Airport GSE Solar 300 kWp — US Use-Case / Total Cost of Ownership

Segment: Airport Ground Service Equipment (GSE) | Region: United States | Array size: 300 kWp DC | Reviewer: muse-ba | Evidence date: 15 January 2026

0. Verdict (read first)

For a modelled 300 kWp DC ground-mount PV canopy (equipment scope: LONGi Hi-MO 5m LR5-72HBD bifacial mono-PERC modules paired with Sungrow ST125CX three-phase string inverters, ground-screw fixed-tilt racking) powering airport GSE charging in the United States, over a 25-year horizon at a 5.00% real discount rate, the scenario model returns an NPV of +USD 343,618.04, an IRR of 11.95%, a simple payback of 8.28 years, a discounted payback of 10.74 years, and an LCOE of USD 0.0870/kWh. Limitation: simple and discounted payback are well inside the 18-year airport-capex horizon, and LCOE sits below the modelled US commercial displaced-grid price of $0.115/kWh (margin ≈ $0.028/kWh) — the project is NPV-positive with comfortable payback; pair with the IRS Section 48E Clean Electricity Investment Credit (https://www.irs.gov/credits-deductions/clean-electricity-investment-credit) for incremental margin.

MetricValue
CurrencyUSD
Horizon (years)25
Discount rate5.00 %
Total undiscounted cost (USD)598,963.62
Total discounted cost / PV of costs (USD)500,111.03
Total undiscounted benefit (USD)1,572,178.44
Total discounted benefit (USD)843,729.06
NPV (USD)343,618.04
IRR0.1195
Simple payback (year)8.28
Discounted payback (year)10.74
LCOE (USD/kWh)0.0870

1. Scope & Equipment

This worksheet estimates the 25-year total cost of ownership of a 300 kWp DC ground-mount photovoltaic canopy powering GSE charging at a US airport. Scope boundary: modules, racking, inverters, AC/DC BOS, grid interconnection on the airport microgrid, O&M, module degradation, and inverter replacement at year 15. Excluded: civil-works upgrades beyond pile-driven foundations, EVSE hardware for the GSE fleet, airport concession fees, ITC tax-equity structuring, and insurance.

Explicit equipment scope (R12):

2. Inputs Table (with specific source URLs)

SymbolInputValueUnitSource
PArray DC nameplate300kWpScenario definition
GSpecific yield (US national average, fixed-tilt ground mount)1,425kWh/kWp/yrNREL PVWatts calculator — https://pvwatts.nrel.gov/ (default DC system size, fixed-tilt, US national)
dModule linear degradation0.5%/yrNREL Best Practices in Photovoltaic System Performance — https://www.nrel.gov/docs/fy23osti/87530.pdf
C_modModule capex (LONGi Hi-MO 5m mono-PERC class)260$/kWpNREL U.S. Solar Photovoltaic System and Energy Storage Cost Benchmark, Q1 2024 — https://www.nrel.gov/docs/fy24osti/87860.pdf (Table 1, utility-scale modules)
C_rackGround-screw fixed-tilt racking140$/kWpNREL U.S. Solar PV Cost Benchmark — https://www.nrel.gov/docs/fy24osti/87860.pdf
C_invSungrow 125 kW-class string inverter capex120$/kWpNREL U.S. Solar PV Cost Benchmark — https://www.nrel.gov/docs/fy24osti/87860.pdf
C_BOSAC/DC BOS + soft costs (interconnect, commissioning, permitting)780$/kWpNREL U.S. Solar PV Cost Benchmark — https://www.nrel.gov/docs/fy24osti/87860.pdf
C_omAnnual O&M (fixed)18$/kWp/yrNREL U.S. Solar PV Cost Benchmark — https://www.nrel.gov/docs/fy24osti/87860.pdf
C_inv_replSungrow inverter replacement at year 15120$/kWpNREL U.S. Solar PV Cost Benchmark — https://www.nrel.gov/docs/fy24osti/87860.pdf
P_gridGrid electricity price displaced0.115$/kWhU.S. EIA, Electric Power Monthly, Table 5.6.B — https://www.eia.gov/electricity/monthly/epm_table_grapher.php?t=table_5_06_b (commercial sector, US average)
r_escalGrid price escalation (real)2.5%/yrU.S. EIA Annual Energy Outlook 2024 — https://www.eia.gov/outlooks/aeo/
r_discDiscount rate (airport-authority WACC proxy)5.00%/yrModel assumption — bounded default (consistent with US municipal-airport cost-of-capital ranges)
NAnalysis horizon25yearsNREL standard system-life assumption — https://www.nrel.gov/docs/fy23osti/87530.pdf
residual_value.amountEnd-of-horizon residual0USDModel bounded default — bounded assumption (no terminal salvage credited)
residual_value.yearResidual recognition year25yrModel bounded default — bounded assumption
asset.pv.self_consumption_pctSelf-consumption share of PV output100%Model bounded default — bounded assumption (all kWh directly offset GSE-charging load; no export)
asset.pv.export_tariff_per_kwhExport tariff (kWh not self-consumed)ZERO-AS-MISSING → 0.0000USD/kWhModel bounded default — bounded assumption (no export credited; 100% self-consumed)

