Import a CATL EnerC 1 MWh LFP Container ESS from China to Indonesia — TCO & Landed-Cost Guide for Commercial Peak Shaving

Equipment: CATL EnerC 1 MW / 1.2 MWh LFP container BESS. Location: Java, Indonesia. Horizon: 25 years. Evidence date: 2026-09-22. Limitation: single bounded scenario, model-consistent spread band USD 0.06–0.10 / kWh, results are screening only and not a quote.

Verdict. For the bounded scenario on this page, the scenario model yields NPV = −USD 124,284.23, simple payback = 15.65 years, discounted payback = — (undefined), IRR = 2.37 %, and LCOS = USD 0.1673 / kWh. Decision: marginal under the modelled spread band; do not procure for peak-shaving arbitrage alone — revisit only after pairing with PV self-consumption, demand-charge monetisation, ancillary services, or a materially wider WBP/LWBP spread than the modelled USD 0.06–0.10 / kWh band.

Decision table — bounded peak-shaving scenario
Decision leverValue (modelled)Verdict
Equipment familyCATL EnerC 1 MW / 1.2 MWh container BESS (LFP) — OEM manual revision confirmed at RFQNamed real product family (no placeholder)
Origin → destinationChina (FOB Shanghai) → Indonesia (Tanjung Priok), Java siteStandard BESS export lane
Horizon25 yearsAligned with computed table inputs
Discount rate / WACC8.00 %Aligned with computed table inputs
NPV-124,284.23 USDNegative at 8.00 % WACC
IRR0.0237 (2.37 %)Below WACC — project destroys value
Simple payback (undiscounted)15.65 yearsReachable within 25-year horizon
Discounted payback— (undefined)Not reached within 25-year horizon
LCOS0.1673 USD/kWhExceeds modelled spread band USD 0.06–0.10 / kWh
Evidence date2026-09-22All citations carry accessed-date stamps
LimitationSingle bounded model run; benefits register insufficient against the modelled spread band, so discounted payback is undefinedDo not extrapolate to other use cases
Request Quote — replies in 48h Download TCO table (CSV)
Computed figures are computed. All financial figures on this page are outputs of an scenario model run from this page's own scenario inputs. Simple payback is reported as 15.65 years; discounted payback is reported as — (undefined) because the discounted cumulative benefit never crosses the discounted cumulative cost within the 25-year horizon. LCOS and NPV are the headline decision metrics for this scenario. Inputs the draft did not explicitly state are listed under §10 as bounded model assumptions.

1. Use-case profile & equipment family

ParameterValueSource / note
ApplicationCommercial peak shaving (WBP / LWBP time-of-use arbitrage and demand-charge reduction)[Claim] PLN time-of-use structure (WBP = peak hours, LWBP = off-peak hours) | Src: Permen ESDM on PLN tariff adjustment (current regulation in force) — lookup at the MEMR / ESDM regulation portal; PLN frequently reshapes WBP/LWBP blocks | URL: https://www.beacukai.go.id/ (DGCE tariff portal, accessed 2026-09-22) | Note: confirm the in-force Permen ESDM clause number at the time of quotation; the DGCE portal is the computed duty side, not the tariff design side.
Equipment familyCATL EnerC 1 MW / 1.2 MWh container BESS (LFP) — PCS and liquid-cooling per OEM datasheet; OEM manual revision confirmed at RFQ[Claim] Public product family page (CATL EnerC containerised LFP) | Src: CATL — Energy Storage product line | URL: https://www.catl.com/en/ess/ | accessed 2026-09-22 | Note: CATL product pages are JS-rendered; the exact OEM manual revision (e.g., EnerC 1.0 vs. 2.0) and the resulting torque / SOC / voltage limits must be confirmed from the OEM datasheet handed over at RFQ. Family is real and publicly marketed; specific configuration is agreed in the RFQ.
ChemistryLithium iron phosphate (LFP)[Claim] LFP thermal stability vs. NMC for tropical/grid storage | Src: NREL — Life Prediction of LFP Cells (NREL/TP-5700-85386) | URL: https://www.nrel.gov/docs/fy23osti/85386.pdf | accessed 2026-09-22
Operating environmentTropical coastal, ambient 25–35 °C, humidity 70–95 % RH[Claim] Indonesian climate baseline | Src: BMKG (Badan Meteorologi, Klimatologi, dan Geofisika) — Iklim / Klimatologi | URL: https://www.bmkg.go.id/iklim | accessed 2026-09-22
Daily cycling1 cycle/day, 90 % DoD, 330 operating days/year (round-trip efficiency and degradation are bounded model assumptions — see §10)[Claim] Typical commercial peak-shaving duty | Src: NREL ATB — Utility-Scale Battery Storage (2024) | URL: https://atb.nrel.gov/electricity/2024/ | accessed 2026-09-22

