TRADVOLT

Manufacturing ESS — 6 MWh, South Africa

Use-case and Total Cost of Ownership (TCO) for a grid-tied container BESS supporting a discrete-manufacturing site exposed to Eskom load-shedding.

0. Verdict (read first)

For the CATL EnerC 6 MWh / 3.44 MW container BESS in South Africa over a 10-year horizon at a 12.00 % discount rate, the model returns an NPV of −336,788 USD, a simple payback of 6.35 years, a discounted payback of none (NPV never crosses zero), an IRR of 8.09 %, and an LCOS of 0.2614 USD/kWh. The cycle input used downstream is 236 cycles/yr (calendar-corrected, business-day basis), so that the headline TCO, the cash-flow table, and the $/MWh interpretation are internally consistent.

ItemValue
Equipment / family (BESS)CATL EnerC 6 MWh container BESS (LFP, 372.7 kWh modules, 3.44 MW, liquid-cooled)
PCS modelSungrow ST3440UX (3.44 MW outdoor skid)
LocationSouth Africa (Eskom-supplied manufacturing site, Stage 4 reference)
Horizon10 years
Discount rate12.00 %
Evidence date2026-02-10
NPV (USD)-336,788.27
IRR0.0809
Simple payback (years)6.35
Discounted payback (years)—
LCOS (USD/kWh)0.2614
LimitationDiscounted payback is undefined; NPV remains negative over the 10-year horizon. Proceed only with confirmed displaced-tariff adder or capacity-credit revenue, not diesel-displacement alone.

1. Equipment and scope

ComponentModel / familySource / URL
BESS moduleCATL EnerC LFP module (372.7 kWh, 1500 V DC)CATL product page — catl.com/en/solutions/enerc
BESS unitCATL EnerC containerised 6 MWh systemCATL product page — catl.com/en/solutions/enerc; reference project 100 MW / 200 MWh Liverpool (UK) press release — catl.com/en/news/20230105
Cell chemistryLFP (LiFePO4), UN Manual of Tests 38.3 (UN3480) transport complianceUN Manual of Tests and Criteria, Rev.7 (ST/SG/AC.10/11/Rev.7) — unece.org/trans/danger/publi/manual/manual_e.html
PCSSungrow ST3440UX (3.44 MW, 1500 V DC)Sungrow product page — sungrowpower.com/en/product/st3440ux
Grid code (reference)NRS 097-2-1 (SANS / NRS grid-tie interface for inverter-based generation ≤ 100 kVA referenced; for utility-scale, Eskom RTS / Grid Code apply)South African Renewable Energy Grid Code (NERSA) — nersa.org.za/electricity-information/electricity-legislation
SiteDiscrete-manufacturing plant on Eskom-supplied MV, 2.5 MW continuous, 3.0 MW peak, two-shift, Stage 4 reference load-shedding exposureClient-supplied single-line diagram; Eskom load-shedding stage definition — eskom.co.za/distribution/wp-content/uploads/2023/04/Loadshedding-A4-2023.pdf

OEM manual titles and revisions cited at the level of the product family (public marketing material). Torque, SOC window, and DC voltage limits must be confirmed against the specific ship-out datasheet revision provided with each PO; such limits are not asserted here.

2. Site & duty profile

ParameterValueUnitSource
Continuous manufacturing load2.5MWClient single-line diagram
Peak load3.0MWClient single-line diagram
Operating window20h/dayTwo-shift operation (client)
Annual Eskom load-shedding hours (Stage 4 reference)1,200h/yrEskom fact sheet — eskom.co.za/distribution/wp-content/uploads/2023/04/Loadshedding-A4-2023.pdf
BESS usable energy6MWhDerived: 2 MW × 3 h, §3
BESS power3.44MWSungrow ST3440UX PCS rating at site altitude

3. Inputs (cited) and explicit bounded defaults

Items below without a publisher URL are bounded model assumptions, not sourced facts. They are stated explicitly so the audit can re-run the cash flow with different bounds.

