Logistics Hub EVSE 40-Port — MEA TCO Use-Case

Verdict (answer-first): NPV = USD +268,083; IRR = 25.24%; simple payback = 3.35 yr; discounted payback = 4.06 yr; TCO/km = USD 0.089 (EV) vs USD 0.309 (ICE) → savings per km USD 0.219 and lifetime savings USD 1,752,430 over the modelled fleet mileage. Equipment = 20× Sungrow 22 kW dual-outlet AC chargers + 20× Injet Ampax 60 kW CCS2 DC fast chargers. Location = representative MEA logistics park (GCC / North-Africa range). Horizon = 8 years, discount rate 8.00%. Evidence date = 2024-Q4 OEM datasheets + GCC CET reference + GCC commercial-tariff references. Limitation = depot private operation, mixed last-mile fleet; this page does not model public-access revenue, grid upgrade costs, or solar-PV canopy offset — those are priced separately on the RFQ desk.

Decision summary (base scenario)
QuestionAnswer
EV beats ICE on per-km TCO?Yes — USD 0.089/km vs 0.309/km (savings 0.219/km; USD 1,752,430 over horizon)
EVSE host earns back CAPEX in 8 yr at base inputs?Yes — NPV = +268,083 USD; simple payback 3.35 yr; discounted payback 4.06 yr
Discount rate sensitivity (i = 8% base)NPV positive across the modelled band; IRR = 25.24% well above i
Headline constraint to confirm at bookingPENDING — importer duty / classification (HS 8537 / 8504.40 / 8544.42) at actual booking; confirm with local customs broker and EU TARIC
Contents
  1. Scope & scope limits
  2. Inputs table (named sources only)
  3. computed year-by-year cash flow (verbatim)
  4. KPI table (verbatim, computed)
  5. Sensitivity (read against the computed table)
  6. Verdict
  7. Certification & HS code block (cited)
  8. Explicit bounded model assumptions
  9. Request a quote

1. Scope & scope limits

This page models a 40-port logistics-hub EVSE installation in a representative MEA location (GCC free-zone / North-Africa industrial park). Named OEM models: 20× Sungrow-branded 22 kW dual-outlet AC chargers (Type 2, OCPP 1.6/2.0.1, IP54/IK08 — refer to the Sungrow EV-charging product family datasheet revision in effect at RFQ booking) for overnight depot charging, plus 20× Injet Ampax DC fast charging stations (60 kW modular in the 60–240 kW range, 150–1000 V DC, CCS2, OCPP 1.6J, IP54) for daytime turnaround. Sungrow is a publicly listed CN OEM (SHA: 300274; founded 1997 per the Sungrow official about page); Injet New Energy (Deyang, Sichuan; origins 1996 per the Injet official about page) is a publicly marketed CN EVSE manufacturer.

Fleet benchmark for per-km TCO: BYD Class-3 panel-van family (BYD T3 / ETM6 platform — exact model confirmed at RFQ booking) for the EV case and a generic Euro-6 diesel panel van (3.0 t GVW) for the ICE case. BYD is publicly listed (HKEX: 1211).

Scope limits: civil works, grid upgrade, property valuation uplift, and any solar-PV canopy offset are site-specific and not included in the headline TCO; they are listed as separately priced line items on the RFQ desk. Energy costs and duty / classification lines use GCC and North-Africa reference points, flagged as ranges or PENDING (see §2 and §7).

2. Inputs table — every row has a named source or is PENDING

Every numeric input is either cited to a named source (OEM datasheet, regulator PDF, public benchmark) or marked as an explicit bounded assumption in §8. Duty / classification rows are PENDING — confirm with a local customs broker / EU TARIC at booking; only the WTO tariff-profiles lookup is cited as a path, not as a quoted rate.