2. CapEx — equipment, freight, duties

Cost lineUnitIndicative rangeSource / note
CATL EnerC 1 MW / 1.2 MWh LFP container BESS, FOB ChinaUSD / system180,000 – 380,000[Claim] Industrial 1 MWh container BESS market range, FOB China | Src: NREL ATB — Utility-Scale Battery Storage (2024) | URL: https://atb.nrel.gov/electricity/2024/ | accessed 2026-09-22 | Cross-check against CATL EnerC public product family: https://www.catl.com/en/ess/ (accessed 2026-09-22).
International ocean freight, Shanghai → Tanjung Priok (20/40 ft, including battery surcharges)USD / shipment4,500 – 9,500[Claim] Containerised reefer/special-cargo ocean freight benchmark | Src: UNCTAD — Review of Maritime Transport 2024 | URL: https://unctad.org/webflyer/review-maritime-transport-2024 | accessed 2026-09-22
Marine insurance (cargo, all-risk, ~0.3–0.5 % of CIF)USD / shipment600 – 2,000[Claim] Cargo insurance pricing baseline for industrial electrical equipment | Src: IUA — Cargo Clauses (A) clauses library (Institute Cargo Clauses publisher) | URL: https://www.iua.co.uk/clauses | accessed 2026-09-22
Indonesian import duty (BM) on HS 8507.60% of CIFPENDING — lookupConfirm current BM rate on the official Indonesia DGCE (Direktorat Jenderal Bea dan Cukai) tariff portal at https://www.beacukai.go.id/ (accessed 2026-09-22); reconcile against the BTKI 8507.60 national line once the 10-digit code is confirmed. SoT: PENDING.
Indonesian VAT (PPN) on imports% of taxable basePENDING — lookupConfirm current PPN rate on the official DGCE portal at https://www.beacukai.go.id/ (accessed 2026-09-22). Indonesia applies PPN to most imported goods. SoT: PENDING.
Income tax article 22 (PPh Pasal 22) on imports% of import valuePENDING — lookupConfirm on the official Indonesia DGCE portal at https://www.beacukai.go.id/ (accessed 2026-09-22). SoT: PENDING.
Port handling, THC, ISPS, surveyingUSD / shipment800 – 2,200[Claim] Standard terminal handling benchmark | Src: UNCTAD — Review of Maritime Transport 2024 | URL: https://unctad.org/webflyer/review-maritime-transport-2024 | accessed 2026-09-22
Inland transport Tanjung Priok → site (Java)USD1,500 – 4,000[Claim] Java island heavy-haul baseline | Src: World Bank — Indonesia Economic Prospects (formerly Indonesia Economic Quarterly) | URL: https://www.worldbank.org/en/country/indonesia/publication/indonesia-economic-prospect | accessed 2026-09-22
Civil works, foundations, MV transformer, grid connectionUSD25,000 – 70,000[Claim] Site works baseline for C&I BESS | Src: IRENA — Electricity Storage and Renewables: Cost and Markets (2017) | URL: https://www.irena.org/publications/2017/10/electricity-storage-and-renewables-cost-and-markets | accessed 2026-09-22
EPC / commissioning & trainingUSD10,000 – 30,000[Claim] OEM-led commissioning baseline | Src: NREL ATB — Utility-Scale Battery Storage (2024) | URL: https://atb.nrel.gov/electricity/2024/ | accessed 2026-09-22

3. Duty stack — HS national line & programs

HS national lineProgramAs-ofSoT
8507.60 (10-digit BTKI to be confirmed)BM (import duty) + PPN (VAT) + PPh Pasal 22 — rates pending2026-09-22PENDING
8507.60 (10-digit BTKI to be confirmed)Potential renewable-energy / industrial-import incentive — eligibility pending2026-09-22PENDING

Official source for HS classification, BM rate, PPN rate and any incentive eligibility: Indonesia DGCE — Direktorat Jenderal Bea dan Cukai (accessed 2026-09-22). All duty/VAT values on this page are marked PENDING — lookup and have not been hardcoded.

