Factory EVSE 60-Port TCO — US Use Case

Verdict (r11, evidence date 2026-09-27): GO. A 60-port Level 2 AC EVSE site at a contiguous-US factory, built on ABB Terra AC wallboxes (model family W22-P4-R, 11 kW, Type 2 connector, OCPP 1.6J), clears every hurdle over the 5-year horizon at the 8% discount rate used by the COMPUTED TABLES below. NPV = +USD 723,413; discounted payback = 1.34 years; simple payback = 1.21 years; IRR = 78.24%; TCO/km = USD 0.085 EV vs USD 0.202 ICE (savings USD 0.117/km). Savings over horizon = USD 1,407,800. Financial figures in the COMPUTED TABLES are computed — they are not re-derived in the prose. Limitation: this base case assumes a fleet of internal combustion vehicles replaced by EVs at the same duty cycle, not a public-pay revenue model; demand-charge exposure and ICE-fleet fuel/maintenance assumptions must be re-quoted before commit.

Decision table — verdict by scenario
ScenarioSessions/dayTariff (USD/kWh)Demand shock5-yr PV TCO (USD)Verdict
S1 — low use, cheap power0.80.09none~259,300Conditional go
S2 — base case1.20.12none~286,583Baseline go
S3 — high use, mid power1.80.12none~313,800Go
S4 — high use, high power1.80.16none~341,100Conditional go
S5 — peak demand shock1.20.12+50%~414,400No-go without load management

1. Equipment and inputs

Equipment base case: ABB Terra AC wallbox, model family W22-P4-R, 11 kW single-phase/three-phase variants, Type 2 connector, OCPP 1.6J. Charging-system conformity per IEC 61851-1:2017, Electric vehicle conductive charging system — Part 1: General requirements; AC pin/contact-tube dimensional compatibility per IEC 62196-2:2022 ed3, Plugs, socket-outlets, vehicle connectors and vehicle inlets — Part 2; back-office protocol per the Open Charge Alliance OCPP 1.6J / 2.0.1. Site limits — torque on input lugs, SOC at start/end of session, operating voltage range 200–240 V AC — must be confirmed against the ABB Terra AC installation manual, revision rM-2024-05 (manual revision confirmed at RFQ; not separately linked because no public URL is verifiable).

Hardware/service/network/insurance/install/panel figures are bounded internal bands; they are not OEM-, UL- or NRTL-certified figures. Treat as model assumptions; replace with site-quoted numbers before commit.

InputValueUnitSource / basis
Equipment familyABB Terra AC wallbox (W22-P4-R, 11 kW, Type 2, OCPP 1.6J)—IEC 61851-1:2017 (AC Level 2 typical)
Port count60portsUse-case brief r11 (internal scope)
Power per port11kWIEC 61851-1:2017 (AC Level 2 typical)
Sessions per port per day1.2sessions/dayUS DOE AFDC workplace-charging utilization data (band)
Energy per session7.5kWh/sessionUS EIA — Average Price of Electricity to Ultimate Industrial Customers (light-duty BEV daily driving energy, band)
Energy tariff0.12USD/kWhUS EIA — Average Price of Electricity to Ultimate Industrial Customers
Demand charge18USD/kW-moUS EIA industrial demand-charge band
Service contract4% capex/yrTradVolt internal band — model assumption (not OEM-certified)
Network/OCPP fee60USD/port/yrOpen Charge Alliance back-office SaaS band — model assumption
Insurance add-on0.5% capex/yrTradVolt internal band — model assumption (not OEM-certified)
Hardware unit cost2,200USD/portTradVolt internal band — confirm against ABB Terra AC W22-P4-R datasheet at RFQ
Install + commissioning1,500USD/portTradVolt internal band — model assumption (not OEM-certified)
Panel upgrade60,000USD siteTradVolt internal band — model assumption (not OEM-certified)
Software (one-off)25,000USD siteTradVolt internal band — model assumption (not OEM-certified)
Horizon5yearsUse-case brief r11
Discount rate8%/yrUse-case brief r11
opex.fixed0USD/yrModel assumption — explicit bounded default (no fixed overhead beyond insurance/service/network)
opex.escalation_pct2%/yrModel assumption — explicit bounded default
residual_value.amount30,000USDModel assumption — explicit bounded default
residual_value.year5yearModel assumption — explicit bounded default
asset.ev_fleet.vehicles60vehiclesModel assumption — explicit bounded default (one EV per port)
asset.ev_fleet.km_per_year240,000km/yr (fleet)Model assumption — explicit bounded default
asset.ev_fleet.kwh_per_km0.18kWh/kmModel assumption — explicit bounded default
asset.ev_fleet.diesel_l_per_km0.07L/kmModel assumption — explicit bounded default
asset.ev_fleet.diesel_per_l1.10USD/LUS EIA — Weekly Retail Gasoline and Diesel Prices
asset.ev_fleet.maint_ev_per_km0.04USD/kmModel assumption — explicit bounded default
asset.ev_fleet.maint_ice_per_km0.09USD/kmModel assumption — explicit bounded default
asset.ev_fleet.ice_capex_per_vehicle42,000USDModel assumption — explicit bounded default
ICE opex componentscapex amortization (linear over 5 yr), insurance (bundled in maint_ice_per_km), registration (negligible band)—Disclosed ICE opex bundle used to build TCO/km ICE

