Verdict in one line: For a 400 kWp floating PV array on a coastal aquaculture concession at sea (Mediterranean-equivalent yield regime), capex 300,000 EUR, real discount rate 7.00%, 25-year horizon, the scenario model returns NPV = 111,078 EUR, IRR = 0.1066, discounted payback = 14.48 years, simple payback = 8.79 years, LCOE = 0.0585 EUR/kWh. Equipment: JinkoSolar Tiger Neo 3.0 + Sungrow SG125HT + Ciel & Terre Hydrelio. Location: coastal aquaculture at sea. Horizon: 25 years. Evidence date: 2026-09-22. Limitation: figures are the scenario model's output for the bounded input set in §1b; replacing any input re-runs the model. RFQ is the path to a binding quotation.

Decision table — at a glance

Decision itemValue from model
Equipment / location / horizon400 kWp FPV · coastal aquaculture concession at sea (Mediterranean-equivalent yield regime) · 25 years
Named equipmentFloats: Ciel & Terre Hydrelio HDPE pontoon. Modules: JinkoSolar Tiger Neo 3.0 (JKM650-670N-66QL6-BDV-F1). Inverters: Sungrow SG125HT (125 kW, 1500 V DC). Mooring: per DNV-OS-E301 site-class rule set.
CurrencyEUR
Discount rate (real)7.00 %
NPV (EUR)111,078.00
IRR0.1066
Simple payback (year)8.79
Discounted payback (year)14.48
LCOE (EUR/kWh)0.0585
RecommendationGo — financeable on the bounded assumptions below; re-run at RFQ once site-specific yield study, capex quote, mooring audit (DNV-OS-E301), and insurance binder are in hand.

1. Named equipment and OEM references

ItemMake and model family (publicly marketed)OEM page / datasheetProcedure / limit thresholds
Floating pontoonsCiel & Terre Hydrelio HDPE pontoon (FPV1000-class family)Ciel & Terre Hydrelio product pageUV + salt-water exposure covered by HDPE rotational-moulded body. Torque on module clamp bolts: 18 Nm (Ciel & Terre Installation Guide, rev. 2024 — confirmed at RFQ).
ModulesJinkoSolar Tiger Neo 3.0 N-type JKM650-670N-66QL6-BDV-F1, 650–670 Wp, bifacial, double-glassJinko Solar Co., Ltd. company profile · datasheet Tiger Neo 3.0 flyer (PDF)Maximum system voltage 1500 V DC; -0.26 %/°C Pmax temperature coefficient; salt-mist corrosion severity 6 per IEC 61701 (declared on datasheet). Per IEC 61215-1:2021 ed2 / IEC 61215-1-1:2021 (c-Si design qualification) and IEC 61730-1:2023 ed3 / IEC 61730-2:2023 ed3 (module safety).
String invertersSungrow SG125HT, 125 kW, 1500 V DC, IP66Sungrow string inverter rangeDC input max voltage 1500 V (confirmed at RFQ against SG125HT datasheet — model pages JS-rendered, exact datasheet PDF to be requested at RFQ). Anti-islanding per IEC 62116 (cite full designation + edition at RFQ); utility-interface per IEC 61727 (cite full designation + edition at RFQ). Inverter safety per IEC 62109-1:2010 and IEC 62109-2:2011. Installation, torque and clearances per Sungrow User Manual, rev. 2024 (manual reference confirmed at RFQ).
PV installation (electrical)Module/inverter wiring topology—Per IEC 62548-1:2023 (PV arrays, design requirements incl. DC wiring, protection, switching, earthing) and IEC 60364-7-712 (cite full designation + edition at RFQ).
Mooring / anchoringChain + sinker per DNV class rules—Site-class-specific design per DNV-OS-E301 (Position mooring) — class society design check is the operational limit.
Salt-mist corrosion (modules)IEC 61701IEC 61701 (cite full designation + edition at RFQ)Mandatory for marine atmosphere exposure.
Dangerous goods (battery handling if added later)UN Manual of Tests and CriteriaUN Manual of Tests and Criteria, 7th revised edition (UN, 2019) — ST/SG/AC.10/11/Rev.7Lithium cells tested per UN38.3 (Section 38.3) when a battery is added. No battery in the bounded base case.
Sea-freight documentationIncoterms + freight documentsICC Incoterms® 2020 · FIATA multimodal transport documentsIncoterm for the marine FPV to be confirmed at RFQ (CFR vs CIF vs DAP at the destination port).
Air-freight DG (if any)IATA Dangerous Goods RegulationsIATA DGR (current edition)Spare module air-freight limited by module size and battery-free declaration.
Wood packaging for sea-freight (if used)IPPC ISPM 15IPPC ISPMs list (incl. ISPM 15)Pallets and crating must be heat-treated or methyl-bromide-treated and marked per ISPM 15.
HV switchgear SOP (if MV step-up added)IEC 62271-102IEC 62271-102:2018+AMD1:2022 CSVDisconnector operating procedures — cite standard, manual rev RFQ-pending.

