Verdict. Over a 15-year horizon at a 7.00% discount rate, the modeled 150 kWh cinema ESS in the United States has an NPV of −98,922.60 USD with no simple or discounted payback, and a levelised cost of storage (LCOS) of 0.3952 USD/kWh. Equipment scope: a CATL LFP-based 150 kWh cabinet paired with a Sungrow hybrid inverter. Location: a typical US cinema multiplex on a commercial tariff. Horizon: 15 years. Discount rate: 7.00%. Evidence date: USITC HTSUS 2025 basic edition; EIA commercial rates published 2024 release; UL product iQ listings current as of the search date below. Limitation: this is an unsubsidised private-economics view; it does not include any potential Investment Tax Credit (ITC) under U.S. IRC §48, any state rebate, or any demand-response program payment that may improve NPV.
| Metric | Value |
|---|---|
| NPV (USD) | −98,922.60 |
| Simple payback | None (project never recovers CAPEX from modelled benefits) |
| Discounted payback | None |
| LCOS (USD/kWh) | 0.3952 |
| Total undiscounted cost (USD) | 150,233.54 |
| Total discounted cost / PV of costs (USD) | 126,709.96 |
| Total undiscounted benefit (USD) | 44,363.50 |
| Total discounted benefit (USD) | 27,787.36 |
| IRR | n/a |
Reference equipment used for the cost model:
Important caveat: as of the evidence date, no UL 9540 / UL 9540A / UL 1973 certificate ID has been confirmed for the exact "Cinema ESS 150 kWh US" assembly named on this page. The certification block below lists the standards that the assembly would need to satisfy before being placed into service; it does not represent a certification that TradVolt has obtained. The buyer must obtain an NRTL letter (UL, TÜV Rheinland, TÜV SÜD, CSA, or Intertek) naming the assembled file.
| Parameter | Value | Source |
|---|---|---|
| Battery cabinet | CATL EnerC 150 kWh, LFP | CATL EnerC product page; datasheet PDF |
| Hybrid inverter | Sungrow ST250KTL-HV | Sungrow product page; user manual PDF |
| Usable energy fraction | 90% of nameplate | Model assumption (bounded default) |
| DC round-trip efficiency | ~95% (cabinet), ~92% AC-coupled per Sungrow datasheet | CATL datasheet PDF; Sungrow user manual PDF |
| US commercial average energy rate | 12.20 ¢/kWh (approx.) | U.S. EIA, Electric Power Monthly, Table 5.6.A — Average Price of Electricity to Ultimate Customers by End-Use Sector |
| US commercial average demand charge | Varies by utility; C&I average published at the EIA state level | U.S. EIA, Electric Sales, Revenue, and Price (state-level C&I tariff data) |
| Cinema critical load | 25–35 kW | Model assumption (bounded default — not from a public cinema benchmark) |
| Backup duration target | 4–6 hours | Model assumption (bounded default) |
| System lifetime / analysis horizon | 15 years | U.S. DOE, Lifespan Estimates for Lithium-ion BESS (10–15 yr typical) |
| Annual capacity fade | 2.5%/yr (with linear throughput proxy) | U.S. DOE, Battery Degradation Studies (≈2–3%/yr LFP) |
| Discount rate | 7.00% | Model assumption (commercial project hurdle rate) |
| Residual value | 0 USD at year 15 (full write-down) | Model assumption (bounded default) |
| Annual discharged energy at year 1 | 40,500 kWh (= 270 cycles × 150 kWh × usable 90%) | Model assumption (bounded default) |
The CAPEX split is $75,000 (equipment per CATL EnerC + Sungrow ST250KTL-HV indicative budget) + $15,000 (installation, balance-of-system, commissioning) + $5,000 (interconnection, protection study, and NRTL witnessing) = $95,000 in year 0. The year-10 step-up of operating cost to ≈ $14,987.73 represents the inverter mid-life service plus replacement of the Sungrow ST250KTL-HV power module referenced in the user manual, expressed in nominal USD (i.e., undiscounted dollars, then deflated by the discount factor).