Note: the line-item split (C_mod + C_rack + C_inv + C_BOS) sums to $1,300/kWp of installed hardware/BOS, matching the §3 formula's CAPEX basis and the $390,000 year-0 capex row of the computed cash-flow table.

3. TCO Formula (illustrative of the scenario model's logic)

The scenario model computes both numerator and denominator on the same real-discount basis (5.00%), with year-0 CAPEX, year-15 inverter replacement, and real O&M escalation set to 2.0%/yr. The tables in §4 are the computed outputs and must be reproduced verbatim.

LCOE = Σt=0..25 (CAPEXt + OPEXt) / (1+r)t   /   Σt=1..25 Et / (1+r)t

Where:

Benefit (energy displaced): Bt = Et × P_grid × (1 + r_escal)t.

4. computed Output Tables (computed — copy verbatim)

The values below are the scenario model outputs (NPV, IRR, payback, LCOE) for the scenario defined in §1–§2. The full year-by-year discounted cash flow is reproduced verbatim in §4.2. All figures are USD; energy in kWh; LCOE in USD/kWh.

4.1 TCO summary (computed)

TCO summary
MetricValue
CurrencyUSD
Horizon (years)25
Discount rate5.00 %
Total undiscounted cost (USD)598,963.62
Total discounted cost / PV of costs (USD)500,111.03
Total undiscounted benefit (USD)1,572,178.44
Total discounted benefit (USD)843,729.06
NPV (USD)343,618.04
IRR0.1195
Simple payback (year)8.28
Discounted payback (year)10.74
LCOE (USD/kWh)0.0870

4.2 Year-by-year cash flow (computed)

Year-by-year cash flow
YearCost (USD)Benefit (USD)Net (USD)Discount factorDiscounted net (USD)Energy (kWh)
0390,000.000.0000-390,000.001.00-390,000.000.0000
15,400.0049,162.5043,762.500.952441,678.57427,500.00
25,508.0050,139.6044,631.600.907040,482.18425,362.50
35,618.1651,136.1345,517.970.863839,320.13423,235.69
45,730.5252,152.4646,421.940.822738,191.44421,119.51
55,845.1353,188.9947,343.860.783537,095.15419,013.91
65,962.0454,246.1248,284.080.746236,030.33416,918.84
76,081.2855,324.2649,242.990.710734,996.07414,834.25
86,202.9056,423.8350,220.930.676833,991.50412,760.08
96,326.9657,545.2651,218.300.644633,015.77410,696.28
106,453.5058,688.9752,235.470.613932,068.05408,642.79
116,582.5759,855.4153,272.840.584731,147.53406,599.58
126,714.2261,045.0454,330.820.556830,253.43404,566.58
136,848.5162,258.3155,409.800.530329,385.00402,543.75
146,985.4863,495.6956,510.220.505128,541.50400,531.03
1543,125.1964,757.6721,632.480.481010,405.59398,528.38
167,267.6966,044.7358,777.040.458126,926.44396,535.73
177,413.0467,357.3759,944.320.436326,153.51394,553.06
187,561.3068,696.0961,134.790.415525,402.77392,580.29
197,712.5370,061.4362,348.900.395724,673.58390,617.39
207,866.7871,453.9063,587.120.376923,965.32388,664.30
218,024.1272,874.0564,849.930.358923,277.39386,720.98
228,184.6074,322.4266,137.820.341822,609.21384,787.38
238,348.2975,799.5867,451.290.325621,960.20382,863.44
248,515.2677,306.0968,790.840.310121,329.83380,949.12
258,685.5678,842.5570,156.990.295320,717.55379,044.38

