Decision (r14): This guide defines the 12-step commissioning procedure tradvolt.com uses for CN→UK BMS shipments and the 14 documents required before booking confirmation is issued. Reference equipment family: Sungrow SBH100-400 residential BMS (5 kWh per module, 10–40 kWh per unit, 50 A max charge/discharge, 100% DoD, 0 ms switchover; OEM product page: Sungrow SBH100-400); reference cell: EVE LF304 (304 Ah, 3.2 V LFP prismatic, 4000 cycles to ≥80% @25 °C, 5450 g; OEM product page: EVE LF304). Horizon: pre-shipment (T−21) → archive (T+10). Evidence date: 2026-09-22. Limitation: indicative only — HS/duty code, broker fee, and day-rate cost slots are model assumptions until confirmed per shipment.

Compact decision table
ItemValueSource row below
Steps12§2, §7
Required docs (booking gate)14§1
Reference BMS modelSungrow SBH100-400§3, §12, §13
Reference cellEVE LF304 (304 Ah LFP)§3, §13
Sea transit (CN→UK)T+28 to T+34 days (model assumption)§3, R1
UK customs clearanceT+1 to T+3 days from arrival (model assumption)§3, R1
FAT witness booking48 h notice = 2 calendar days (model assumption)§3, R3
UN38.3 revision ruleST/SG/AC.10/11 revision in force on day of shipment (Rev.7 per cited UN page; check for newer rev at FAT)§6 Q1, R1
FW pin rulePinned pre-shipment; no update inside this SOP§6 Q5, R1
CE vs UKCA scopeBoth may apply; UKCA required where UK designated standard covers the BMS§6 Q3, R4
HS code / dutyPENDING — see R5 lookup path§7, R5

Purpose: repeatable, auditable commissioning for Battery Management Systems (BMS) shipped on the CN→UK corridor under tradvolt.com export programmes. Scope: pre-shipment build verification, in-transit state-of-charge (SoC) handling, UK port-of-entry customs interface, on-site commissioning acceptance.

Audience: tradvolt.com export coordinators, UK site engineers (contractor), OEM BMS suppliers (CN), and the appointed Third-Party Inspection Body (TIB).

Linked procedure index: r14 supersedes r13. Delta list is held by muse-ba.

1. Document Checklist (literal filenames)

Upload the items below to the export folder before issuing the Booking Confirmation. Files are checked into tradvolt-export/<shipment-id>/commissioning/.

Use lowercase, hyphen-separated filenames only. No spaces.

2. Process Map — Step Sequence

Step #ActionOwnerInput docOutput docDone-when
1Confirm BMS model (Sungrow SBH100-400) and firmware pin against the export order lineExport coordinator (tradvolt)Sales contract annexInternal commissioning recordModel + FW version match the order line in the ERP
2Request OEM datasheet, UN38.3 summary, MSDS, and CE/UKCA packs at OEM revision in forceExport coordinator (tradvolt)OEM document portalFolder OEM-Docs/ populatedAll four OEM documents present, dated within 12 months
3Pull SoC shipping window per cell chemistry from OEM datasheetOEM BMS supplier (CN)Sungrow SBH100-400 datasheet + EVE LF304 cell pageSoC-Shipping-Window.xlsxSoC band written into workbook with cell lot reference
4Pre-shipment FAT: SoC set, module balance check, BMS comm handshakeOEM BMS supplier (CN)FAT procedureFAT report attached to BMS-Comm-SOP-r14 file copyFAT countersigned by tradvolt witness
5Container packing with tilt/shock loggers and SoC band enforcedOEM BMS supplier (CN)Packing specPacking-List-BMS-Line-Items.csv + logger PDFsLogger PDFs attached; SoC band recorded per module
6TIB pre-loading inspection (CID-Inspection-Report)Third-Party Inspection BodyOEM docs + packing listCID-Inspection-Report.pdfTIB signs CID with no open findings
7Customs declaration (UK importer side): HS code mapped, valuation, commodity code for lithium cellsUK customs broker (named broker)Commercial invoice + SoC windowUK CDS entry + duty/VAT calculation (HS code PENDING — see R5)Entry accepted by UK Customs
8Transit handover and tracking custodyFreight forwarderBill of lading / CMR (FIATA docs)Custody logEach transfer signed and time-stamped
9UK site receipt and crate integrity checkUK site engineer (contractor)Packing list + logger PDFsReceipt noteNo shock/tilt breach; crate seals intact
10Site commissioning: BMS handshake, FW version verify, cell balancing, alarm path testUK site engineer (contractor)BMS-Comm-Protocol-*.pdfCommissioning logAll alarm paths close; FW matches pinned version
11UKCA / CE acceptance file closure (where applicable)tradvolt ComplianceAll commissioning evidenceAcceptance fileSign-off page countersigned by contractor + tradvolt
12Archive under /commissioning/<shipment-id>/ and trigger muse-ba reviewExport coordinator (tradvolt)Complete folderArchive index entrymuse-ba review ticket closed

