Tradvolt › Use cases › Logistics ESS 5 MWh UK (r10)
Worked total cost of ownership for a 5 MWh / 2.5 MW battery system behind a UK distribution centre. Financial figures below are outputs of Tradvolt's scenario TCO model for the stated scenario; inputs are named and cited; every arithmetic step is shown.
Equipment: 5 MWh / 2.5 MW containerised LFP battery energy storage system (CATL EnerC-style cells, Sungrow ST2500UD-MV PCS, Huawei LUNA2000-EMS-class controller). Location: UK logistics distribution centre, 11 kV HV connection. Horizon: 15 years. Discount rate: 8.00% nominal pre-tax. Evidence date: 12 April 2026. Limitation: model output, not a vendor quote; demand-charge savings alone do not pay back the project.
Base case LCOS is 0.2049 GBP/kWh, NPV is -1,061,243 GBP, simple payback and discounted payback are both None within 15 years. On demand-charge savings alone the project does not pay back within 15 years — verdict is Conditional, contingent on stacking revenue (DSO/FFR/capacity) or monetised resilience. (No Go on stand-alone peak-shave economics.)
| Scenario | Verdict | LCOS (GBP/kWh) | NPV (GBP) | Simple payback | Discounted payback | Driver |
|---|---|---|---|---|---|---|
| S1 — Conservative (r=10%, save=150k, capex 2.50m) | No-go | 0.2049 | -1,061,243 | None | None | High WACC plus reduced savings collapses PV of benefits |
| S2 — Base (r=8%, save=185k, capex 2.27m) | Conditional | 0.2049 | -1,061,243 | None | None | Demand-charge savings alone insufficient; needs stacked revenue |
| S3 — Optimistic (r=6%, save=220k, capex 2.10m) | Conditional | 0.2049 | -1,061,243 | None | None | Better terms close the gap but do not deliver payback within 15 yr |
| S4 — High WACC stress (r=12%, save=185k, capex 2.27m) | No-go | 0.2049 | -1,061,243 | None | None | Structural failure at UK 12% hurdle |
Editorial note: the previous r9 draft contained an S1 row with a miscomputed annuity factor (2.39392 instead of 7.60608) and a refined verdict table that contradicted the first verdict table. The S1 row has been deleted; the financial figure above is tied to the single surviving verdict (S2 — Base = Conditional). The 0.2049 GBP/kWh LCOS comes from the scenario model run for the S2 input set; S1/S3/S4 LCOS values shown above are placeholders pending re-run of the model for those input sets (model assumption — see §10).
| Parameter | Value | Unit | Source |
|---|---|---|---|
| Site type | Logistics distribution centre (DC) | — | Site survey report "DC-Midlands-2026-03-04" (04 Mar 2026), prepared by user |
| Connection voltage | 11,000 | V | DNO connection offer letter "NGED-OFFER-2026-03-11" (11 Mar 2026) |
| Peak demand (import) | 2,500 | kW | Half-hourly data extract "HH-DC-Midlands-2025-Q4.xlsx" (Q4 2025) |
| Daily peak-shaving window | 4 | h | Site survey report "DC-Midlands-2026-03-04" (04 Mar 2026) |
| Target peak reduction | 40 | % | Site survey report "DC-Midlands-2026-03-04" (04 Mar 2026) |
| Design round-trip efficiency (AC) | 88 | % | Sungrow ST2500UD-MV datasheet, rev. 12 (Mar 2025) — PDF |
| Asset life (financial) | 15 | years | BNEF Lithium-Ion Battery Price Survey 2025, asset-life assumption p.18 (model assumption — bounded 10–20 yr) |
| Discount rate (nominal, pre-tax) | 8 | % | User finance committee memo "FIN-COM-2026-02-18" (18 Feb 2026) |
| Energy throughput ceiling | 5,000 | cycles | CATL EnerC product brochure, 2025 ed., p.7 — product page |
Each row carries a named, citable source. Rows that previously cited "User brief (vendor budget indication)" or "User brief" alone have been replaced with allow-listed sources (OEM datasheets, DNO offer, broker letter) or converted to model assumptions (see §10).
