LFP Rack 100 kWh — China to Poland TCO Reference (Hotel Solar Use-Case)

Verdict: On this 10-year, 8.00 % discount-rate scenario the 100 kWh LFP rack import shows NPV = -€15,653.83, LCOS = €0.2590 / kWh, and no simple or discounted payback within the horizon — i.e. benefits do not recover costs at the modelled inputs. Equipment class: vertical LFP rack battery, 100 kWh nominal. Location: China (origin) → Poland (destination, EU). Horizon: 10 years. Evidence-date: 2026-09-22. Limitation: figures are an scenario TCO reference, not a binding quote; certificate numbers and customs duties remain PENDING — request via /rfq/.

Decision table

IndicatorValueInterpretation
NPV (EUR)-15,653.83Negative — costs exceed discounted benefits over 10 years.
IRR-0.0873Below hurdle — project does not clear 8.00 % discount rate.
Simple payback (year)—Not reached within 10-year horizon.
Discounted payback (year)—Not reached within 10-year horizon.
LCOS (EUR/kWh)0.2590Levelised cost of storage, 10-year basis.
Total discounted cost / PV of costs (EUR)32,192.12Present value of all costs, Year 0 included.
Total discounted benefit (EUR)16,538.29Present value of avoided import over 10 years.
Disclaimer. All numeric values are an scenario TCO reference for the use-case profile in §1, assembled from allow-listed OEM datasheets, official EU customs / tariff portals, IEC standards bodies, and the EU Battery Regulation. They are not a binding commercial offer. Submit the RFQ form for a firm quotation. Rates marked PENDING — lookup must be confirmed on the official source named next to each line, as-of the shipment date.
Request Quote — replies in 48h Datasheet request

1. Use-Case Profile

ApplicationBehind-the-meter solar PV self-consumption for a hotel facility in Poland
Product classVertical LFP (lithium iron phosphate) rack battery system, 100 kWh nominal
SKUlfp-rack-100kwh
Reference equipment familyLFP rack, 100 kWh nominal — a generic product class. Tradvolt does not assert a specific OEM model on this page; the OEM / model / certificate numbers are confirmed only at RFQ stage. Publicly marketed LFP rack products in this class include CATL EnerC (commercial LFP container reference), EVE Energy LF100LA / LF280K cells, Sungrow ST2752UX battery cabinet family, and Huawei LUNA2000-100/200 family — confirm specific SKU at RFQ against OEM datasheet.
OriginChina (CN)
DestinationPoland (PL), EU
Typical DoD80 % (cycle-life reference)
Reference ambient25 °C operating, indoor / sheltered install

2. TCO Summary (computed)

TCO summary
MetricValue
CurrencyEUR
Horizon (years)10
Discount rate8.00 %
Total undiscounted cost (EUR)34,962.29
Total discounted cost / PV of costs (EUR)32,192.12
Total undiscounted benefit (EUR)24,337.27
Total discounted benefit (EUR)16,538.29
NPV (EUR)-15,653.83
IRR-0.0873
Simple payback (year)—
Discounted payback (year)—
LCOS (EUR/kWh)0.2590

Source: Computed TCO tables — Tradvolt scenario model, evidence-date 2026-09-22. Numerical figures are computed and not editable on this page.

3. Year-by-Year Cash Flow (computed)

Year-by-year cash flow
YearCost (EUR)Benefit (EUR)Net (EUR)Discount factorDiscounted net (EUR)Energy (kWh)
026,750.000.0000-26,750.001.00-26,750.000.0000
1750.002,660.871,910.870.92591,769.3220,000.00
2765.002,607.651,842.650.85731,579.7819,600.00
3780.302,555.501,775.200.79381,409.2119,208.00
4795.912,504.391,708.480.73501,255.7918,823.84
5811.822,454.301,642.480.68061,117.8418,447.36
6828.062,405.221,577.150.6302993.8818,078.42
7844.622,357.111,512.490.5835882.5217,716.85
8861.512,309.971,448.450.5403782.5517,362.51
9878.742,263.771,385.020.5002692.8617,015.26
10896.322,218.491,322.170.4632612.4216,674.96

Source: Computed TCO tables — Tradvolt scenario model, evidence-date 2026-09-22. Year 0 = landed CapEx (€26,750.00). Annual energy declines as the LFP cell ages; benefit falls accordingly.

4. Bounded Model Assumptions (inputs the draft did not state)

All four items are explicit bounded assumptions, not sourced facts. Update them at RFQ if your counter-case differs.

5. CapEx — Indicative Import Landed Cost (per 100 kWh system)

Line itemDescriptionValue (EUR)
Ex-works unit (CN)FOB / EXW reference from OEM tier-1 datasheet band (e.g. CATL EnerC family, Sungrow ST2752UX, Huawei LUNA2000 family — specific SKU confirmed at RFQ against OEM datasheet). [Src: CATL — https://www.catl.com/en/ess/; Sungrow — https://www.sungrowpower.com/en; Huawei — https://solar.huawei.com/en]18,000 – 26,000
Logistics
Ocean freight (CN→PL)~1 system, 40 ft container share, port Gdańsk1,200 – 1,800
Insurance~0.3 % of CIF~75
THC + ISPS + documentationTerminal handling, port security, B/L fees250 – 400
Customs & duties (see §7 — all rates PENDING — lookup)
Customs dutyEU TARIC (Poland) — lookup on official portalPENDING — lookup
VATEU TARIC (Poland) VAT — lookup on official portalPENDING — lookup
Last-mile
Inland transport Gdańsk → site~400 km, tilt-truck, escort if required600 – 1,100
Off-loading & positioningForklift, rigging, indoor placement300 – 600
DC cabling + DC combinerto existing PV inverters / hybrid inverter400 – 800
Commissioning & grid sign-offDSO application, settings, witness test700 – 1,200
Producer responsibility (Battery Regulation)Per Regulation (EU) 2023/1542 — registration evidence requiredincluded in unit
Indicative CapEx (ex. duties)Range, before customs21,525 – 31,975
Modelled CapEx (Year 0)Audit-aligned figure used in §326,750.00

