ESS PCS Grid-Fault Ride-Through Test — CN→BR Corridor (LFP, Vertical)

Verdict (first 100 words): This SOP delivers a 14-day, IEC 62933-5-2-based LVRT/HVRT acceptance test on Power Conversion System units arriving on the CN→BR corridor, with a documented release-or-quarantine decision by D+12. Equipment: Sungrow PowerTitan2.0 PCS (1500 V DC; -30 to 50 °C operating envelope) coupled with the Sungrow ST2752UX liquid-cooled LFP battery container (2752 kWh per unit, 1500 V DC). Horizon: D+0 arrival to D+14 client notification. Evidence-date: 2026-09-22. Limitation: HS code, ICMS, PIS/COFINS, and Siscomex duty rates are not hardcoded — they must be looked up at booking on the Brazil Siscomex portal. Model-specific torque, SOC window, and DC voltage limits below are taken from the OEM product page and must be re-confirmed against the shipment-specific Sungrow PowerTitan2.0 Service Manual revision attached at RFQ.

ItemValueSource / link
SOP horizon14 calendar days (D+0 → D+14)Internal TradVolt process design
Release decision dateD+12§4 timeline
Equipment familySungrow PowerTitan2.0 PCS + Sungrow ST2752UX LFP containerSungrow PowerTitan2.0 product page · Sungrow ST2752UX product page
Standard for ride-throughIEC 62933-5-2 (BESS safety — grid-integrated systems)IEC Webstore — cite designation IEC 62933-5-2 in full
Safety standardUL 9540 (Energy Storage Systems and Equipment)UL energy-storage certification scope
Sampling standardISO 2859-1:1999 (attribute sampling)ISO 2859 search — cite ISO 2859-1:1999 in full
Customs lookup (BR)Siscomex portalSiscomex Portal Único · Siscomex NCM enquiry
RFQ/rfq/TradVolt RFQ form

Request Quote — replies in 48h


1. Scope and Applicability

This procedure applies to Sungrow PowerTitan2.0 PCS units and associated Sungrow ST2752UX liquid-cooled LFP battery containers received under TradVolt's China-to-Brazil (CN→BR) corridor service. Sungrow PowerTitan2.0 is published as a 2.5 MW / 5 MWh PCS-coupled BESS in a 20-ft container, 1500 V DC, operating -30 to 50 °C [Src: Sungrow PowerTitan2.0 product page]. The ST2752UX battery container is published at 2752 kWh stored energy, 1500 V DC, operating -30 to 50 °C [Src: Sungrow ST2752UX product page].

It governs the on-arrival grid-fault ride-through acceptance test required before site commissioning in Brazil.

The procedure references the following allow-listed standards and documents only. Any local deviation must be filed as an addendum referenced against the same source.

Allow-list enforcement: No third-party blog, distributor marketing sheet, or unverified forum post may be cited as a source for any factual claim in this SOP. The Sungrow PowerTitan2.0 / ST2752UX OEM Service Manual revision (with firmware version, DC torque values, SOC window, and 1500 V DC insulation limits) is not yet attached; it must be supplied per shipment at the RFQ stage and re-attached to this SOP as an addendum before Step 4 begins.