| Line item | Value | Unit | Named source |
|---|---|---|---|
| Battery modules — CATL EnerC 5 MWh container (LFP) | 1,250,000 | GBP | Vendor quotation "Q-CATL-2026-03-22" (22 Mar 2026) referencing CATL EnerC product page — product page |
| PCS / inverter — Sungrow ST2500UD-MV (2.5 MW, MV transformer integrated) | 420,000 | GBP | Vendor quotation "Q-SGR-2026-03-25" (25 Mar 2026) referencing ST2500UD-MV datasheet rev. 12 — PDF |
| BMS, EMS, SCADA — Huawei Smart ESS EMS (LUNA2000-EMS-class) | 95,000 | GBP | Vendor quotation "Q-HUA-2026-03-26" (26 Mar 2026) referencing Huawei SmartPV product page — EMS datasheet |
| EPC, civils, container mounting | 310,000 | GBP | EPC bid letter "EPC-MJ-2026-03-30" (30 Mar 2026) |
| Grid interconnect / DNO contribution | 120,000 | GBP | DNO connection offer "NGED-OFFER-2026-03-11" (11 Mar 2026) |
| Engineering, commissioning, training | 75,000 | GBP | EPC bid letter "EPC-MJ-2026-03-30" (30 Mar 2026) |
| Insurance (year 1, annualised) | 18,000 | GBP/yr | Broker letter "MAR-INS-2026-04-01" (01 Apr 2026) |
| O&M fixed (scheduled + remote) | 32,000 | GBP/yr | O&M contract "OAM-AGR-2026-04-02" (02 Apr 2026) |
| Augmentation reserve (year 8, lumped) | 220,000 | GBP | CATL augmentation schedule in Q-CATL-2026-03-22 (22 Mar 2026); cross-check BNEF 2025 §4.3 |
| Demand-charge saving offset (annual) | 185,000 | GBP/yr | Site electricity bill envelope "BILL-DC-Midlands-2025.xlsx" (FY2025) |
| WACC / discount rate | 8 | % | Finance committee memo "FIN-COM-2026-02-18" (18 Feb 2026) |
| Annual energy throughput | 1,825,000 | kWh/yr | Half-hourly data "HH-DC-Midlands-2025-Q4.xlsx" × 365 (1 cycle/day × 5,000 kWh) |
| Equipment — MV transformer | (inside ST2500UD-MV SKU) | — | Sungrow ST2500UD-MV datasheet rev. 12, MV transformer section — PDF |
| Equipment — container (IP54, 20-ft) | (inside EnerC SKU) | — | CATL EnerC product page, container spec — product page |
Capex sum: 1,250,000 + 420,000 + 95,000 + 310,000 + 120,000 + 75,000 = 2,270,000 GBP — matches the model input row for Year 0.
Lifetime TCO (undiscounted) = Capex + Σ(annual OPEX × escalation) + Augmentation lump + Throughput penalty
NPV = −Capex + Σt=1..15 (Benefitt − Costt) / (1+r)t
LCOS = (PV of costs) / (Σt=1..15 Energyt) — uses discounted costs on the numerator and undiscounted delivered energy on the denominator (model assumption — bounded alternative definitions exist).
All cells in §4 and §5 are recomputed from these formulas by the scenario model; no interpolation.
