot accepted or rejected against the chosen AQL level. |
| 8 | Function check with measured values: detectors, actuators, alarms, BMS shutdown chain. | Commissioning Engineer + FSS Specialist | OEM commissioning checklist | Function-test report | Every set vs. measured value within tolerance. |
| 9 | Logistics close-out for CN→BR: reconcile docs, customs filings (DI/DSIC), Incoterms® 2020 cost allocation. | Logistics Coordinator + Customs Broker | Commercial invoice, B/L, packing list, DI/DSIC | Customs clearance file | Clearance file closed; CIF Santos cost allocation signed. |
| 10 | Handover package compilation and filing under project ID. | Project Manager (PM) | All prior outputs | Handover package (ZIP) | Handover archived; OEM sign-off block completed. |
Filenames are literal; keep them in the project folder before step 3.
| Literal filename | Purpose | Produced at step |
|---|---|---|
01_scope_memo.pdf | Scope memo (LFP / vertical / Huawei LUNA2000-215 / FSS in scope). | 1 |
02_oem_doc_index.xlsx | Index of Huawei LUNA2000-215 service manual (rev.), FSS datasheet, agent certification. | 2 |
03_grn.pdf | Goods Receipt Note from on-site receipt. | 3 |
04_precheck_values.csv | Recorded torque, bus-bar torque, grounding, insulation values. | 4 |
05_fss_loop_test.csv | FSS loop integrity test results per loop. | 5 |
06_interlock_matrix.xlsx | Filled BMS ↔ FSS ↔ HVAC ↔ DC contactor matrix. | 6 |
07_aql_plan.xlsx | ISO 2859-1 AQL sampling plan and acceptance level. | 7 |
07_aql_report.pdf | AQL inspection report for the lot. | 7 |
08_function_test_report.pdf | Function check results with set/measured values. | 8 |
09_customs_clearance_file.zip | Commercial invoice, B/L, packing list, DI/DSIC, CIF Santos cost allocation. | 9 |
10_handover_package.zip | Full handover archive under project ID. | 10 |
| Step | Indicative duration | Depends on | Note |
|---|---|---|---|
| 1 — Scope memo | 0.5 h | — | Start once PO confirmed. |
| 2 — Doc index | 1 h | Step 1 | Huawei service manual revision recorded. |
| 3 — Receipt & visual | 2 h | Step 2, on-site delivery | Pre-energise gate. |
| 4 — Mechanical/electrical pre-checks | 3 h | Step 3 | Tools calibrated. |
| 5 — FSS loop integrity | 2 h | Step 4 | FSS Specialist present. |
| 6 — Interlock verification | 2 h | Steps 4–5 | BMS firmware matched to manual. |
| 7 — AQL sampling | 1.5 h | Step 3 | ISO 2859-1 plan linked before step 7. |
| 8 — Function check | 3 h | Steps 4–6 | Capture set vs. measured. |
| 9 — Logistics close-out | 2 h | Steps 3 and 8 | Customs broker engaged. |
| 10 — Handover | 1.5 h | Steps 1–9 | Filing under project ID. |
| Total | 18 h 30 min (indicative) | — | Split across one or two on-site days. |
| Item | HS / NCM code (lookup reference) | Applicable rate (BR import) | Source |
|---|---|---|---|
| LFP battery storage cabinets / BESS equipment (Huawei LUNA2000-215 cabinet hardware) | PENDING — lookup (commonly classified under NCM 8507.60 for Li-ion cells/packs; verify per item) |
PENDING — lookup | Brazil — Siscomex Portal Único (Receita Federal / Comex Stat) |
| Fire-suppression subsystem parts (control panel, detectors, actuators, agent cylinder) | PENDING — lookup (commonly 8424 for spraying/appliance machinery or 8537 for control panels; verify per item) |
PENDING — lookup | Brazil — Siscomex consulta tratamento |
| Tools, gauges and consumables shipped together | PENDING — lookup | PENDING — lookup | Brazil — Siscomex Portal Único |
Disclaimer. NCM codes, applicable duty rates, and any tax benefits (e.g., Reintegra, ex-tarifário) depend on the exact technical description of the goods and on current Brazilian customs/tax legislation. Lookups must run against the official Siscomex Portal Único and the Siscomex consulta_tratamento pages before each shipment; TradVolt does not provide legal or fiscal advice.
PENDING — lookup. Treat any number outside those pages as UNCERTAIN.
indicative — final figure depends on number of racks, FSS model, and on-site days; provided in the RFQ response.indicative; sourced against the Huawei LUNA2000-215 service manual parts list.indicative; CIF Santos (Incoterms® 2020) cost allocation itemised in the quote.UNCERTAIN until NCM classification is confirmed on the Siscomex Portal Único.UNCERTAIN — supplied on a per-RFQ basis from the manufacturer.The corridor combines a maritime leg (CN → BR) under CIF Santos (Incoterms® 2020) with a fixed-destination commissioning step. Under CIF, the seller contracts carriage and insurance to the named port of destination; commissioning at the Brazilian site is a separate service scope run by TradVolt and is not part of the Incoterms® 2020 cost allocation.
02_oem_doc_index.xlsx". Cabinet/rack ratings confirmed at RFQ.02_oem_doc_index.xlsx.62619; cite "IEC 62619:2022" verbatim — do not invent a /publication/ ID) | accessed 2026-09-22
62477-1; cite "IEC 62477-1:2022" verbatim — do not invent a /publication/ ID) | accessed 2026-09-22
PENDING — lookup.
Src: Siscomex Portal Único | URL: https://portalunico.siscomex.gov.br/portal/ · Siscomex consulta_tratamento | URL: https://siscomex.desenvolvimento.gov.br/tratamento/private/pages/consulta_tratamento.jsf | accessed 2026-09-22
02_oem_doc_index.xlsx; any value not appearing on a cited URL is marked PENDING — manual.