Tradvolt › TCO › Singapore › CATL EnerC 1 MWh › Peak-Shaving

Import CATL EnerC 1 MWh LFP Container BESS from China to Singapore — Commercial Peak-Shaving — Total Cost of Ownership

Verdict (evidence-date 2026-09-22): On the bounded defaults in Section 5, the scenario TCO model over a 25-year horizon at an 8.00% discount rate returns NPV = -SGD 2,120,443.92, simple payback = none, discounted payback = none, IRR = -0.0910, and LCOS = SGD 0.8862/kWh. Equipment: Contemporary Amperex Technology Co., Limited (CATL) EnerC, 1 MWh-class LFP containerised BESS (1C / 0.5C variant). Location: Singapore. Horizon: 25 years. Evidence-date: 2026-09-22. Limitation: per-kWh charge cost (SGD 0.25/kWh) and per-kWh discharged value (SGD 0.381/kWh) are explicit model assumptions, not sourced facts; replace with your retail tariff schedule and validated OEM throughput curves before relying on the output. Verdict: do not proceed on these inputs.[1][2]

Decision inputValueNote
Equipment / OEMCATL EnerC 1 MWh-class LFP container BESS (1C / 0.5C variant)OEM: Contemporary Amperex Technology Co., Limited (CATL)
LocationSingaporeEMA grid, SCDF fire scope, Singapore Customs
Horizon25 yearsMatches table inputs
Discount rate8.00 %Matches table inputs
CapEx (lump-sum, year 0)SGD 2,400,000.00Matches table inputs
NPVSGD -2,120,443.92From COMPUTED TABLES
Simple paybacknoneBenefits never recover CapEx on cash basis inside horizon
Discounted paybacknoneBenefits never recover CapEx on PV basis inside horizon
IRR-0.0910 (-9.10%)From COMPUTED TABLES
LCOSSGD 0.8862 / kWhPV of costs ÷ lifetime discounted kWh delivered (see Section 11)
VerdictDo not proceed on these inputsRe-run with RFQ-confirmed CapEx and a tariff spread that yields a positive NPV

Request Quote — replies within 48h

1. Equipment Reference (OEM + Model)

2. Computed TCO Summary (verbatim from scenario model)

TCO summary
MetricValue
CurrencySGD
Horizon (years)25
Discount rate8.00 %
Total undiscounted cost (SGD)2,400,000.00
Total discounted cost / PV of costs (SGD)2,400,000.00
Total undiscounted benefit (SGD)607,829.09
Total discounted benefit (SGD)279,556.08
NPV (SGD)-2,120,443.92
IRR-0.0910
Simple payback (year)—
Discounted payback (year)—
LCOS (SGD/kWh)0.8862

3. Year-by-Year Cash Flow (verbatim from scenario model)

Year-by-year cash flow
YearCost (SGD)Benefit (SGD)Net (SGD)Discount factorDiscounted net (SGD)Energy (kWh)
02,400,000.000.0000-2,400,000.001.00-2,400,000.000.0000
10.000030,657.0030,657.000.925928,386.11297,000.00
20.000030,043.8630,043.860.857325,757.77291,060.00
30.000029,442.9829,442.980.793823,372.79285,238.80
40.000028,854.1228,854.120.735021,208.64279,534.02
50.000028,277.0428,277.040.680619,244.88273,943.34
60.000027,711.5027,711.500.630217,462.95268,464.48
70.000027,157.2727,157.270.583515,846.01263,095.19
80.000026,614.1226,614.120.540314,378.78257,833.28
90.000026,081.8426,081.840.500213,047.41252,676.62
100.000025,560.2125,560.210.463211,839.32247,623.09
110.000025,049.0025,049.000.428910,743.09242,670.62
120.000024,548.0224,548.020.39719,748.36237,817.21
130.000024,057.0624,057.060.36778,845.73233,060.87
140.000023,575.9223,575.920.34058,026.68228,399.65
150.000023,104.4023,104.400.31527,283.47223,831.66
160.000022,642.3122,642.310.29196,609.08219,355.02
170.000022,189.4722,189.470.27035,997.12214,967.92
180.000021,745.6821,745.680.25025,441.83210,668.56
190.000021,310.7621,310.760.23174,937.96206,455.19
200.000020,884.5520,884.550.21454,480.74202,326.09
210.000020,466.8620,466.860.19874,065.86198,279.57
220.000020,057.5220,057.520.18393,689.39194,313.98
230.000019,656.3719,656.370.17033,347.78190,427.70
240.000019,263.2419,263.240.15773,037.80186,619.14
250.000018,877.9818,877.980.14602,756.52182,886.76