Cross-check: LCOE = PV(costs) / PV(generation) computed on the same 5.00% discount basis yields USD 0.0870/kWh, matching the computed cell above. The year-15 cost column (USD 43,125.19) bundles the year-15 OPEX and the USD 36,000 inverter-replacement line; the discounted net for year 15 (USD 10,405.59) reflects the 5.00% discount factor. The simple payback of 8.28 years and discounted payback of 10.74 years are consistent with the discounted-net column.

5. Sensitivity Table (illustrative — single-input perturbations)

Each scenario re-runs the scenario model with a single input perturbed; LCOE is computed on a consistent 5.00% real-discount basis (except S5/S6 which perturb the discount rate itself). Sensitivity figures are illustrative single-input perturbations and are not computed in the computed output tables in §4; treat them as bounded model assumptions until the buyer re-runs the model.

ScenarioΔ vs baseP (kWp)G (kWh/kWp)CAPEX basis ($/kWp)r_disc (%)P_grid ($/kWh)LCOE (USD/kWh)Verdict
S0 — Base—3001,4251,3005.000.1150.0870Pay — margin of $0.028/kWh vs displaced grid.
S1 — Low yield (Pacific NW)G −15%3001,2111,3005.000.1150.1024 (illustrative)Marginal — pair with ITC.
S2 — High yield (AZ)G +18%3001,6821,3005.000.1150.0737 (illustrative)Strong pay.
S3 — Capex −10%C −10%3001,4251,1705.000.1150.0783 (illustrative)Strong pay.
S4 — Capex +15%C +15%3001,4251,4955.000.1150.1001 (illustrative)Marginal — defer until capex normalizes.
S5 — Discount 8%r +3 pp3001,4251,3008.000.1150.0904 (illustrative)Pay — high-WACC airports still pass.
S6 — Discount 3%r −2 pp3001,4251,3003.000.1150.0846 (illustrative)Strong pay.
S7 — Grid price $0.085P_grid low3001,4251,3005.000.0850.0870 (illustrative)Do not pursue on economics alone — subsidy required.
S8 — Grid price $0.180P_grid high3001,4251,3005.000.1800.0870 (illustrative)Strong pay — large margin.

Sensitivity figures are illustrative bounded model assumptions, not computed outputs. computed outputs are the tables in §4.

6. Calls to Action

Request a single absolute RFQ for Airport GSE Solar 300 kWp (US, r9)

Download the editable model inputs behind this worksheet: airport-gse-solar-300kwp-us-r9.csv (companion airport-gse-solar-300kwp-us-r9.xlsx).

This page is a worksheet, not a binding offer.

7. Cert & Standards Block

Certification status is supplier- and project-specific; tradvolt.com does not warrant any individual shipment's listing.

8. HS Code Block & Duty Rates

HS codeDescriptionUS import duty
8541.43.0000Photovoltaic cells, assembled into modules or made up into panelsPENDING — lookup via USITC HTS (https://hts.usitc.gov/) — confirmation required at time of import.
8504.40.9550Static converters — solar inverters (Sungrow 125 kW-class)PENDING — lookup via USITC HTS (https://hts.usitc.gov/) — confirmation required at time of import.
7308.90.3000Structures and parts of structures, of iron or steel — ground-screw rackingPENDING — lookup via USITC HTS (https://hts.usitc.gov/) — confirmation required at time of import.

Lookup instructions: Open https://hts.usitc.gov/, enter each code above, confirm the current General duty rate, and check whether any Section 301 (China-origin) measures apply at the time of entry. For Section 301 exclusions, consult the USTR four-year review page (https://ustr.gov/trade-topics/enforcement/section-301-investigations/section-301-china-technology-transfer/china-section-301-tariff-actions-and-exclusion-process/four-year-review).