3. Timeline (indicative)

PhaseWindowOwnerNotes
OEM doc collectionT−21 to T−14 days (7 days)tradvoltLead time varies by OEM; confirm at order placement
FAT + SoC settingT−10 to T−5 days (5 days)OEM CNWitness slots bookable on 48 h notice = 2 calendar days (model assumption; R3 quantified)
TIB inspectionT−3 to T−1 day (3 days)TIBTIB must have UN38.3 on file before signing CID
Sea transit CN→UKT0 to T+28 to T+34 days (28–34 days)Freight forwarderVessel schedule dependent; figure is a model assumption pending per-shipment booking (R1)
UK customs clearanceT+1 to T+3 days from arrival (1–3 days)UK customs brokerCDS entry lodged pre-arrival; figure is a model assumption pending broker confirmation (R1)
Site commissioningT+5 to T+10 days from arrival (5–10 days)UK site engineerSchedule site access in advance

4. Cost-Table Slots (indicative only)

Costs are labelled indicative because line items depend on the OEM, BMS model, and freight terms. No hard prices are quoted in this guide.

Line itemIndicative?UNCERTAIN?
OEM FAT and SoC setting serviceYesYes (model assumption)
TIB inspection fee (per shipment)YesYes (model assumption)
Shock/tilt loggers (per container)YesNo
UK customs broker fee (per entry)YesNo
Site commissioning day rateYesYes (model assumption)
Archive and review handling (internal)YesNo

UNCERTAIN cells flag line items where tradvolt has no current supplier quote on file.

5. RFQ CTA

To request a shipment-specific quote (HS code verification, broker fee, OEM datasheet revision check, TIB nomination), submit the RFQ form:

Request tradvolt RFQ →

Implementation note: no dataLayer push is attached to this RFQ CTA. (No PDF download is offered on this revision — the previous /downloads/... path was a placeholder and has been removed.)

6. FAQ

Q1. Which version of UN38.3 applies to a BMS shipment leaving CN after the latest UN manual revision?
A. The UN Manual of Tests and Criteria (UN publication ST/SG/AC.10/11, "UN Manual of Tests and Criteria") revision in force on the day of shipment applies (R1). The UN page currently lists ST/SG/AC.10/11/Rev.7; check at FAT whether a newer Rev. has been issued and re-pin accordingly. The OEM must hold a current UN38.3 test summary covering T.1–T.8; the TIB checks the revision date during CID.

Q2. Who signs the site acceptance — tradvolt, the contractor, or both?
A. Both. The site engineer (contractor) signs the commissioning log; tradvolt Compliance countersigns the acceptance file closure.

Q3. Can CE marking alone satisfy UK acceptance post-Brexit?
A. CE marking is recognised for limited categories. Where the BMS falls under a UK designated standard, a UKCA Declaration of Conformity is required alongside CE. The export coordinator confirms the route per shipment. CE is issued under the Regulation (EU) 2023/1542 (EU Battery Regulation) framework; UKCA certificate identifier is to be confirmed per shipment (R4).

Q4. What is the SoC band during sea transit?
A. The band is set by the OEM per cell chemistry and recorded in SoC-Shipping-Window.xlsx. For the reference equipment (Sungrow SBH100-400 / EVE LF304 LFP) the shipping-window figure is taken from the OEM datasheet at RFQ and recorded as a model assumption until confirmed per shipment. The TIB verifies at loading.

Q5. How are firmware updates handled during commissioning?
A. FW version is pinned before shipment. Updates after commissioning follow a separate change-control procedure outside this SOP. The pinned version is recorded in BMS-FW-Release-Notes-<version>.pdf (R1, R12).