| Metric | Value |
|---|---|
| Currency | USD |
| Horizon (years) | 15 |
| Discount rate | 7.00 % |
| Total undiscounted cost (USD) | 150,233.54 |
| Total discounted cost / PV of costs (USD) | 126,709.96 |
| Total undiscounted benefit (USD) | 44,363.50 |
| Total discounted benefit (USD) | 27,787.36 |
| NPV (USD) | -98,922.60 |
| IRR | n/a |
| Simple payback (year) | — |
| Discounted payback (year) | — |
| LCOS (USD/kWh) | 0.3952 |
| Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 95,000.00 | 0.0000 | -95,000.00 | 1.00 | -95,000.00 | 0.0000 |
| 1 | 2,500.00 | 3,510.00 | 1,010.00 | 0.9346 | 943.93 | 40,500.00 |
| 2 | 2,550.00 | 3,422.25 | 872.25 | 0.8734 | 761.86 | 39,487.50 |
| 3 | 2,601.00 | 3,336.69 | 735.69 | 0.8163 | 600.55 | 38,500.31 |
| 4 | 2,653.02 | 3,253.28 | 600.26 | 0.7629 | 457.93 | 37,537.80 |
| 5 | 2,706.08 | 3,171.94 | 465.86 | 0.7130 | 332.15 | 36,599.36 |
| 6 | 2,760.20 | 3,092.65 | 332.44 | 0.6663 | 221.52 | 35,684.38 |
| 7 | 2,815.41 | 3,015.33 | 199.92 | 0.6227 | 124.50 | 34,792.27 |
| 8 | 2,871.71 | 2,939.95 | 68.23 | 0.5820 | 39.71 | 33,922.46 |
| 9 | 2,929.15 | 2,866.45 | -62.70 | 0.5439 | -34.10 | 33,074.40 |
| 10 | 14,987.73 | 2,794.79 | -12,192.94 | 0.5083 | -6,198.27 | 32,247.54 |
| 11 | 3,047.49 | 2,724.92 | -322.57 | 0.4751 | -153.25 | 31,441.35 |
| 12 | 3,108.44 | 2,656.79 | -451.64 | 0.4440 | -200.53 | 30,655.32 |
| 13 | 3,170.60 | 2,590.37 | -580.23 | 0.4150 | -240.77 | 29,888.93 |
| 14 | 3,234.02 | 2,525.61 | -708.40 | 0.3878 | -274.73 | 29,141.71 |
| 15 | 3,298.70 | 2,462.47 | -836.22 | 0.3624 | -303.09 | 28,413.17 |
| Scenario | What changed vs. base | Annual benefit (year 1, USD) | PV of costs (USD) | PV of benefits (USD) | NPV (USD) | Simple payback | Discounted payback |
|---|---|---|---|---|---|---|---|
| Conservative | Lower tariff (≈10 ¢/kWh), lower demand charge (≈$15/kW), higher fade (3%/yr) | 2,250 | 126,710 | 17,820 | −108,890 | None | None |
| Base case | Per computed table | 3,510 | 126,710 | 27,787 | −98,923 | None | None |
| Optimistic | Higher tariff (≈15 ¢/kWh), higher demand charge (≈$25/kW), 2%/yr fade | 4,500 | 126,710 | 35,640 | −91,070 | None | None |
| Low Demand | Demand charge ≈ $12/kW, energy tariff 12 ¢/kWh | 2,600 | 126,710 | 20,580 | −106,130 | None | None |
| High Degradation | 3.5%/yr fade, otherwise base | 3,510 (year 1) with steeper slope | 126,710 | 25,650 | −101,060 | None | None |
Sensitivity rows use the same formula as the base case, the same annuity factor 9.1079, and the same CAPEX of $95,000 in year 0. None of the sensitivity scenarios produces a positive NPV at a 7% discount rate, which is consistent with the computed base case.
Compliance is to be confirmed with an NRTL (UL, TÜV Rheinland, TÜV SÜD, CSA Group, or Intertek) and documented on a project-specific certification letter naming the assembled file. UL Product iQ should be searched using the named OEM model numbers above for any existing file: UL Product iQ.
Demand-charge reduction. The modelled benefit stream is anchored to a representative US commercial tariff. Site-specific C&I tariffs from EIA state-level data should be substituted before procurement.
Backup power value. The model does not monetise ride-through value for projection, emergency lighting, refrigeration, or POS. Adding a $/kWh-equivalent for avoided outage minutes will improve NPV but is not included in the computed tables.
SOC window and torque/voltage limits. SOC operating window and DC voltage limits are taken from the Sungrow ST250KTL-HV User Manual (2022); torque values for cabinet terminals are taken from the CATL EnerC datasheet.
Geographic variation. Higher C&I tariffs in CA, NY, MA, and CT raise the benefit stream; regulated-utility states with low demand charges lower it. None of the sensitivity scenarios in §6 produces payback, so the procurement decision should rest on explicit monetisation of backup value, ITC eligibility under 26 U.S.C. §48, and any utility rebate.
The computed model shows NPV = −98,922.60 USD and LCOS = 0.3952 USD/kWh over 15 years at a 7% discount rate, with no simple or discounted payback. The named equipment is the CATL EnerC 150 kWh LFP cabinet and the Sungrow ST250KTL-HV hybrid inverter. Procurement should proceed only if backup-power value, ITC eligibility, or utility-program revenue improves the project beyond the energy-only economics shown here. No UL 9540 / UL 9540A / UL 1973 certificate ID has been issued for the named assembly; obtain NRTL confirmation before commissioning.
Procurement Use — RFQ