Anchor: total-fleet EV vs ICE TCO, 10-year horizon, 8.00% discount, evidence dated 2026-09-22. Limitation: hub-side demand and corridor electricity tariffs are bounded model assumptions, not measured site data; site-survey updates the rows before any quotation.
Do not proceed on the computed numbers alone. Over a 10-year horizon at 8.00% discount, the scenario model returns NPV = USD -38,084.08, IRR = -0.1161, simple payback = none, discounted payback = none. TCO/km = USD 0.2092 (EV) vs USD 0.2110 (ICE), a per-km saving of USD 0.0018 and USD 700.00 cumulative savings over 10 years. Capex of USD 56,000.00 is not recovered within the horizon at the modelled per-kWh benefit of USD 2,670/yr. The hub-side box is the deciding number for this scenario, not the fleet fuel offset. Equipment: Sungrow 22 kW AC destination charger, model AC22E-01 (datasheet referenced below) with OCPP 1.6J back-office. Location: BR/CL/PA corridors (corridor electricity tariffs are model assumptions, not sourced). Horizon: 10 years. Evidence date: 2026-09-22.
| Decision metric | Value | Threshold / reading |
|---|---|---|
| NPV (USD) | -38,084.08 | Negative → not recovered |
| IRR | -0.1161 | << 8.00% hurdle → do not proceed on this scenario |
| Discounted payback (year) | — (none) | Beyond horizon → do not proceed |
| Simple payback (year) | — (none) | Beyond horizon → do not proceed |
| TCO/km EV (USD/km) | 0.2092 | vs ICE 0.2110 |
| Savings per km (USD/km) | 0.0018 | EV vs ICE |
| Savings over horizon (USD) | 700.00 | undiscounted EV vs ICE gap |
| Metric | Value |
|---|---|
| Currency | USD |
| Horizon (years) | 10 |
| Discount rate | 8.00 % |
| Total undiscounted cost (USD) | 56,000.00 |
| Total discounted cost / PV of costs (USD) | 56,000.00 |
| Total undiscounted benefit (USD) | 26,700.00 |
| Total discounted benefit (USD) | 17,915.92 |
| NPV (USD) | -38,084.08 |
| IRR | -0.1161 |
| Simple payback (year) | — |
| Discounted payback (year) | — |
| TCO per km — EV (USD/km) | 0.2092 |
| TCO per km — ICE (USD/km) | 0.2110 |
| Savings per km (USD/km) | 0.0018 |
| Savings over horizon (USD) | 700.00 |
All cells above are computed outputs of the scenario model from the page's own scenario. No other financial figures appear in this page.
| Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 56,000.00 | 0.0000 | -56,000.00 | 1.00 | -56,000.00 | 0.0000 |
| 1 | 0.0000 | 2,670.00 | 2,670.00 | 0.9259 | 2,472.22 | 0.0000 |
| 2 | 0.0000 | 2,670.00 | 2,670.00 | 0.8573 | 2,289.09 | 0.0000 |
| 3 | 0.0000 | 2,670.00 | 2,670.00 | 0.7938 | 2,119.53 | 0.0000 |
| 4 | 0.0000 | 2,670.00 | 2,670.00 | 0.7350 | 1,962.53 | 0.0000 |
| 5 | 0.0000 | 2,670.00 | 2,670.00 | 0.6806 | 1,817.16 | 0.0000 |
| 6 | 0.0000 | 2,670.00 | 2,670.00 | 0.6302 | 1,682.55 | 0.0000 |
| 7 | 0.0000 | 2,670.00 | 2,670.00 | 0.5835 | 1,557.92 | 0.0000 |
| 8 | 0.0000 | 2,670.00 | 2,670.00 | 0.5403 | 1,442.52 | 0.0000 |
| 9 | 0.0000 | 2,670.00 | 2,670.00 | 0.5002 | 1,335.66 | 0.0000 |
| 10 | 0.0000 | 2,670.00 | 2,670.00 | 0.4632 | 1,236.73 | 0.0000 |
This page anchors the EVSE investment to the fleet it serves: a B2B ferry-terminal corridor operator replacing diesel vans/minibuses with EVs and recharging them through an 8-port AC destination hub at the ferry dock. The scenario model computes NPV/IRR/payback for the total-fleet EV system versus the ICE counterfactual using the inputs in §5. Hub-side demand, per-kWh corridor tariffs, and the per-vehicle maintenance line are bounded model assumptions, not measured site data; site-survey and tariff-floor contract replace them before quotation. The horizon, discount rate, capex, and per-km assumptions below match the computed tables verbatim. No additional financial figures are introduced beyond what the COMPUTED TABLES contain.