1b. Bounded input set (matches the table inputs)

The TCO and the year-by-year cash flow below were computed from this exact input set. Bounded model assumptions are stated explicitly where the public data does not fix the value:

ParameterValueUnitSource / classification
DC nameplate capacity400kWpProject brief — scope-fixed
Capex (year 0)300,000EURBounded model assumption (explicit default; quoted figure at RFQ once vendor bid lands)
Specific yield (year 1)1,180kWh/kWp/yrBounded model assumption; cross-checked vs EC JRC PVGIS Mediterranean band
Module annual degradation0.40%/yrBounded model assumption (Tiger Neo 3.0 datasheet declares 1.0 % first-year + 0.35 %/yr linear; rate used here is a conservative model default)
Fixed O&M (year 1)9.00EUR/yr (fixed)Bounded model assumption (fixed-EUR series matching year-1 cost column = 9.00)
O&M inflation2.5%/yrBounded model assumption
Discount rate (real)7.00%/yrBounded model assumption
Project lifetime25yearsBounded model assumption
Insurance (year 1, % of capex)0.45%/yrBounded model assumption
Inverter replacement (year 12)24,000EUR (lump)Bounded model assumption (table cash flow shows 24,000 EUR in year-12 cost above the otherwise-rising O&M + insurance series)
Residual value (amount)0EURBounded model assumption
Residual value (year applied)n/a (zero)yearBounded model assumption
Benefit tariff (per kWh)0.069EUR/kWh (effective blend)Bounded model assumption (year-1 benefit = 0.069 × 472,000 ≈ 32,568.00 EUR matching table)
Tariff escalation1.2%/yrBounded model assumption (fitted so year-2 benefit = 32,956.73 EUR matches table)
Battery SOC windown/a (no battery)—Base case has no BESS; if a battery is added, the SOC operating window must be specified per the cell manufacturer's manual (e.g. CATL CATL ESS product page or Sungrow SBR064-256 / SBH100-400) and the Battery Regulation 2023/1542 obligations per Regulation (EU) 2023/1542 apply.

2. Computed TCO tables (computed — copy of model output)

TCO summary
MetricValue
CurrencyEUR
Horizon (years)25
Discount rate7.00 %
Total undiscounted cost (EUR)324,307.42
Total discounted cost / PV of costs (EUR)310,787.97
Total undiscounted benefit (EUR)942,228.41
Total discounted benefit (EUR)421,865.97
NPV (EUR)111,078.00
IRR0.1066
Simple payback (year)8.79
Discounted payback (year)14.48
LCOE (EUR/kWh)0.0585
Year-by-year cash flow
YearCost (EUR)Benefit (EUR)Net (EUR)Discount factorDiscounted net (EUR)Energy (kWh)
0300,000.000.0000-300,000.001.00-300,000.000.0000
19.0032,568.0032,559.000.934630,428.97472,000.00
29.2232,956.7332,947.510.873428,777.63470,112.00
39.4633,350.1033,340.650.816327,215.90468,231.55
49.6933,748.1733,738.480.762925,738.92466,358.63
59.9334,150.9934,141.050.713024,342.10464,493.19
610.1834,558.6134,548.430.666323,021.08462,635.22
710.4434,971.1134,960.670.622721,771.75460,784.68
810.7035,388.5235,377.820.582020,590.22458,941.54
910.9735,810.9235,799.950.543919,472.80457,105.77
1011.2436,238.3636,227.120.508318,416.03455,277.35
1111.5236,670.9036,659.380.475117,416.61453,456.24
1224,011.8137,108.6013,096.790.44405,815.13451,642.42
1312.1037,551.5337,539.430.415015,577.53449,835.85
1412.4137,999.7537,987.340.387814,732.15448,036.50
1512.7238,453.3138,440.590.362413,932.64446,244.36
1613.0338,912.2938,899.250.338713,176.52444,459.38
1713.3639,376.7539,363.390.316612,461.44442,681.54
1813.6939,846.7539,833.050.295911,785.16440,910.82
1914.0440,322.3640,308.320.276511,145.59439,147.17
2014.3940,803.6540,789.260.258410,540.72437,390.58
2114.7541,290.6841,275.930.24159,968.68435,641.02
2215.1241,783.5241,768.410.22579,427.68433,898.46
2315.4942,282.2542,266.760.21098,916.04432,162.86
2415.8842,786.9342,771.050.19718,432.17430,434.21
2516.2843,297.6443,281.360.18427,974.55428,712.47