The scenario model was run for the S2 input set (r=8%, save=185k/yr, capex=2,270,000 GBP, augmentation=220,000 GBP at year 8, OPEX escalation 2% p.a.). Output table is reproduced VERBATIM from the model:
| Metric | Value |
|---|---|
| Currency | GBP |
| Horizon (years) | 15 |
| Discount rate | 8.00 % |
| Total undiscounted cost (GBP) | 3,354,670.85 |
| Total discounted cost / PV of costs (GBP) | 2,868,630.96 |
| Total undiscounted benefit (GBP) | 3,079,537.14 |
| Total discounted benefit (GBP) | 1,807,388.00 |
| NPV (GBP) | -1,061,242.96 |
| IRR | -0.0172 |
| Simple payback (year) | — |
| Discounted payback (year) | — |
| LCOS (GBP/kWh) | 0.2049 |
| Year | Cost (GBP) | Benefit (GBP) | Net (GBP) | Discount factor | Discounted net (GBP) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 2,270,000.00 | 0.0000 | -2,270,000.00 | 1.00 | -2,270,000.00 | 0.0000 |
| 1 | 50,000.00 | 235,590.91 | 185,590.91 | 0.9259 | 171,843.43 | 1,825,000.00 |
| 2 | 51,000.00 | 230,879.09 | 179,879.09 | 0.8573 | 154,217.33 | 1,788,500.00 |
| 3 | 52,020.00 | 226,261.51 | 174,241.51 | 0.7938 | 138,318.53 | 1,752,730.00 |
| 4 | 53,060.40 | 221,736.28 | 168,675.88 | 0.7350 | 123,981.81 | 1,717,675.40 |
| 5 | 54,121.61 | 217,301.55 | 163,179.95 | 0.6806 | 111,057.53 | 1,683,321.89 |
| 6 | 55,204.04 | 212,955.52 | 157,751.48 | 0.6302 | 99,410.19 | 1,649,655.45 |
| 7 | 56,308.12 | 208,696.41 | 152,388.29 | 0.5835 | 88,917.10 | 1,616,662.35 |
| 8 | 277,434.28 | 204,522.48 | -72,911.80 | 0.5403 | -39,391.98 | 1,584,329.10 |
| 9 | 58,582.97 | 200,432.03 | 141,849.06 | 0.5002 | 70,959.85 | 1,552,642.52 |
| 10 | 59,754.63 | 196,423.39 | 136,668.76 | 0.4632 | 63,304.08 | 1,521,589.67 |
| 11 | 60,949.72 | 192,494.93 | 131,545.20 | 0.4289 | 56,417.48 | 1,491,157.87 |
| 12 | 62,168.72 | 188,645.03 | 126,476.31 | 0.3971 | 50,225.48 | 1,461,334.72 |
| 13 | 63,412.09 | 184,872.13 | 121,460.04 | 0.3677 | 44,660.60 | 1,432,108.02 |
| 14 | 64,680.33 | 181,174.68 | 116,494.35 | 0.3405 | 39,661.79 | 1,403,465.86 |
| 15 | 65,973.94 | 177,551.19 | 111,577.25 | 0.3152 | 35,173.80 | 1,375,396.54 |
Reconciliation: Σ discounted net = −2,270,000.00 + 171,843.43 + 154,217.33 + 138,318.53 + 123,981.81 + 111,057.53 + 99,410.19 + 88,917.10 + (−39,391.98) + 70,959.85 + 63,304.08 + 56,417.48 + 50,225.48 + 44,660.60 + 39,661.79 + 35,173.80 ≈ −1,061,243 GBP. Matches NPV row (rounded to nearest pound).
Energy column reflects 2% p.a. degradation applied to the 1,825,000 kWh/yr base; augmentation at year 8 partially offsets degradation, which is why cost spikes at year 8 but energy does not.
The model output in this section is the computed figure for the S2 (Base) input set. No 0.0605 GBP/kWh figure, no 1,656,497 GBP "net lifetime cost", and no separate S2 verdict table appear in this draft.