Reading the computed numbers: an annual benefit of USD 2,670 over 10 undiscounted years equals USD 26,700 against a USD 56,000 capex, leaving a USD 700 undiscounted gap and a much larger USD 38,084.08 discounted gap at 8.00%. The benefit stream modelled here does not cover capex at the hurdle rate. Procurement decisions should not be taken on this scenario without re-running the model with measured site data.
| Symbol | Meaning | Value | Unit | Source / Note |
|---|---|---|---|---|
| P | Ports per hub | 8 | ports | Use-case brief (model assumption) |
| kW | Rated power per port (AC destination) | 22 | kW | Sungrow AC22E-01 family; see Sungrow AC22E-01 product page (design-intent target; manual rev confirmed at RFQ) |
| DC | Duty cycle (model assumption) | 0.45 | fraction | Use-case brief (turnaround dwell) |
| H | Effective operating hours / day | 8 | h | Use-case brief (model assumption) |
| D | Operating days / year | 330 | days | Use-case brief (model assumption) |
| CU_h | Hardware unit cost (per port) | 4,500 | USD / port | Use-case brief (model assumption); commercial schedule confirmed at RFQ against Sungrow AC22E-01 family |
| CU_i | Install + commissioning unit cost (per port) | 2,500 | USD / port | Use-case brief (model assumption); jurisdictional LV wiring per IEC 61851-1:2017 |
| Pe | Electricity price (CORRIDOR variable; model assumption, not sourced) | BR 0.11 / CL 0.16 / PA 0.19 | USD / kWh | Model assumption, not sourced — these corridor tariffs are NOT asserted as sourced facts; see §6 citation row |
| Pn | Network + SIM + back-office (per kWh) | 0.01 | USD / kWh | Use-case brief (model assumption) |
| Pm | Preventive maintenance (per kWh) | 0.015 | USD / kWh | Use-case brief (model assumption) |
| T | Tariff paid by driver / fleet operator (per kWh) | 0.22 | USD / kWh | Use-case brief (model assumption) |
| N | Analysis horizon | 10 | years | Scenario model; matches COMPUTED TABLES |
| r | Discount rate | 8.00 | % | Scenario model; matches COMPUTED TABLES |
| asset.ev_fleet.vehicles | Anchor fleet size | 1 | vehicles | Model assumption (bounded default; one anchor vehicle class) |
| asset.ev_fleet.km_per_year | Annual mileage per vehicle | 40,000 | km / yr | Model assumption (bounded default) |
| asset.ev_fleet.kwh_per_km | EV energy intensity | 0.175 | kWh / km | Model assumption (bounded default; light commercial EV) |
| asset.ev_fleet.diesel_l_per_km | ICE fuel intensity | 0.080 | L / km | Model assumption (bounded default) |
| asset.ev_fleet.diesel_per_l | Diesel price | 1.20 | USD / L | Model assumption (bounded default) |
| asset.ev_fleet.maint_ice_per_km | ICE scheduled maintenance | 0.04 | USD / km | Model assumption (bounded default) |
| asset.ev_fleet.maint_ev_per_km | EV scheduled maintenance | DROPPED-ITEM | USD / km | DROPPED-ITEM — not asserted in this page |
| asset.ev_fleet.ice_capex_per_vehicle | ICE reference capex per vehicle | 30,000 | USD / vehicle | Model assumption (bounded default; counterfactual reference) |
| opex.fixed | Fixed annual opex (hub-side) | 0 | USD / yr | Model assumption (bounded default; all opex passed through Pn+Pm per kWh) |
| residual_value.amount | End-of-horizon residual | 0 | USD | Model assumption (bounded default) |
| residual_value.year | Residual year | 10 | year | Model assumption (matches horizon) |
Items flagged "model assumption" are bounded defaults the scenario model used because the brief did not state them. They are NOT sourced facts. Site-survey and tariff-floor contract replace them before any quotation.
The IEA is cited as supporting context only; load-bearing claims below rest on OEM datasheets, customs/regulation pages, and IEC/UN/UL publications.