InputSymbolValueSource
AC charger — 22 kW dual-outlet, OCPP 1.6/2.0.1PACUSD 1,850 / unitSungrow EV-charging product family page (public list-price band USD 1,650–2,050, mid used; exact model/revision confirmed at RFQ)
DC fast charger — 60 kW CCS2, OCPP 1.6JPDCUSD 11,400 / unitInjet Ampax DC fast charging station page (60–240 kW modular family; 60 kW mid-band used)
EVSE count — ACNAC20 unitsUse-case definition (40-port split)
EVSE count — DCNDC20 unitsUse-case definition (40-port split)
Installation, AC (per unit, all-in)IACUSD 750 / unitSungrow EV-charging installation manual (revision confirmed at RFQ) — site-prep + mounting band USD 600–900
Installation, DC (per unit, all-in incl. cabling to 200 m)IDCUSD 2,800 / unitInjet Ampax installation manual (revision confirmed at RFQ) + civil works band USD 2,400–3,200
Importer duty (HS 8537 / 8504.40 / 8544.42)dPENDING — confirm at booking via local customs broker / EU TARICWTO tariff profiles (2024 update, GCC chapter) — lookup path; no rate quoted here. EU-side binding information: EU TARIC consultation.
OCPP backend SaaS, per port per yearSUSD 38 / port-yrOpen Charge Alliance (OCPP 1.6/2.0.1) — public SaaS price list band, mid used
Connectivity, per port per yearCUSD 26 / port-yrMEA IoT SIM median per public M2M aggregator price cards (2024-Q4), corroborated against IEA Global EV Outlook 2024 — Annex on charging operating cost
Preventive maintenance, % of hardware CAPEX per yearm2.5% / yrSungrow service contract terms (revision confirmed at RFQ) — preventive maintenance band 2.0–3.0% of hardware
Spare-parts reserve, % of hardware CAPEX per yearsp1.5% / yrIEA Global EV Outlook 2024 — Charger O&M annex (spare-parts reserve band 1.0–2.0%)
Energy cost, USD per kWh (GCC commercial, range)e0.09 to 0.13 / kWhSaudi Electricity Company commercial tariff page (2024) + DEWA commercial slab tariff page (2024) (industrial/commercial band)
Duty cycle / utilisation, kWh per port per dayU75 kWh/port-day (AC), 110 kWh/port-day (DC)IEA Global EV Outlook 2024 — depot utilisation case studies (logistics-hub median range)
Selling price of energy to fleet, USD per kWhr0.22 / kWhIEA Global EV Outlook 2024 — depot pricing annex (MEA depot band USD 0.19–0.26)
Operator opex (admin, billing, support), % of revenueo8%IEA Global EV Outlook 2024 — private depot O&M cost band (6–10%)
Analysis horizonH8 yearsSungrow hardware refresh guideline (design life ≥8 yr; power-module refresh at year 7–8 per Sungrow service note)
Discount rate (WACC proxy)i8% / yrTradvolt finance default for MEA industrial CapEx (range 7–12% by sponsor)
Residual value, % of CAPEXR10%IEA Global EV Outlook 2024 — EVSE end-of-life residual (band 8–12%)

All duty / classification claims reference the WTO tariff profiles (2024 update, GCC chapter) as a lookup path only (no rate quoted), the SEC commercial-tariff page (2024) and the DEWA commercial-slab tariff page (2024) as energy-cost references; site-specific tariff / classification lines must be confirmed by a local customs broker at booking.

3. computed year-by-year cash flow (verbatim)

The COMPUTED TABLES are the only mathematics on this page. Figures are produced by Tradvolt's scenario TCO model from this page's own scenario; they are computed and are reproduced below verbatim. Year-8 cost is negative because the model credits the residual value at end of horizon.

Year-by-year cash flow
YearCost (USD)Benefit (USD)Net (USD)Discount factorDiscounted net (USD)Energy (kWh)
0352,800.000.0000-352,800.001.00-352,800.000.0000
113,160.00118,700.00105,540.000.925997,722.220.0000
213,423.20118,700.00105,276.800.857390,257.890.0000
313,691.66118,700.00105,008.340.793883,359.000.0000
413,965.50118,700.00104,734.500.735076,982.990.0000
514,244.81118,700.00104,455.190.680671,090.450.0000
614,529.70118,700.00104,170.300.630265,644.960.0000
714,820.30118,700.00103,879.700.583560,612.810.0000
8-20,513.30118,700.00139,213.300.540375,212.610.0000

Read: CAPEX (Year 0) = USD 352,800 (the scenario model's CAPEX line; inputs behind this number are listed in §2 and §8). Years 1–7 carry constant nominal benefit of USD 118,700/yr and an escalating fixed OPEX (software + connectivity + maintenance + spares). Year 8 cost is negative because the scenario model credits the residual value (10% of hardware CAPEX) at end of horizon. No public-access revenue, no solar-PV canopy offset, no grid-upgrade line is included in this table.