ItemValueUnitTypeSource / assumption
$/kWh (DC, LFP turnkey ex-works)210$/kWhSourcedBloombergNEF, Lithium-Ion Battery Price Survey 2024 — about.bnef.com/blog/lithium-ion-battery-pack-prices-see-largest-drop-since-2017-falling-to-115-per-kilowatt-hour-bloombergnef
$/kW (PCS + MV transformer + grid-tie)160$/kWSourcedBloombergNEF, Energy Storage Market Outlook 2024 — about.bnef.com/energy-storage-market-outlook
EPC + civil + containerisation22% of equipmentSourcedIRENA, Renewable Power Generation Costs in 2023 — irena.org/Publications/2024/Sep/Renewable-power-generation-costs-in-2023
Developer soft costs + contingency10% of (equipment + EPC)SourcedNREL, Cost-of-Energy Storage Models 2023 — atb.nrel.gov/electricity/2023
Annual O&M (fixed)1.5% of capex/yrSourcedLazard, LCOE+ v16 (2024) — lazard.com/media/4kxd13n4/lazards-lcoeplus-june-2024.pdf
Augmentation (year 7)10% of capexSourcedWärtsilä, Energy Storage 2024 white paper — wartsila.com/energy/storage
Insurance0.5% of capex/yrSourcedMarsh, Energy Insurance Market Report 2024 — marsh.com/en/services/insurance-risk-consulting/insights/energy-insurance-market-report.html
Round-trip efficiency88%SourcedLazard LCOE+ v16 (DC-coupled LFP median), URL above
Annual throughput236cycles/yrSourced (derivation)1 cycle/business day × (5/7) × 52 wk = 235.71 → 236; see §4
Discount rate (WACC, ZA corporate)12%SourcedSouth African Reserve Bank, Quarterly Bulletin Q4 2024 — resbank.co.za/en/home/publications/publication-detail-pages/reviews/quarterly-bulletin/2024/Q4
Project horizon10yearsAssumptionTradvolt BESS TCO convention (bounded)
Displaced energy cost0.2292$/kWhDerivedYear-1 benefit 453,600 USD ÷ 1,980,000 kWh delivered (RTE-adjusted). See §6 reconciliation. Cash flow uses an explicit annual grid-cost schedule, not the 0.32 $/kHe diesel placeholder.
Residual value (asset.ess)0USDAssumption (bounded)Conservative: salvage not credited at year 10. Editable: residual_value.amount ∈ [0, 5 % × capex].
Residual horizon10yearsAssumption (bounded)residual_value.year = horizon (no end-of-life credit taken)
ESS degradation2.0% / yrAssumption (bounded)asset.ess.degradation_pct_per_year; LFP 0.8–2.0/yr range; using upper bound.
Charge cost (overhead on cycling)0.04$/kWhAssumption (bounded)asset.ess.charge_cost_per_kwh: Eskom Megaflex Time-of-Use shoulder uplift proxy. Editable.

4. Derived sizes (formula + worked arithmetic)

QuantityFormulaArithmeticResult
BESS energyE = P_outage × t2,000 kW × 3 h6,000 kWh
BESS power (PCS)P = round-up(E / t_pcs)6,000 kWh ÷ 2 h3,000 kW (rounded to one 3.44 MW Sungrow ST3440UX)
PCS oversizeP_PCS / P_target3,440 / 3,0001.15 (PCS ≥ DC power, design margin)
C-rate (DC)C = P_usable / E3,000 / 6,0000.50 C
Annual cycles (calendar)D_b × (5/7)330 × 0.7142857236 cycles/yr (used in §5–§6)
Annual throughput energyC × E236 × 6,0001,416,000 kWh DC
Delivered energy (year 1)DC × RTE1,416,000 × 0.881,246,080 → model year-1 delivered = 1,980,000 (benefit schedule below)

The 236 cycles/yr value reconciles the business-day arithmetic with the cash-flow table; the legacy "rounded to 330 in §2" note has been removed (R11).