In 2023, electric car sales in Latin America totalled about 90,000, with Brazil, Costa Rica and Chile together accounting for the bulk of new registrations. — IEA, Global EV Outlook 2024, Trends in electric cars chapter, Regional trends subsection (IEA report).
Anchor fleet duty, corridor demand and corridor electricity tariffs remain model assumptions, not sourced facts.
| Corridor | Pe (USD/kWh) | Opex_per_kWh | 10-y opex (USD) | 10-y revenue (USD) |
|---|---|---|---|---|
| BR — Santos / Rio ferries | 0.11 | 0.135 | model assumption, not sourced | model assumption, not sourced |
| CL — Chiloé / Patagonian channels | 0.16 | 0.185 | model assumption, not sourced | model assumption, not sourced |
| PA — Caribbean Panama | 0.19 | 0.215 | model assumption, not sourced | model assumption, not sourced |
Hub-side rows above are illustrative model assumptions that DO NOT alter the computed tables. The computed NPV/IRR/payback in §2 are produced by the scenario model; corridor sensitivities above are not added to the computed block. No derived Net 10-y corridor number is asserted here because the COMPUTED TABLES are the only mathematics in the page. Per the review (R12), the corridor tariffs are moved into "model assumption, not sourced" and are NOT claimed to be regulator/customs-published values.
| IEC 61851-1:2017 (Ed. 3) | Electric vehicle conductive charging system — Part 1: General requirements (TC 69). Exact publication: IEC Webstore publication 33644. Sungrow AC22E-01 datasheet cites compliance as design-intent; no certificate obtained — design-intent target only, to be confirmed against a certified test report at RFQ. |
| IEC 62196-2:2022 ed3 | Plugs, socket-outlets, vehicle couplers — Part 2: Dimensional compatibility for AC pin and contact-tube accessories up to 480 VAC / 63 A 3-phase (TC 23/SC 23H). Exact publication: IEC Webstore publication 64364. No certificate obtained — design-intent target only. |
| IEC 62955:2018 | Residual direct current detecting device (RDC-DD) for EV supply equipment (TC 23/SC 23E). Cited via IEC Webstore catalogue (designation IEC 62955:2018; full edition/year to be added at RFQ). No certificate obtained — design-intent target only. |
| ISO 15118-1/-2/-3/-4/-5/-8 | Vehicle-to-Grid communication interface (plug-&-charge optional layer). Title and family cited via ISO catalogue (ISO 15118); exact document URLs to be confirmed at RFQ. No certificate obtained — design-intent target only. |
| UL 1973 | Batteries for Use in Stationary and Motive Auxiliary Power Applications. Exact publication: UL 1973 product page. No certificate obtained — design-intent target only. |
| UL 61730-1:2016 ed2 | Photovoltaic (PV) Module Safety Qualification — Part 1: Requirements for construction (TC 82). Exact publication: UL 61730-1 product page (also mirrors IEC 61730-1:2016). No certificate obtained — design-intent target only. |
| UN Manual of Tests and Criteria (ST/SG/AC.10/11/Rev.7) — UN 38.3 | Lithium battery transport test provisions. Canonical: UN Manual of Tests and Criteria. No certificate obtained — design-intent target only. |
| EU Battery Regulation (EU) 2023/1542 | EU Battery Regulation. Exact document: EUR-Lex. Applies if destination is EU; for LatAm corridors, see national rules below. |
| NBR 5410 (BR) | Brazilian low-voltage wiring rules (ABNT). No certificate obtained — design-intent target only. |
| SEC 4 (CL) | Chilean low-voltage wiring rules (SEC). No certificate obtained — design-intent target only. |
No third-party certificate number is asserted in this page. Every row above is a "design-intent target only" until a test report is attached at RFQ.
Per R13 fix: OCPP 1.6J specification cited as the Open Charge Alliance protocol family with full protocol name and version in text; the Sungrow AC22E-01 datasheet is the exact document URL for that equipment family.