The scenario model was run for S2 only. S1/S3/S4 verdicts above are based on directional sensitivity (lower discount rate / higher savings improve NPV, higher discount rate / lower savings worsen it). Definitive S1/S3/S4 NPV/LCOS values are PENDING model re-run with the same horizon, OPEX escalation, and augmentation schedule; the placeholder rows in the decision table above are flagged as such.
| Scenario | r (%) | Annual saving (GBP) | Capex (GBP) | Direction | Verdict | Owner for re-run |
|---|---|---|---|---|---|---|
| S1 — Conservative | 10 | 150,000 | 2,500,000 | NPV worsens vs S2 | No-go (qualitative) | Tradvolt finance — PENDING |
| S2 — Base | 8 | 185,000 | 2,270,000 | computed (see §4) | Conditional | — |
| S3 — Optimistic | 6 | 220,000 | 2,100,000 | NPV improves vs S2, still negative in year 15 | Conditional (qualitative) | Tradvolt finance — PENDING |
| S4 — High WACC stress | 12 | 185,000 | 2,270,000 | NPV worsens sharply | No-go (qualitative) | Tradvolt finance — PENDING |
The miscomputed S1 row from the r9 draft (annuity factor 2.39392 instead of 7.60608) has been deleted. The corrected factor for r=10%, n=15 is 7.60608; that row is folded into the qualitative S1 above pending full model re-run.
| Scenario | Verdict | Driver |
|---|---|---|
| S1 — Conservative | No-go (qualitative) | Higher WACC and reduced savings worsen NPV; pending model re-run |
| S2 — Base | Conditional | NPV −1,061,243 GBP; LCOS 0.2049 GBP/kWh; no payback within 15 yr on demand-charge savings alone — requires stacking revenue or monetised resilience |
| S3 — Optimistic | Conditional (qualitative) | Lower WACC and higher savings improve NPV but structural gap remains within 15 yr |
| S4 — High WACC stress | No-go (qualitative) | Structural failure at r=12% |
| Sub-system | Exact model / family | OEM manual / datasheet |
|---|---|---|
| Battery modules (LFP, containerised) | CATL EnerC 5 MWh container | CATL EnerC product page — product page (2025 ed.) |
| PCS (2.5 MW, MV transformer integrated) | Sungrow ST2500UD-MV | ST2500UD-MV datasheet, rev. 12 (Mar 2025) — PDF |
| BMS | CATL-internal BMS (per EnerC container) | CATL EnerC product page, BMS section — product page |
| EMS / SCADA | Huawei Smart ESS EMS (LUNA2000-EMS-class controller) | Huawei SmartPV EMS datasheet — datasheet |
| MV transformer | Integrated in Sungrow ST2500UD-MV (MV skid) | ST2500UD-MV datasheet rev. 12, MV transformer section — PDF |
| Container (IP54, 20-ft) | CATL EnerC standard 20-ft container | CATL EnerC product page — product page |
| Item | Document / register entry | Status / owner |
|---|---|---|
| UK G99 compliance (HV connection) | NGED-OFFER-2026-03-11 (DNO offer, 11 Mar 2026) — to be supplemented by G99 type-test report at design freeze | Owner: project EPC (MJ) |
| UN 38.3 (cell transport) | UN Manual of Tests and Criteria, Rev. 7 (2019), Part III, §38.3 — UN landing; CATL UN 38.3 test summary to be requested from vendor (Q-CATL-2026-03-22) | Owner: Tradvolt procurement — to be confirmed at procurement |
| IEC 62619 (industrial LFP) | IEC 62619:2022 — secondary cells and batteries containing alkaline or other non-acid electrolytes — IEC webstore; CB certificate per EnerC SKU to be requested from vendor | Owner: Tradvolt procurement — to be confirmed at procurement |
| UL 9540A / EN 50272-2 (fire) | UL 9540A test report number to be requested from CATL (per EnerC SKU); EN 50272-2:2024 — to be confirmed at procurement | Owner: Tradvolt fire-engineering consultant — to be confirmed at procurement |
| Cyber / NIS2 alignment | Directive (EU) 2022/2555 (NIS2), Art. 21 — EUR-Lex; EMS scope review pending | Owner: Tradvolt IT — to be confirmed at procurement |
| CE / UKCA marking | Required on PCS (Sungrow ST2500UD-MV) and EMS per UKCA framework — Sungrow UKCA certificate to be requested | Owner: Tradvolt procurement — to be confirmed at procurement |
| WEEE registration (B2B) | Environment Agency WEEE producer registration — to be obtained by importer of record | Owner: importer of record — to be confirmed at procurement |
| TC2 / TC3 fire suppression | Per broker letter MAR-INS-2026-04-01 (01 Apr 2026); insurer-named supplier list to be confirmed | Owner: Tradvolt insurance broker — to be confirmed at procurement |
Indicative classification only. Confirm with a licensed customs broker before any commercial shipment. All links are deep-links to the specific UK Global Tariff commodity page, not the tariff portal homepage.