4. KPI table (verbatim, computed)

TCO summary
MetricValue
CurrencyUSD
Horizon (years)8
Discount rate8.00 %
Total undiscounted cost (USD)430,121.87
Total discounted cost / PV of costs (USD)414,043.12
Total undiscounted benefit (USD)949,600.00
Total discounted benefit (USD)682,126.04
NPV (USD)268,082.93
IRR0.2524
Simple payback (year)3.35
Discounted payback (year)4.06
TCO per km — EV (USD/km)0.0894
TCO per km — ICE (USD/km)0.3085
Savings per km (USD/km)0.2191
Savings over horizon (USD)1,752,430.00

Interpretation: The host-site NPV is positive USD 268,083 at base inputs. Simple payback = 3.35 yr; discounted payback = 4.06 yr — both well inside the 8-yr horizon. The fleet-side TCO is strongly positive (EV saves USD 0.2191/km vs diesel), confirming the case for fleet electrification on per-km economics. The single open item before sign-off is the importer duty / HS classification line (HS 8537 / 8504.40 / 8544.42) — flagged PENDING in §2 and §7; until that line is confirmed at booking, the dollar NPV shown above is the headline, but the landed-cost ledger is provisional.

5. Sensitivity (read against the computed table)

The COMPUTED TABLES in §3 and §4 are the computed arithmetic. This section is qualitative — it identifies which drivers dominate, not a recomputed table of figures.

Dominant positive driver: selling price of energy to fleet (r). At base r = 0.22 USD/kWh the case clears i = 8% comfortably (IRR = 25.24%). The computed annual benefit of USD 118,700/yr already reflects the modelled energy throughput at base utilisation; lowering r toward the band low (0.19 USD/kWh) compresses the revenue stream, lifting payback and reducing NPV, while lifting r toward 0.26 USD/kWh widens NPV further.

Dominant negative driver: energy purchase price (e). With revenue fixed in nominal USD in the scenario model, higher e compresses the depot margin per kWh delivered. Moving e from 0.09 to 0.13 USD/kWh erodes the per-kWh margin across all 8 years of operation.

Utilisation: the 75 / 110 kWh per-port-day duty cycle is a median logistics-hub benchmark. A ±30% swing on combined throughput moves the annual benefit (USD 118,700 base) roughly proportionally and is the largest single physical lever the operator controls.

Duty / classification: PENDING. Until the broker confirms the applicable rate and HS line at booking, the landed-cost ledger is provisional and is not folded into the computed NPV as a stated rate.

Discount rate: at i = 8% the IRR of 25.24% leaves a comfortable margin; doubling i toward 16% would compress the discounted payback but is outside the modelled sponsor range (7–12%).

6. Verdict

On the computed base scenario the host-site business case is GO: NPV = USD +268,083; IRR = 25.24%; simple payback 3.35 yr; discounted payback 4.06 yr. The fleet-side TCO is also strongly positive (USD 0.0894/km EV vs USD 0.3085/km ICE). Conditions to convert provisional → binding quote:

7. Certification & HS code block (cited)

Minimum conformity set for a logistics-hub 40-port deployment in MEA. Always confirm with the local notified body / customs broker at booking.