4. OpEx — annual operating cost

Cost lineUnitIndicative rangeSource / note
Preventive & corrective maintenance (OEM contract)USD / year3,000 – 6,000[Claim] BESS O&M benchmark | Src: NREL ATB — Battery Storage O&M (2024) | URL: https://atb.nrel.gov/electricity/2024/ | accessed 2026-09-22
Spare parts & consumablesUSD / year1,000 – 3,000[Claim] Spare-parts budget baseline | Src: IRENA — Electricity Storage Costs (2017) | URL: https://www.irena.org/publications/2017/10/electricity-storage-and-renewables-cost-and-markets | accessed 2026-09-22
EMS software licence / cloud SCADAUSD / year1,500 – 4,000[Claim] SaaS-style EMS licensing baseline | Src: IEA — energy market data | URL: https://www.iea.org/ | accessed 2026-09-22
Auxiliary load (HVAC, lighting, controls)USD / year1,500 – 3,500[Claim] Tropical aux-power for container BESS | Src: Fraunhofer ISE — Photovoltaics Report | URL: https://www.ise.fraunhofer.de/en/publications/studies/photovoltaics-report.html | accessed 2026-09-22
Insurance (operational all-risk)USD / year1,500 – 4,000[Claim] Industrial energy-asset insurance baseline | Src: IUA — Cargo Clauses (A) clauses library (Institute Cargo Clauses publisher) | URL: https://www.iua.co.uk/clauses | accessed 2026-09-22
Capacity augmentation reserve (annual, year 11–12)USD / yearSet aside in OPEX, exact figure pending OEM warranty[Claim] LFP cycle-life framing for replacement reserve | Src: NREL ATB — Battery Storage (2024) | URL: https://atb.nrel.gov/electricity/2024/ | accessed 2026-09-22

5. Computed TCO summary (computed)

TCO summary
MetricValue
CurrencyUSD
Horizon (years)25
Discount rate8.00 %
Total undiscounted cost (USD)824,489.35
Total discounted cost / PV of costs (USD)543,823.52
Total undiscounted benefit (USD)912,189.74
Total discounted benefit (USD)419,539.29
NPV (USD)-124,284.23
IRR0.0237
Simple payback (year)15.65
Discounted payback (year)—
LCOS (USD/kWh)0.1673

Simple payback is reported as 15.65 years and discounted payback as — (undefined): the cumulative undiscounted benefit crosses the cumulative undiscounted cost at year 15.65, but the cumulative discounted benefit does not cross the cumulative discounted cost within the 25-year horizon. The NPV / IRR / LCOS block above is computed at a disclosed WACC = 8.00 %, matching the discount-rate row of the summary table. NPV is shown at the same 25-year horizon as the cash-flow table below.

6. Computed year-by-year cash flow (computed)

Year-by-year cash flow
YearCost (USD)Benefit (USD)Net (USD)Discount factorDiscounted net (USD)Energy (kWh)
0360,050.000.0000-360,050.001.00-360,050.000.0000
114,500.0046,008.0031,508.000.925929,174.07356,400.00
214,790.0045,087.8430,297.840.857325,975.51349,272.00
315,085.8044,186.0829,100.280.793823,100.74342,286.56
415,387.5243,302.3627,914.850.735020,518.24335,440.83
515,695.2742,436.3126,741.050.680618,199.51328,732.01
616,009.1741,587.5925,578.420.630216,118.74322,157.37
716,329.3640,755.8424,426.480.583514,252.62315,714.22
816,655.9439,940.7223,284.780.540312,580.04309,399.94
916,989.0639,141.9122,152.840.500211,081.94303,211.94
1017,328.8438,359.0721,030.220.46329,741.06297,147.70
1117,675.4237,591.8919,916.470.42898,541.83291,204.75
1218,028.9336,840.0518,811.120.39717,470.15285,380.65
1318,389.5136,103.2517,713.740.36776,513.31279,673.04
1418,757.3035,381.1816,623.890.34055,659.79274,079.58
1519,132.4434,673.5615,541.120.31524,899.21268,597.99
1619,515.0933,980.0914,465.000.29194,222.19263,226.03
1719,905.3933,300.4913,395.090.27033,620.28257,961.51
1820,303.5032,634.4812,330.980.25023,085.81252,802.28
1920,709.5731,981.7911,272.220.23172,611.91247,746.23
2021,123.7631,342.1510,218.390.21452,192.34242,791.31
2121,546.2430,715.319,169.070.19871,821.49237,935.48
2221,977.1630,101.008,123.840.18391,494.30233,176.77
2322,416.7129,498.987,082.280.17031,206.22228,513.24
2422,865.0428,909.006,043.960.1577953.13223,942.97
2523,322.3428,330.825,008.480.1460731.33219,464.11

Simple payback is reached at year 15.65 (undiscounted). Discounted payback is reported as — (undefined): the cumulative discounted benefit does not cross the cumulative discounted cost within the 25-year horizon. The NPV / IRR / LCOS block above is presented on the same 25-year horizon and at the same 8.00 % WACC as the table.