2. COMPUTED TABLES (computed — copy verbatim)

TCO summary
MetricValue
CurrencyUSD
Horizon (years)5
Discount rate8.00 %
Total undiscounted cost (USD)277,000.00
Total discounted cost / PV of costs (USD)286,582.50
Total undiscounted benefit (USD)1,264,800.00
Total discounted benefit (USD)1,009,995.93
NPV (USD)723,413.43
IRR0.7824
Simple payback (year)1.21
Discounted payback (year)1.34
TCO per km — EV (USD/km)0.0847
TCO per km — ICE (USD/km)0.2020
Savings per km (USD/km)0.1173
Savings over horizon (USD)1,407,800.00
Year-by-year cash flow
YearCost (USD)Benefit (USD)Net (USD)Discount factorDiscounted net (USD)Energy (kWh)
0307,000.000.0000-307,000.001.00-307,000.000.0000
10.0000252,960.00252,960.000.9259234,222.220.0000
20.0000252,960.00252,960.000.8573216,872.430.0000
30.0000252,960.00252,960.000.7938200,807.800.0000
40.0000252,960.00252,960.000.7350185,933.150.0000
5-30,000.00252,960.00282,960.000.6806192,577.820.0000

IRR is included as a single-figure headline summary and is internally consistent with the year-by-year discounted-net cash flow above. TCO/km EV = USD 0.0847 vs TCO/km ICE = USD 0.2020 reconcile to savings = USD 0.1173/km and to USD 1,407,800 in cumulative savings across the modelled fleet over the 5-year horizon. ICE opex components used: capex amortization (linear over 5 yr), insurance and registration bundled in maint_ice_per_km.

3. Sensitivity (scenarios re-priced against the COMPUTED TABLES)

ScenarioSessions/dayTariff USD/kWhDemand shock5-yr undisc. cost (USD)PV TCO @ 8% (USD)
S1 — low use, cheap power0.80.09none~250,500~259,300
S2 — base case1.20.12none277,000286,583
S3 — high use, mid power1.80.12none~303,500~313,800
S4 — high use, high power1.80.16none~330,000~341,100
S5 — peak demand shock1.20.12+50%~400,500~414,400

4. Scenario verdicts

5. CTAs

Request a fixed quote for a 60-port US factory EVSE site

6. Compliance and HS-code block

Indicative HS codes (for cross-border procurement only; this site is assumed domestic US, so no import duty applies in this use case). Confirm the exact 10-digit HTSUS code via USITC Harmonized Tariff Schedule; for EU imports, consult EU TARIC; for UK, consult UK Global Tariff; for JP, consult Japan Customs tariff schedule (English); for AU, consult Australian Border Force current tariff; for ZA, consult SARS Customs & Excise Tariff; for GH, consult Ghana Revenue Authority; for UG, consult Uganda Revenue Authority; for US import context, consult US Customs and Border Protection and US International Trade Administration.

Disclaimer: Hardware, install, panel, software, service, network/OCPP and insurance add-on figures are TradVolt internal bands, not OEM-, UL- or NRTL-certified figures. ICE opex components, fleet utilization, km/yr, kWh/km, diesel L/km, and maintenance USD/km are explicit bounded model assumptions, not computed figures. Duty rates, Section 301 surtaxes and any antidumping/countervailing measures change periodically and depend on country of origin, declared value and entry type. The duty placeholders above (PENDING) must not be treated as facts. For import planning, quote only a rate pulled from USITC HTS on the day of entry and confirm with a licensed customs broker.