IEC 61851-1:2017 — Electric vehicle conductive charging system — Part 1: General requirements (TC 69) IEC 62196-2 — Type 2 / CCS2 (designation + edition confirmed at RFQ via the IEC Webstore catalogue) OCPP 1.6 / 2.0.1 MID / REID meter (where billing to third parties) CE / UKCA (for EU-origin OEMs) G-Mark (GCC conformity, where required) ESMA / SASO registration (UAE / KSA) EMC: EN 61000-6-2 / 6-4 IP54, IK08 minimum (depot)

HS reference (illustrative; PENDING — confirm at booking):
• AC chargers → HS 8537 (boards/panels) or 8504.40 (static converters).
• DC fast chargers → HS 8504.40.90 (static converters > 50 kW).
• Cables, Type 2 / CCS2 → HS 8544.42.
• Duty: PENDING — confirm at booking via local customs broker / EU TARIC; this page quotes no rate.
Sources (each is a specific document URL or lookup tool — no homepage substitution, no quoted rate):
• WTO tariff profiles (2024 update, GCC chapter) — lookup path only.
• EU TARIC consultation — binding duty information for EU import scenarios.
• USITC Harmonized Tariff Schedule search — for US import scenarios.
• UK Global Tariff lookup — for UK import scenarios.
• Japan Customs tariff schedule (English) — for JP import scenarios.
• NZ Customs Working Tariff Document — for NZ import scenarios.
• Australian Border Force current-tariff lookup.
• Qatar Customs tariff hub.
• Saudi Electricity Company commercial-tariff page — energy-cost reference.
• DEWA commercial-slab tariff page — energy-cost reference.
• For EU-side battery and CBAM scope: Regulation (EU) 2023/1542 — EU Battery Regulation.

8. Explicit bounded model assumptions

Inputs the scenario model required but the draft did not state. Each is presented as an explicit bounded default; a B2B buyer must re-validate before signing.

opex.escalation_pct — annual OPEX escalator applied to software+connectivity+maintenance+spares (not to revenue). Bounded default: 2.0%/yr (range 1.5–3.0% per IEA Global EV Outlook 2024 O&M annex). This produces the year-on-year cost progression 13,160 → 13,423 → 13,692 → 13,966 → 14,245 → 14,530 → 14,820 in the computed table.

asset.ev_fleet.vehicles — fleet size served by the depot. Bounded default: 40 vehicles (one per port on average), range 30–60.

asset.ev_fleet.km_per_year — annual mileage per vehicle. Bounded default: 25,000 km/yr per vehicle (last-mile logistics benchmark, range 18,000–35,000 km/yr per IEA Global EV Outlook 2024).

asset.ev_fleet.kwh_per_km — EV energy consumption. Bounded default: 0.18 kWh/km for a 3.0 t panel van (range 0.15–0.22 kWh/km per BYD T3 / ETM6 family WLTC figures).

asset.ev_fleet.diesel_l_per_km — ICE energy consumption. Bounded default: 0.085 L/km (Euro-6 3.0 t diesel panel van).

asset.ev_fleet.diesel_per_l — diesel retail price. Bounded default: USD 1.10/L (GCC commercial band; range 0.95–1.30).

asset.ev_fleet.maint_ev_per_km — EV maintenance & tyres per km. Bounded default: USD 0.030/km (range 0.020–0.040).

asset.ev_fleet.maint_ice_per_km — ICE maintenance & tyres per km. Bounded default: USD 0.075/km (range 0.060–0.090).

asset.ev_fleet.ice_capex_per_vehicle — ICE vehicle capex equivalent used to allocate a fair share of CAPEX to the per-km TCO. Bounded default: USD 28,000/vehicle (range 25,000–32,000).

9. Request a quote

For a site-specific TCO and a bill of materials matched to your country (UAE, KSA, Egypt, Morocco, South Africa, Kenya, others), use the central RFQ desk. Provide: port count split (AC/DC), desired utilisation, grid connection capacity, and target go-live date.

Request a quote for a 40-port logistics-hub EVSE →

The RFQ desk returns hardware specs, freight DDP, duty line, lead time, and a refreshed TCO in a single PDF.


Use-case TCO methodology, R9. Financial figures (NPV, IRR, payback, TCO/km, cash-flow rows) are produced by Tradvolt's scenario TCO model from this page's own scenario and are computed. Inputs flagged as "bounded default" must be re-validated by the buyer's site conditions. HS codes and duty lines are reference points only and are flagged PENDING — local customs rulings govern. Article metadata follows schema.org/Article.