2. Step Sequence

Step #ActionOwnerInput docOutput docDone-when
1Receive shipment, verify Incoterms® 2020 term, count PCS units and serial numbers against packing list.Logistics CoordinatorPacking list, Bill of Lading, Sungrow PowerTitan2.0 datasheetGoods Receipt Note (GRN-CNB-###)GRN signed, discrepancy = 0 unit; HS code field populated (see §6).
2Validate customs clearance documents (FIATA FCR / multimodal waybill); confirm Siscomex DU-E registration on the Siscomex Portal Único [Src: Siscomex Portal Único].Customs BrokerCommercial Invoice, FIATA FCR, GACC export declarationDespacho de Importação (DI) recordDI registered, tax IDs reconciled, no holds in Siscomex.
3Stage Sungrow PowerTitan2.0 PCS units in the test bay; pull the shipment-specific OEM Service Manual revision and firmware version (to be attached at RFQ stage).Workshop SupervisorSungrow PowerTitan2.0 Service Manual (per-shipment rev.), ST2752UX datasheet, GRNStaging SheetEach serial cross-referenced to its OEM manual revision page.
4Execute pre-test safety checklist: 1500 V DC isolation verification, AC isolation, lockout/tagout, PPE, earthing continuity, container spacing ≥ 15 cm per Sungrow PowerTitan2.0 published spec [Src: PowerTitan2.0].Safety OfficerUL 9540 isolation checklist, Sungrow Service ManualPre-Test Safety Sign-OffAll items checked; two-person sign-off recorded.
5Configure grid simulator to the LVRT / HVRT profiles defined in IEC 62933-5-2 and the Sungrow PowerTitan2.0 ride-through envelope (1500 V DC, max AC output 2520 kW) [Src: PowerTitan2.0].Test EngineerIEC 62933-5-2, Sungrow PowerTitan2.0 datasheetSimulator Profile SheetProfile time-voltage curve exported and saved as PDF.
6Execute LVRT and HVRT ride-through sequence at 1500 V DC; record DC bus behaviour, reactive current injection, and trip/hold status.Test EngineerSimulator Profile Sheet, Sungrow Service ManualRaw oscilloscope / DSO traces (.csv)Three consecutive successful runs per fault profile recorded.
7Compile test report, attach traces, obtain OEM-spec sign-off block.Quality EngineerRaw traces, Sungrow PowerTitan2.0 datasheetGrid-Fault Ride-Through Test Report (GF-RT-###)Report signed by Test Engineer, Safety Officer, and QA Lead.
8Apply ISO 2859-1:1999 attribute sampling on the lot; record AQL level used and lot size.Quality EngineerISO 2859-1:1999, Lot RegisterSampling Inspection RecordSample size, Ac/Re numbers, and disposition recorded.
9Archive the compliance pack (GRN, DI, Sungrow Service Manual, report, sampling record) to the project folder.Document ControllerAll upstream outputsArchived Compliance Pack (PDF + native)Checksum recorded; folder path logged in ERP.
10Release units for commissioning, or quarantine the lot if any step failed; raise NCR if quarantined.Operations ManagerCompliance Pack, NCR formRelease Note or NCR-###ERP status updated; client notified within 24 h.

3. Document Checklist (literal filenames)

Each shipment handled under this SOP must produce the following artefacts with the filename convention shown. Filenames are literal; do not abbreviate.

#FilenameOwnerFormat
D1GRN-CNB-{YYYYMMDD}-{Seq}.pdfLogistics CoordinatorPDF (signed scan)
D2DI-{ShipmentID}.pdfCustoms BrokerPDF (Siscomex export)
D3FCR-{ShipmentID}.pdfCustoms BrokerPDF (FIATA multimodal)
D4Sungrow-PowerTitan2.0-ServiceManual-{Rev}_{FWver}.pdfWorkshop SupervisorPDF (per-shipment OEM doc — datasheet to be attached at RFQ stage)
D5Sungrow-PowerTitan2.0-Datasheet.pdfWorkshop SupervisorPDF (per-shipment OEM doc)
D6PreTest-Safety-{YYYYMMDD}.pdfSafety OfficerPDF (signed)
D7Simulator-Profile-{ProfileID}.pdfTest EngineerPDF + .csv
D8GF-RT-Report-{Serial}.pdfQuality EngineerPDF + native
D9ISO2859-Sampling-{LotID}.xlsxQuality EngineerExcel
D10Compliance-Pack-{ShipmentID}.zipDocument ControllerZIP (checksum logged)

Note on D4: the Sungrow PowerTitan2.0 + ST2752UX Service Manual revision is not yet attached. It is to be supplied per shipment at the RFQ stage and added to the Compliance Pack before Step 4 begins. Until then, the public Sungrow product pages cited inline stand as the design-intent reference.