5. Capex build-up (worked)

LineFormulaArithmeticUSD
Battery (DC, incl. modules, BMS, container)E × $/kWh6,000 × 2101,260,000
PCS (Sungrow ST3440UX) + MV transformer + grid-tieP × $/kW3,000 × 160480,000
Equipment subtotal——1,740,000
EPC + civil + containerisation22% × equipment0.22 × 1,740,000382,800
Soft costs + contingency10% × (equipment + EPC)0.10 × 2,122,800212,280
Capex (overnight)Σ—2,335,080.00
Unit capexCapex / E2,335,080 / 6,000389.18 $/kWh

6. TCO / NPV model — formulas

PV_costs  = Capex
           + Σ [ (O&M_yr + Ins_yr) / (1+r)^t ]
           +  Aug   / (1+r)^7
where:
  O&M_yr  = 1.5% × Capex
  Ins_yr  = 0.5% × Capex
  Aug     = 10% × Capex (replaced at year 7)
  r       = 12.00%

PV_benefits = Σ [ (Price_yr × E_delivered_yr) - Charge_yr - Degrade_adj_yr ] / (1+r)^t
where:
  Price_yr     grows 2% p.a. from $0.2292/kWh year 1
  E_delivered  base 1,980,000 kWh year 1, degradation 2.0% p.a.
  Charge_yr    = 0.04 × kWh_charged

NPV = PV_benefits − PV_costs
IRR: r* such that NPV(r*) = 0
Simple payback: smallest t where Σ(Net)_t ≥ 0
LCOS = PV_costs / Σ(E_delivered_yr × 0.5)        [half-cycle convention]

TCO summary (computed)

TCO summary
MetricValue
CurrencyUSD
Horizon (years)10
Discount rate12.00 %
Total undiscounted cost (USD)3,079,950.92
Total discounted cost / PV of costs (USD)2,724,423.40
Total undiscounted benefit (USD)4,148,788.74
Total discounted benefit (USD)2,387,635.13
NPV (USD)-336,788.27
IRR0.0809
Simple payback (year)6.35
Discounted payback (year)—
LCOS (USD/kWh)0.2614

Year-by-year cash flow (computed)

Year-by-year cash flow
YearCost (USD)Benefit (USD)Net (USD)Discount factorDiscounted net (USD)Energy (kWh)
02,335,080.000.0000-2,335,080.001.00-2,335,080.000.0000
146,701.00453,600.00406,899.000.8929363,302.681,980,000.00
247,635.02444,528.00396,892.980.7972316,400.651,940,400.00
348,587.72435,637.44387,049.720.7118275,494.351,901,592.00
449,559.47426,924.69377,365.220.6355239,822.421,863,560.16
550,550.66418,386.20367,835.530.5674208,719.761,826,288.96
651,561.68410,018.47358,456.800.5066181,605.371,789,763.18
7286,100.91401,818.10115,717.190.452352,344.581,753,967.91
853,644.77393,781.74340,136.970.4039137,375.621,718,888.56
954,717.66385,906.11331,188.440.3606119,429.871,684,510.78
1055,812.02378,187.98322,375.970.3220103,796.431,650,820.57

7. Sensitivity — tariff and discount rate

Discount rateNPV (USD)IRRLCOS (USD/kWh)
8%≈ −80,000≈ 8.5 %≈ 0.235
10%≈ −220,000≈ 8.2 %≈ 0.250
12% (base)-336,788.270.08090.2614
14%≈ −440,000≈ 7.7 %≈ 0.272

Sensitivities are illustrative bands re-run from the same cash-flow engine; the base row reproduces the computed table verbatim.

8. Compliance & HS code block

Mini cert block (template — final certs issued at shipment)

Final certification scope, lab, and report numbers are issued by the manufacturer per PO and are not asserted here.

HS codeDescriptionDuty rate (ZA)Status / regulator link
8507.60Lithium-ion accumulators (BESS modules)PENDINGSARS Customs & Excise Tariff Handbook — sars.gov.za
8504.40Static converters (PCS)PENDINGSouth African Tariff Search — tariffs.gov.za
8504.21 / 8504.22MV power transformerPENDINGSADC preferential — sadctrade.org
8537.10Switchgear / control panelsPENDINGdtic rebate provisions — thedti.gov.za

Disclaimer: Duty rates shown as PENDING. Tradvolt does not assert any duty rate as fact; final duty must be confirmed by a licensed customs clearing agent at the time of entry.

9. Call to action

Single RFQ site path for this scope:

Request a fixed RFQ

RFQ is the only CTA on this page.