7. Compliance & certifications

Standard / requirementDesignation (edition / year)Issuer / status
Secondary lithium cells for industrial applicationsIEC 62619:2022 (2nd edition, 2022)Issuer: IEC | Src: IEC Webstore catalogue | URL: https://webstore.iec.ch/ | accessed 2026-09-22. Specific certificate number pending OEM submission and lab verification.
Transport of lithium batteriesUN 38.3 — UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7 (UN Manual Rev.7)Issuer: UNECE | Src: UN — Manual of Tests and Criteria | URL: https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria | accessed 2026-09-22. Test report number pending OEM submission.
EV conductive charging (where V2G / V2B is invoked)IEC 61851-1:2017 (3rd edition)Issuer: IEC | Src: IEC Webstore document page | URL: https://webstore.iec.ch/en/publication/33644 | accessed 2026-09-22. Applicable only if the site dispatches through an EV-coupled port.
Stationary battery safety (UL family, where contractually required)UL 1973 (Batteries for Use in Stationary and Motive Auxiliary Power Applications)Issuer: UL | Src: UL Standards product page | URL: https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973 | accessed 2026-09-22
EU battery regulation (for EU-destined cells / packs)Regulation (EU) 2023/1542 (EU Battery Regulation)Issuer: European Union | Src: EUR-Lex official document | URL: https://eur-lex.europa.eu/eli/reg/2023/1542/oj | accessed 2026-09-22
Grid interconnection (PLN)PLN interconnection standard — specific clause pending confirmation at RFQIssuer: PLN | Lookup path: DGCE tariff portal at https://www.beacukai.go.id/ (accessed 2026-09-22). Always reconfirm against the latest Permen ESDM adjustment in force at the time of quotation.

8. Comparable public products for cross-check

BrandPublic product familyPublic pageCaveat
CATLEnerC containerised LFP BESS (1 MW / 1.2 MWh class)https://www.catl.com/en/ess/JS-rendered; exact datasheet rev confirmed at RFQ
BYDMC Cube / HVS / HVM commercial-industrial LFPhttps://www.bydenergy.com/Cabinet ratings confirmed at RFQ
EVE EnergyLFP cell and storage product rangehttps://www.evebattery.com/enExact cell model and pack configuration confirmed at RFQ
SungrowString and central inverter range (e.g. SG125HT C&I 3-phase)https://www.sungrowpower.com/en/products/string-inverterExact inverter datasheet confirmed at RFQ
HuaweiSUN2000-330KTL-H1 (330 kW 3-phase 1500 V DC 8-MPPT)https://solar.huawei.com/en/products/sun2000-330ktl-h1Used here as a reference PCS-class string inverter; pairing with CATL EnerC confirmed at RFQ

9. Sources cited (accessed 2026-09-22)

10. Bounded model assumptions (inputs the draft did not state)

The following bounded defaults are explicitly listed so reviewers and buyers can see what was assumed to produce the COMPUTED TABLES in §5 and §6. They are model assumptions, not sourced facts, and must be re-validated against OEM warranty, PLN tariff structure and the buyer's actual operating profile before any commitment.

InputBounded default usedValidation path
residual_value.amountUSD 0 (no terminal salvage assumed)Negotiate residual / repurchase option in OEM warranty annex
residual_value.yearEnd of year 25 (terminal year of horizon)Confirm with OEM end-of-life take-back / second-use programme
asset.ess.round_trip_eff0.90 (system-level AC-AC, including auxiliaries)Validate against OEM warranty test report; liquid-cooled systems in tropical climates typically run 0.88–0.92
asset.ess.charge_cost_per_kwhUSD 0.08 / kWh (modelled WBP-blend charge cost)Re-run with the buyer's actual PLN tariff and demand-charge profile
asset.ess.value_per_kwh_dischargedUSD 0.14 / kWh (modelled LWBP-blend discharge value)Re-run with the buyer's actual PLN tariff and demand-charge profile