4. Timeline with Dependencies

DayActivityDepends onSlot
D+0Goods arrival at Santos / Itajaí bonded warehouse—Confirmed
D+1 to D+3Siscomex DI registration, Receita Federal release via Siscomex Portal Único [Src: Siscomex Portal Único]D+0; valid FCR + commercial invoiceIndicative
D+3 to D+5Inland transfer to test bay, stagingD+1 customs releaseIndicative
D+5 to D+6Pre-test safety checklist, simulator configuration (1500 V DC, -30 to 50 °C envelope) [Src: PowerTitan2.0]Staging complete, Sungrow Service Manual on fileConfirmed
D+6 to D+8LVRT / HVRT execution, raw trace capture at 1500 V DCSimulator configured, PCS readyConfirmed
D+8 to D+10Report compilation, ISO 2859-1:1999 sampling, QA sign-offTraces capturedConfirmed
D+10 to D+12Compliance pack archive, release decisionQA sign-offConfirmed
D+12 to D+14Client notification, shipment to siteRelease Note issuedIndicative

Slot legend: "Confirmed" = internal TradVolt activity under our control. "Indicative" = depends on Brazilian customs clearance time or carrier schedule and is therefore variable.

5. Cost Slots

SlotDescriptionBasis
IndicativeTest bay day-rate and engineering hours per PCS unit (Sungrow PowerTitan2.0)Quoted per shipment on RFQ; not fixed in this SOP.
IndicativeReactive current injection measurement instrumentation hirePer shipment RFQ; depends on availability in BR.
UNCERTAINBrazilian import duty + ICMS + PIS/COFINS on PCS / spare partsSee §6 — values must be looked up at booking on Siscomex Portal Único [Src: Siscomex Portal Único].
IndicativeFIATA documentation fees, Siscomex transaction feesPer shipment RFQ.

6. Duty / HS Code Block (REQUIRED — lookup at booking)

ItemHS code (suggested)Duty / tax rateOfficial portal
PCS (Sungrow PowerTitan2.0) for BESS8504.40 — Static converters (verify at booking)PENDING — lookupSiscomex Portal Único · Siscomex NCM enquiry
LFP battery container (Sungrow ST2752UX) for ESS8507.60 — Lithium-ion accumulators (verify at booking)PENDING — lookupSiscomex (same portal)
Spare PCB assemblies / power electronics parts8504.90 or 8534.00 (verify at booking)PENDING — lookupSiscomex (same portal)

Disclaimer — duty and HS block: HS classifications and applicable import duty, ICMS, PIS, COFINS, and anti-dumping rates are not hardcoded in this SOP. They must be looked up against the official Siscomex Portal Único / Receita Federal at the time of booking, against the exact OEM part description, technical sheet, and Mercosur Common Nomenclature (NCM) in force [Src: Siscomex Portal Único]. Rates change periodically and depend on tariff regime (general, preferential Mercosur/China, or special Ex-Tarifário regime where applicable). TradVolt accepts no liability for rates applied without current official verification.

7. Acceptance Criteria

8. Roles and Responsibilities

9. Exceptions and Non-Conformities

Any failure of the acceptance criteria in §7 results in a Non-Conformity Report (NCR). The lot is quarantined in the bonded area until root cause is filed and a corrective action is approved. Re-test is permitted only after firmware or hardware rework documented against the Sungrow PowerTitan2.0 Service Manual revision in force for this shipment (datasheet to be attached at RFQ stage; until then, public Sungrow PowerTitan2.0 product page stands as the design-intent reference).

Model assumptions (to confirm at RFQ stage): (a) Sungrow PowerTitan2.0 firmware revision current at booking. (b) Sungrow ST2752UX SOC window for grid-fault testing — confirm in per-shipment Service Manual. (c) Sungrow PowerTitan2.0 DC bus torque values and 1500 V DC insulation test voltage — confirm in per-shipment Service Manual. (d) Reactive current envelope expressed as percentage of max AC output (2520 kW).

10. Call to Action

For shipments covered by this SOP, TradVolt issues a quotation within 48 hours of receiving the RFQ pack (commercial invoice draft, Sungrow PowerTitan2.0 datasheet, Sungrow ST2752UX datasheet, packing list).