4. CapEx Breakdown (Landed Cost to Singapore)

Line itemValueUnitNotes / Source
Equipment modelCATL EnerC 1 MWh class (1C / 0.5C variant)—CATL ESS landing; procedure limits per OEM Installation & Operation Manual, current rev (RFQ)[3]
Battery capacity (nameplate)1.0MWhUse-case requirement[4]
Cell chemistryLFP (LiFePO₄)—CATL ESS vertical[3]
EXW unit price (battery + PCS + EMS + container)PENDING — quote on RFQUSD / MWhOEM quotation
Ocean freight (CN → SG, 20 ft FCL)PENDING — quote on RFQUSDFIATA freight forwarder quotation; FIATA[5]
Origin export clearance & docsPENDING — quote on RFQUSDChina customs broker
Marine insurance (0.3%–0.5% of CIF)PENDING — quote on RFQUSDMarine cargo policy — Institute Cargo Clauses (A) wording; verify rate with insurer quotation[6]
Singapore Customs dutyPENDING — Singapore Customs lookupSGDSingapore Customs HS code lookup / TradeNet[7]
GST (Singapore)PENDING — IRAS lookupSGDIRAS — current rate and any import reliefs[8]
Last-mile delivery + lifting (Singapore)PENDING — quote on RFQSGDLocal logistics quotation
Installation & commissioningPENDING — quote on RFQSGDEPC / OEM scope per CATL EnerC Installation & Operation Manual, current rev[3]
Certification & grid compliance (EMA)PENDING — quote on RFQSGDEMA-licensed certifier quotation; EMA[9]

5. Bounded Model Assumptions (not sourced facts)

The draft did not state the per-unit economics that drive the benefit stream. The scenario model was supplied with the following bounded defaults. Replace each with RFQ- and tariff-confirmed values before relying on the output.

Model inputDefault usedSource / convention
opex.fixed (annual fixed OpEx)SGD 0 / yrModel default — no fixed OpEx recognised inside horizon
opex.escalation_pct0.0 % / yrModel default — flat OpEx; escalate to your site's opex escalation if non-zero
residual_value.amountSGD 0Model default — no terminal salvage
residual_value.yearn/a (residual = 0)Model default
asset.ess.degradation_pct_per_year2.0 %Model default consistent with year-1 delivered energy of 297,000 kWh falling to 182,886.76 kWh by year 25 (see Energy column of cash-flow table)
asset.ess.charge_cost_per_kwhSGD 0.25 / kWhModel assumption — Singapore regulated low-tension tariff band; verify with SP Group published tariff
asset.ess.value_per_kwh_dischargedSGD 0.381 / kWhModel assumption — net of charge cost and 90% round-trip efficiency; reconciles to year-1 benefit of SGD 30,657.00 at 297,000 kWh delivered
Round-trip efficiency (used)90 %Implied by benefit formula; OEM-published RTE for CATL EnerC to be confirmed at RFQ against the OEM Installation & Operation Manual, current rev[3]
Depth of discharge90 %Conservative for LFP cycle life; per OEM warranty terms[3]
Cycles per year1 cycle / dayModel assumption (= 330 cycles / yr against a 360-day dispatch window); OEM cycle-life curve to confirm[3]
Auxiliary load (cooling, BMS, controls)3%–5% of nameplateIndustry convention; OEM datasheet to confirm[3]
Routine O&M1%–2% of CapEx / yrIndustry convention; OEM warranty / service-contract terms to confirm[3]
Marine insurance0.3%–0.5% of CIFIndustry convention for containerised BESS; insurer quotation to confirm[6]

6. Compliance, Certifications & Grid Connection

Disclaimer: Tradvolt does not warrant that the certifications listed above are held by any specific OEM model. Final certification evidence must be requested via the RFQ form and verified with the issuing body.

7. Duty & HS Code Stack (Singapore)

HS national lineProgramAs-ofSoT
PENDING — lookup (likely Chapter 85, lithium-ion battery storage apparatus) PENDING — lookup (Singapore Customs duty) 2026-09-22 Singapore Customs HS code lookup / TradeNet[7]
PENDING — lookup (same HS line) PENDING — lookup (Singapore GST / IRAS) 2026-09-22 IRAS[8]

Rate entries are marked PENDING — lookup and must be confirmed against the official Singapore Customs HS lookup and IRAS before any landed-cost commitment.

8. Request a Quote (RFQ) — replies within 48h

9. Frequently Asked Questions

Q1. Does the 1 MWh CATL EnerC BESS pay back within 25 years in Singapore on the bounded model defaults?

No. On the bounded defaults in Section 5 the scenario model returns NPV = -SGD 2,120,443.92, simple payback = none, discounted payback = none, LCOS = SGD 0.8862/kWh, IRR = -0.0910. Replace the per-kWh charge cost (SGD 0.25/kWh) and per-kWh discharged value (SGD 0.381/kWh) with your tariff schedule and the OEM's RTE and cycle-life curves from the CATL EnerC Installation & Operation Manual, current revision, before relying on the output.

Q2. What HS code applies to a CATL EnerC LFP container BESS imported into Singapore?

Lithium-ion battery storage systems typically fall under Chapter 85 of the Singapore Harmonized System. The exact national line, applicable duty rate, and any GST treatment must be confirmed on the Singapore Customs HS code lookup and via IRAS.

Q3. Which OEM and exact model designation is the basis of this TCO?

Contemporary Amperex Technology Co., Limited (CATL), EnerC 1 MWh-class LFP containerised BESS, 1C / 0.5C configurable variant. See the CATL ESS product landing; SOC window, max charge/discharge C-rate, DC bus voltage window, and torque values must be confirmed against the CATL EnerC Installation & Operation Manual, current revision at RFQ stage.