6. OpEx — Annual Operating Cost (per 100 kWh system)

Line itemBasisEUR / year
Round-trip efficiency lossesCharged at €0.22/kWh against modelled annual kWhincluded in §3
Preventive maintenanceVisual + BMS log review, fan filter swap120 – 240
Spare parts reserveSmoothed allocation over service life150 – 300
Remote monitoring subscriptionOEM cloud portal, optional60 – 180
Insurance (asset)~0.25 % of CapEx/yr~70
DSO / capacity feesNOT INCLUDED — varies by operator and tariff—
Modelled OpEx (Year 1, audit-aligned)Figure used in §3, inflated 2 %/yr750.00

7. Duty & HS Code Block

ComponentReference / sourceRate / value
HS subheading — lithium-ion storage batteriesEU TARIC consultation — commonly 8507.60 for lithium-ion accumulators. Confirm exact 8/10-digit national line as-of shipment date. [Src: https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en]PENDING — lookup
Customs duty (EU Common Customs Tariff + national)Confirm on EU TARIC (Poland) as-of shipment date. [Src: https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en]PENDING — lookup
VAT (Poland)Confirm on EU TARIC / Polish tax authority portal as-of shipment date.PENDING — lookup
EU Battery Regulation — producer responsibilityProducer registration evidence required when placing batteries on the EU market. [Src: EUR-Lex — Regulation (EU) 2023/1542 — https://eur-lex.europa.eu/eli/reg/2023/1542/oj]Evidence required
Anti-dumping / safeguard measures on CN-origin LFP cells (if any)Confirm on EU TARIC measures tab as-of shipment date.PENDING — lookup
UN transport classificationLithium batteries classified under UN 3480 / UN 3481 as applicable — UN Manual of Tests and Criteria, UN 38.3.Test summary required
IATA Dangerous GoodsAir shipment subject to IATA DGR. [Src: https://www.iata.org/en/programs/cargo/dgr/]Operator rules apply

No rate has been hardcoded on this page. Official source-of-truth: EU TARIC consultation at https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en.

8. Compliance & Certifications

Cert numbers pending — request via /rfq/. The framework below is the typical compliance pack for a 100 kWh LFP rack imported into Poland. Specific certificate numbers and issuing bodies are NOT asserted on this page; they are confirmed per supplier at RFQ stage.

9. Spec / Datasheet

Request controlled datasheet & certificate pack via /rfq/ Engineering review request via /rfq/

OEM / model / datasheet revision are confirmed at RFQ stage against the supplier's controlled PDF (e.g. CATL EnerC, EVE LF100LA / LF280K, Sungrow ST2752UX, Huawei LUNA2000-100/200 — datasheet revision to be confirmed per shipment).

10. Request Quote — replies in 48h

Submit the form below. Required fields: product_sku, qty + unit, incoterm, target_cert, destination_country, buyer_email, buyer_company. The form posts to the Tradvolt RFQ endpoint at /rfq/.

Incoterms 2020 (ICC) — https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/. EU Battery Regulation (EU) 2023/1542 — https://eur-lex.europa.eu/eli/reg/2023/1542/oj. EU TARIC consultation — https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en.

11. FAQ

Is this page a binding quote for LFP rack 100 kWh import to Poland?

No. The CapEx, OpEx, NPV, IRR, payback and LCOS figures on this page are an scenario TCO reference — NOT A QUOTE. They use the inputs stated in §1 and the bounded assumptions in §4. Submit the RFQ form for a binding offer.

Which HS code applies to LFP battery racks imported into Poland?

Lithium-ion storage batteries commonly fall under HS subheading 8507.60 in the EU TARIC. The exact 8/10-digit national line, duty rate, VAT, and any anti-dumping / safeguard measures must be confirmed on the EU TARIC consultation portal as of the shipment date — see §7. [Src: https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en]

Which certifications are typically required for a 100 kWh LFP rack in Poland?

Typical compliance pack: IEC 62619 (industrial LFP safety), UN 38.3 (transport), CE marking under the Low Voltage Directive (2014/35/EU) and EMC Directive (2014/30/EU), and EN 61000 series EMC tests. Grid interconnection follows the Polish DSO requirements (operator-specific). Cert numbers are NOT asserted on this page; request via /rfq/.

What is the expected lifetime and warranty baseline for an LFP rack?

OEM datasheets in this product class typically rate LFP cells for 6,000+ cycles at 80 % DoD and 10–15 year calendar life at 25 °C ambient, with warranties of 5–10 years or a defined energy-throughput figure, whichever comes first. Confirm against the chosen supplier's datasheet and manual revision (e.g. CATL EnerC, Sungrow ST2752UX, Huawei LUNA2000 family — datasheet rev. confirmed at RFQ).

Does the TCO include Polish grid fees or capacity market charges?

No. OpEx lists efficiency losses, maintenance, spares, monitoring, and insurance only. Polish DSO fees, capacity market charges, and demand charges are NOT included because they vary by operator, tariff group, and contract structure. Confirm with the local DSO before procurement.

How do I request a firm quote?

Use the Request Quote — replies in 48h form above. Provide product_sku, qty + unit, incoterm (Incoterms 2020), target_cert, destination_country, buyer_email, buyer_company. Cert pack and controlled datasheet are issued per shipment.

Request Quote — replies in 48h Datasheet request