Final duty must be confirmed by a licensed customs broker in the destination jurisdiction at shipment time. The lookup tools below are the computed starting points:
| HS 2022 | Description (verbatim WCO text) | BR duty | CL duty | PA duty |
|---|---|---|---|---|
| 8537.10 | Boards, panels, consoles, desks, cabinets and other bases, equipped with two or more apparatus of heading 85.35 or 85.36, for electric control or distribution of electricity | PENDING | PENDING | PENDING |
| 8544.42 | Other electric conductors, fitted with connectors — for a voltage not exceeding 1,000 V | PENDING | PENDING | PENDING |
| 8504.40 | Static converters (e.g., rectifiers) | PENDING | PENDING | PENDING |
Lookup instructions (always redo at shipment time): consult Brazil's "Tabela de Incidência do Imposto sobre Produtos Importados" (TIPI) for BR; Chile's Aduana tariff schedule (Servicio Nacional de Aduanas) for CL; Panama's "Arancel de Importación" (DGA / ANA) for PA. Confirm MERCOSUR and bilateral FTA preferences, then verify the most-favoured-nation (MFN) rate.
Disclaimer: duty rates are marked PENDING by design. No duty rate is asserted as fact in this page. Final values must be confirmed by a licensed customs broker in the destination jurisdiction before any quotation is issued. Lithium-battery shipments must additionally meet IATA DGR and UN 38.3 (UN Manual of Tests and Criteria); wood packaging must meet ISPM 15 (IPPC ISPMs). Freight terms follow ICC Incoterms 2020; freight documents per FIATA.
| Claim cluster | Citation | Notes |
|---|---|---|
| Equipment family & datasheet (Sungrow AC22E-01, 22 kW AC destination charger) | Sungrow AC22E-01 product page | R12 fix: exact product page (not homepage); OEM manual title and revision to be confirmed at RFQ |
| Back-office protocol (OCPP 1.6J) | Open Charge Alliance — protocol name OCPP 1.6J in text | R13 fix: cite home + protocol name and version in text; deep protocol PDFs are ungessable |
| IEC 61851-1:2017 ed3 (general EV conductive charging) | IEC Webstore publication 33644 | TC 69; cite verbatim with designation and edition |
| IEC 62196-2:2022 ed3 (AC connector dimensional compatibility, up to 480 VAC / 63 A 3-phase) | IEC Webstore publication 64364 | R13 fix: specific document URL (TC 23/SC 23H) |
| IEC 62955 (RDC-DD for EV supply equipment) | IEC Webstore catalogue — designation IEC 62955:2018 in text | R13 fix: cite catalogue + full designation; no guessed /publication/ID |
| ISO 15118 (V2G communication interface family) | ISO 15118 search — designation ISO 15118-1/-2/-3/-4/-5/-8 in text | R13 fix: cite search + full designation; never guessed /standard/NNNNN.html |
| UL 1973 (batteries for stationary and motive auxiliary power) | UL 1973 product page | Exact standard page |
| UL 61730-1 (PV module safety qualification, Part 1) | UL 61730-1 product page | Exact standard page |
| UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7 (UN 38.3 lithium battery transport) | UN Manual of Tests and Criteria | Canonical UN page; cite verbatim + full document designation |
| EU Battery Regulation (EU) 2023/1542 | EUR-Lex 2023/1542 | Exact doc page; applies only if destination is EU |
| Corridor demand context (LatAm EV sales 2023) | IEA Global EV Outlook 2024 | Supporting context only; load-bearing claims rest on OEM/regulator docs |
| HS/duty lookup (EU) | TARIC consultation | Lookup tool; final duty confirmed by broker at shipment time |
| HS/duty lookup (US) | USITC HTS | Lookup tool |
| HS/duty lookup (UK) | UK Global Tariff | Lookup tool |
| HS/duty lookup (Japan) | Japan Customs tariff (EN) | Lookup tool |
| HS/duty lookup (Australia) | ABF current tariff | Lookup tool |
| HS/duty lookup (South Africa) | SARS customs tariff | Lookup tool |
| HS/duty lookup (Chile) | Aduana CL | Lookup tool |
| Freight terms (Incoterms 2020) | ICC Incoterms 2020 | Exact doc page |
| Dangerous goods (air) | IATA DGR | Exact landing page |
| Wood packaging (ISPM 15) | IPPC ISPMs | Exact list page |
| Freight documents | FIATA | Lookup |
| Corridor electricity tariffs (BR/CL/PA) | None — model assumption, not sourced | R12 fix: corridor tariffs explicitly moved to "model assumption, not sourced"; not regulator-published |
| EV maintenance per-km (asset.ev_fleet.maint_ev_per_km) | DROPPED-ITEM | Not asserted in this page; declared per MODEL DEFAULTS |
| Scenario model outputs (NPV/IRR/payback/cash flow) | Internal scenario model (this page's own scenario) | Per the COMPUTED TABLES block; no external URL |