Q4. Which safety and grid standards apply to LFP BESS in Singapore?

Commonly referenced: IEC 62619:2022 (industrial lithium cells), IEC 63056:2020 (BESS DC supply), UL 9540:2020 / UL 9540A:2019 (BESS and thermal runaway), UN 38.3 (UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7), CE/EMC for EU-bound units, and Singapore-specific grid compliance via EMA. Fire-safety scope with SCDF must be confirmed with the appointed Qualified Person.

Q5. What shipping terms does Tradvolt support for Singapore?

Common Incoterms are EXW, FOB, CIF, and DDP Singapore (per ICC Incoterms 2020). State your preference in the RFQ form.

10. Sources & Footnotes

  1. Verdict inputs and decision rule are derived from the scenario model's COMPUTED TABLES (Section 2 and Section 3) on this page.
  2. All financial figures on this page are the COMPUTED TABLES' outputs; no other financial figure is asserted in prose. Currency: SGD. Horizon: 25 years. Discount rate: 8.00%.
  3. CATL ESS product landing — https://www.catl.com/en/ess/. Model designation: EnerC, 1 MWh class, 1C / 0.5C configurable variant. Specific SOC window, max C-rate, DC bus voltage window, and torque values are taken from the CATL EnerC Installation & Operation Manual, current revision; that document is JS-gated on the OEM site and the revision number + date must be confirmed at RFQ stage before any torque, SOC, or voltage figure is cited.
  4. Battery capacity (nameplate 1.0 MWh) is the use-case requirement set in this scenario; the OEM datasheet figure must be cross-checked at RFQ.
  5. FIATA — https://fiata.org/ (freight forwarding documents and negotiable FIATA B/L). Freight rate to be obtained from a FIATA-member forwarder.
  6. Institute Cargo Clauses (A) policy wording publisher — IUA clauses library — https://www.iua.co.uk/clauses. Rate band 0.3%–0.5% of CIF is industry convention for containerised BESS; insurer quotation to confirm.
  7. Singapore Customs — https://www.customs.gov.sg/ (HS code lookup / TradeNet). Rate entries marked PENDING — lookup until confirmed.
  8. IRAS — https://www.iras.gov.sg/ (current GST rate and any import reliefs).
  9. EMA Singapore — https://www.ema.gov.sg/ (grid connection and generator/storage licensing).
  10. IEC Webstore catalogue — https://webstore.iec.ch/. Specific designations cited in text: IEC 62619:2022 (Secondary cells and batteries containing alkaline or other non-acid electrolytes — Safety requirements for secondary lithium cells and batteries for industrial applications, edition 2, 2022); IEC 63056:2020 (DC supply for battery energy storage systems, edition 1, 2020). Edition-specific URLs are not enumerated in the IEC catalogue; cite designation + edition in procurement documents.
  11. UL Standards shop — https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973. Specific designations cited in text: UL 9540, 2nd Edition (2020) — Energy Storage Systems; UL 9540A, 4th Edition (2019) — Test Method for Evaluating Thermal Runaway Fire Propagation (Suffix to UL 9540). UL 1973 (adjacent cell standard) is shown on the shop page.
  12. UN Manual of Tests and Criteria — https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria — UN 38.3 lithium battery test provisions, document designation ST/SG/AC.10/11/Rev.7. Canonical UN page is bot-walled for automated checks.
  13. Regulation (EU) 2023/1542 (EU Battery Regulation) — https://eur-lex.europa.eu/eli/reg/2023/1542/oj.
  14. ICC Incoterms 2020 — https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/.
  15. CE marking framework — https://single-market-economy.ec.europa.eu/single-market/ce-marking_en.
  16. SCDF — https://www.scdf.gov.sg/ (fire safety).
  17. Tradvolt RFQ form — https://tradvolt.com/rfq/ (live; use for ALL RFQ CTAs; only site paths that exist: /, /tco/, /guides/, /suppliers/, /rfq/, /rfq/thanks, /assets/*).
  18. IATA Dangerous Goods (DGR) programme — https://www.iata.org/en/programs/cargo/dgr/ (air-freight scope, if applicable).

11. LCOS Formula Disclosure

LCOS is defined as PV of costs ÷ lifetime discounted kWh delivered. PV of costs = SGD 2,400,000.00 (Section 2). Lifetime discounted kWh delivered is the sum of Energy (kWh) × Discount factor across years 1–25 of the Section 3 cash-flow table. Because the model's per-kWh charge cost (SGD 0.25/kWh) and per-kWh discharged value (SGD 0.381/kWh) are bounded model assumptions, the headline LCOS of SGD 0.8862/kWh is scenario-dependent and must not be quoted as a sourced fact.

Disclaimer: All numbers in the COMPUTED TABLES are the only financial figures on this page and are computed for the bounded defaults stated in Section 5. Tradvolt does not warrant any specific OEM performance, certification status, or duty outcome until validated by the issuing body and the official Singapore Customs tariff lookup. Replace every PENDING — lookup marker with values confirmed against the named portals before any procurement decision.