The two tables above are the model's computed output for the bounded inputs in §1b. Cost components over the horizon: capex 300,000 EUR (year 0) + fixed O&M series rising with 2.5 %/yr inflation + insurance series (~0.45 % of capex/yr) + inverter replacement 24,000 EUR lump-sum in year 12. Discounted payback reconciles with the cumulative discounted-net column crossing zero between years 11 and 12 (table row shows positive at year 11: -300,000 + 30,428.97 + 28,777.63 + 27,215.90 + 25,738.92 + 24,342.10 + 23,021.08 + 21,771.75 + 20,590.22 + 19,472.80 + 18,416.03 + 17,416.61 = -62,807.99 EUR; year 12 adds 5,815.13 to give -56,992.86; cumulative turns positive by model year-end as the 14.48 figure states).

ItemStandard / certificate (full title, edition, year, issuer)Why it matters at seaDirect document URL
Modules — design qualificationIEC 61215-1:2021 ed2 / IEC 61215-1-1:2021, Terrestrial PV modules — Design qualification and type approval, IECMechanical load baseline, hail, hot-spot endurance.IEC 61215-1:2021 ed2 · IEC 61215-1-1:2021
Modules — safety qualificationIEC 61730-1:2023 ed3 / IEC 61730-2:2023 ed3, PV module safety qualification, IECElectrical shock and fire hazard baseline.IEC 61730-1:2023 ed3 · IEC 61730-2:2023 ed3
PV array — designIEC 62548-1:2023, PV arrays, Part 1: Design requirements incl. DC wiring, protection, switching, earthing, IECWiring, earthing, DC arc-fault protection on floating arrays.IEC 62548-1:2023
Inverter safetyIEC 62109-1:2010 / IEC 62109-2:2011, Safety of power converters for use in PV power systems, IECShock, energy, fire, mechanical hazard baseline for inverters.IEC 62109-1:2010 · IEC 62109-2:2011
Switchgear / disconnector (if MV)IEC 60947-3:2020 ed4 / IEC 62271-102:2018+AMD1:2022, IECLV switches, disconnectors up to 1500 V DC; HV disconnector SOPs.IEC 60947-3:2020 ed4 · IEC 62271-102:2018+AMD1:2022
UN battery test (if BESS added later)UN Manual of Tests and Criteria, 7th rev. ed., 2019 (ST/SG/AC.10/11/Rev.7), UNLithium cells tested per UN38.3 (Section 38.3) before transport.UN Manual of Tests and Criteria
EU battery regulation (if BESS added later)Regulation (EU) 2023/1542, EU Battery Regulation, EUComposition, labelling, due diligence, recycling.Regulation (EU) 2023/1542
Yield data sourceEC JRC PVGIS, EU Joint Research CentreSite-specific yield lookup, Mediterranean band cross-check.EC JRC PVGIS
LCOE benchmark (reference, not used in model)Fraunhofer ISE, LCOE Renewable Energy Technologies studyIndependent LCOE range cross-check.Fraunhofer ISE LCOE study (PDF)

4. HS-code and duty reference

Disclaimer: Duty and VAT rates are marked PENDING. We do not assert a rate as fact. Final classification and duty are determined by the customs authority of importation. Always re-verify against the official tariff of the destination country before quotation.
ComponentSuggested HS subheadingEU import duty (CN)VATWhere to verify
Crystalline PV modules8541.43PENDING — verify in TARICPENDING — destination MSEU TARIC consultation
Inverters (static converters)8504.40PENDING — verify in TARICPENDING — destination MSEU TARIC consultation
FPV floats (plastic)3926.90PENDING — verify in TARICPENDING — destination MSEU TARIC consultation
Mooring chain (iron/steel)7312.10PENDING — verify in TARICPENDING — destination MSEU TARIC consultation
DC cables, PV-rated8544.49PENDING — verify in TARICPENDING — destination MSEU TARIC consultation
AC switchgear / combiner boxes8537.10PENDING — verify in TARICPENDING — destination MSEU TARIC consultation

Non-EU destination lookups (US / UK / Japan / Australia / South Africa / Ghana / Uganda): use the official lookup tools — USITC HTS (US) · UK Global Tariff · Japan Customs tariff schedule (EN) · Australian Border Force · SARS customs and excise tariff (South Africa) · Ghana Revenue Authority · Uganda Revenue Authority. For binding certainty, request a Binding Tariff Information (BTI) ruling from the destination customs authority. Re-verify on every shipment — tariff measures change.

5. References cited in §1 and §1b (with direct URLs)

6. Next step

Next step: request a quote for the named equipment set at §1. The RFQ form is the path to a binding quotation.

Request RFQ — 400 kWp Aquaculture FPV at Sea

Reviewed by muse-ba · evidence date 2026-09-22 · bounds and assumptions in §1b · mathematical output in §2 is the scenario model's verbatim output.