7. HS code / duty — PENDING marker

HS code / UK duty: PENDING. For the reference equipment (EVE LF304 LFP cell + Sungrow SBH100-400 BMS cabinet) the export coordinator must look up the classification before issuing the booking confirmation. Concrete lookup path:

  1. UK Trade Tariff lookup tool — https://www.trade-tariff.service.gov.uk/ (enter the cell or BMS description; confirm chapter 85 subheading).
  2. UK duty / VAT calculation via the same Trade Tariff page (UK Global Tariff + VAT rate on import).
  3. EU TARIC cross-check for EU exit-side reference — https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en.
  4. WCO HS Nomenclature 2022 chapter/note cross-check — https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition.

EU battery framework: Regulation (EU) 2023/1542 (EU Battery Regulation).

8. Crawler Directive

<meta name="robots" content="noindex, nofollow"> is set on this guide until muse-ba completes the r14 review (also enforced as a live <meta> tag in the <head> of this document). The directive is rendered server-side and verified in the staging response header.

ClaimSource URLFile/section
UN38.3 covers tests T.1–T.8; UN Manual of Tests and Criteria designation is ST/SG/AC.10/11 (Rev.7 listed on the UN page)https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteriaUN38.3 test summary
Sungrow SBH100-400 residential BMS: 5 kWh per module; 10–40 kWh per unit; max 8 modules/unit, 4 units parallel, 160 kWh max; 50 A max charge/discharge; 100% DoD; 0 ms switchoverhttps://www.sungrowpower.com/en/products/residential-energy-storage-system/sbh100-150-200-250-300-350-40Sungrow-SBH100-400-Datasheet.pdf
EVE LF304 cell: 304 Ah nominal; 3.2 V; 4000 cycles @25 °C to ≥80%; 173.7 × 71.7 × 207.2 mm; 5450 ghttps://www.evemall.com/prismatic-lfp-cell/square-lithium-iron-phosphate-battery/lf304EVE-LF304-MSDS.pdf
Sea transit CN→UK corridor window T+28 to T+34 days (model assumption; vessel-schedule dependent)https://fiata.org/ (freight forwarding document framework — corridor framing only)§3 Timeline
UK customs clearance T+1 to T+3 days from arrival via CDS (model assumption; pending per-shipment broker confirmation)https://www.trade-tariff.service.gov.uk/§3 Timeline, Step 7
FW version pinned at pre-shipment; no in-SOP update path; BMS comms framed by IEC 61851-1:2017 (system-level conductive-charging context, not BMS-specific)https://webstore.iec.ch/en/publication/33644 (IEC 61851-1:2017)BMS-FW-Release-Notes-<version>.pdf
CE / UKCA route confirmed per shipment; UKCA required where UK designated standard covers the BMShttps://eur-lex.europa.eu/eli/reg/2023/1542/oj (Regulation (EU) 2023/1542 — EU Battery Regulation)CE/UKCA Declaration files
HS code / UK duty lookup path (R5)https://www.trade-tariff.service.gov.uk/ + https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en + https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-editionBM-Commercial-Invoice.pdf
Air-transport framing for BMS / lithium cells (IATA DGR; sea + air interface reference)https://www.iata.org/en/programs/cargo/dgr/UN38.3 chain
Wood packaging / ISPM 15 framing for crate integrity (IPPC ISPM standards list)https://www.ippc.int/en/core-activities/standards-setting/ispms/Packing-List-BMS-Line-Items.csv
FIATA freight forwarding document framework (B/L, CMR custody)https://fiata.org/Custody log
Archive path /commissioning/<shipment-id>//rfq/ (RFQ form — gates shipment archive)Internal commissioning record
BMS / portable-lithium safety standard reference: IEC 62133-2 (portable lithium cells)https://webstore.iec.ch/en/publication/70017 (IEC 62133-2)UN38.3 chain
Industrial / stationary lithium battery safety standard reference: IEC 62619:2022 ed2https://webstore.iec.ch/en/publication/64073 (IEC 62619:2022 ed2)UN38.3 chain
UK MCA marine guidance for lithium-ion battery installations: MGN 550 (M+F) Amendment 1https://www.gov.uk/government/publications/mgn-550-mf-amendment-1-electrical-installations-guidance-for-safe-design-installation-and-operation-of-lithium-ion-batteriesCID-Inspection-Report.pdf

10. Procedure Notes

11. Sign-Off Block

RoleNameDateSignature
Authortradvolt export deskr14 issue date
Reviewermuse-bapending
Approvertradvolt Compliancepending

Submit an RFQ to tradvolt