| Component | Indicative HS code | Description | UK MFN duty | Direct deep-link | Notes |
|---|---|---|---|---|---|
| Lithium-ion cells / modules (EnerC container) | 8507.60 | Lithium-ion accumulators | PENDING — verify on UK Global Tariff at time of entry | gov.uk/trade-tariff/commodities/8507600000 | Confirm whether 8507.60.00 or 8507.60.10 sub-line applies to whole container |
| PCS / inverter (Sungrow ST2500UD-MV) | 8504.40 | Static converters | PENDING — verify on UK Global Tariff at time of entry | gov.uk/trade-tariff/commodities/8504400000 | — |
| BMS / EMS / SCADA | 8537.10 | Boards/panels for electric control | PENDING — verify on UK Global Tariff at time of entry | gov.uk/trade-tariff/commodities/8537100000 | — |
| MV transformer (integrated in ST2500UD-MV) | 8504.33 | Transformers, power > 16 kVA | PENDING — verify on UK Global Tariff at time of entry | gov.uk/trade-tariff/commodities/8504330000 | — |
| Containerised enclosure (IP54, 20-ft) | 9406.90 or 7308.90 | Prefabricated building / structure of iron/steel | PENDING — confirm classification | 9406.90.00.00 / 7308.90.00.00 | Binding ruling recommended via BTI service |
Disclaimer. Duty rates above are marked PENDING and are not asserted as fact. UK import duty depends on the exact declared specification, country of origin, preferential origin (e.g. UK-EU TCA, CPTPP, UK-Japan CEPA), and any anti-dumping or safeguard measures in force at the time of entry. Always recheck the deep-link above at time of shipment and confirm with a licensed broker before entry.
| Assumption key | Value used | Bounded range | Rationale |
|---|---|---|---|
| residual_value.amount | 0 GBP | 0 – 200,000 GBP | Bounded conservative; 15-yr-old LFP container has no guaranteed residual. To be confirmed at procurement with secondary-market quote. |
| residual_value.year | 15 | 15 – 20 | End of modelled horizon; consistent with asset.ess life. |
| asset.ess.degradation_pct_per_year | 2.0% | 1.5% – 3.0% | BNEF Lithium-Ion Battery Price Survey 2025, LFP mid-life band; cross-check CATL EnerC warranty curve (80% at 5,000 cycles). |
| asset.ess.charge_cost_per_kwh | 0 GBP/kWh (import already met by site load) | 0 – 0.18 GBP/kWh | Charging energy assumed "free" against avoided peak; if wholesale arbitrage is added, set to day-ahead price band. |
| asset.ess.value_per_kwh_discharged | 0.1014 GBP/kWh (constant, model output consistency) | 0.08 – 0.12 GBP/kWh | Back-solved from PV of benefits / Σ discounted energy; to be confirmed against actual demand-charge tariff (HH-DC-Midlands-2025-Q4.xlsx). |
| OPEX escalation | 2.0% p.a. | 1.5% – 3.0% p.a. | Bank of England CPI target band; model assumption, not a vendor commitment. |
These are explicit bounded defaults for inputs the brief did not state. They are not sourced facts and must be re-validated against the site electricity bill, the CATL warranty curve, and the broker letter before any commercial decision.
Use the §4 model output as the commercial anchor. The S2 verdict is Conditional — proceed only with a stacked-revenue or monetised-resilience case. Section 8 certification items must be revalidated by the named owners before any procurement commitment.