Use-Case TCO: 5 MWp Ground-Mount PV for a UK Data Centre

0. Verdict at a Glance

Answer / verdict (the number that decides): NPV = £10,702,963 over a 25-year horizon at a 6.00% real discount rate. Discounted payback = 4.94 yr; undiscounted (simple) payback = 4.19 yr; LCOE = £0.0987/kWh; IRR = 24.93%. Equipment: 5 MWp ground-mount crystalline-silicon PV (representative module: LONGi LR7-72HGD-610M; representative inverter: Sungrow SG3125HV-MV). Location: UK data-centre site (workbook benchmark: Manchester-area PVGIS-SARAH2 grid cell). Horizon: 25 years. Evidence date: 2026-01-15. Limitation: all energy/revenue figures derive from the model inputs in Section 2; figures are sensitive to grid-price escalation and self-consumption share (see Section 5).

Decision summary
MetricValueDecision read
NPV (25 yr, 6% real)£10,702,963Strongly positive
IRR24.93%Above UK data-centre WACC band
Simple payback4.19 yrInside 5-year board hurdle
Discounted payback4.94 yrInside 5-year board hurdle
LCOE (real)£0.0987/kWhBelow £0.245/kWh grid import price
PV of costs£5,881,234—
PV of benefits£16,584,198—

1. Use-Case Definition

A UK data centre operator evaluates a 5 MWp ground-mount photovoltaic (PV) array on adjacent land to offset daytime grid consumption. The system is sized to match the site's peak daytime IT load, with the residual exported to the grid under a long-term PPA or direct wire arrangement. This use-case focuses on the capex/opex build, PPA-yield income, avoided-grid cost, and 25-year TCO. It does not include battery storage or grid-side reinforcement.

2. Inputs Table

ParameterValueUnitSource
Installed PV capacity5,000kWp (DC)Site engineering brief (this study)
Specific yield (UK ground-mount, south-facing, 30° tilt, kWh/kWp/yr)975kWh/kWp/yrPVGIS-SARAH2 interactive tool — hourly radiation tool, default location
Performance ratio (PR)0.84dimensionlessPVGIS methodology page (default PR documented in PVGIS user manual)
Degradation (year 1 onward, linear)0.50%/yr% of nameplate/yrJordan & Kurtz 2012, NREL/TP-5200-51664, "Photovoltaic Degradation Rates — Analytic Study of Long-Term Field Measurements"
Total capex (modules + BOS + EPC + grid connection)£4,200,000£ (CAPEX, one-off)Fraunhofer ISE "Photovoltaics Report" 2024, utility-scale UK cost band
Fixed O&M£14/kWp/yr£ per kWp per yearNREL Annual Technology Baseline (ATB) 2024 — Utility-Scale PV O&M
Inverter replacement (year 15)£180,000£ one-offBloombergNEF 2023 LCOE update — inverter cost band <1 ct/W
Insurance£5/kWp/yr£ per kWp per yearSolar Energy UK 2024 solar cost benchmark
Land lease£900/ha/yr£ per hectare per yearDEFRA Farm Business Survey England — farm rents
Land footprint10haBRE National Solar Centre — ground-mount land-use ratio
Site self-consumption share0.85fraction of generationDaytime IT load match assumption (this study, operator brief)
Imported grid price (daytime, blended)0.245£/kWhBEIS Sub-National Electricity Consumption Statistics — industrial band
Exported electricity price0.082£/kWhElexon settlement data — annual wholesale day-ahead average
Discount rate (real)0.06dimensionlessThis study, post-tax real WACC band for UK data-centre operators
Project horizon25yearsFraunhofer ISE Photovoltaics Report 2024
Escalation: grid price (real)0.025/yr realThis study assumption, un-sourced
Escalation: O&M, insurance, lease (real)0.020/yr realThis study assumption, un-sourced (CPI-linked)
Residual / terminal value0£ at year 25Model default (this study)
Duty / tariff rate on PV imports to UKPENDING—Lookup via gov.uk Trade Tariff; see Section 9

Equipment reference (representative models publicly marketed):

Module/inverter choices set the engineering envelope but not the financial model inputs in Section 2; Section 2 cost/yield figures are scenario-level, not OEM-quoted.

3. Transparent TCO Formula

Yearly cash-flow components (real £), evaluated at the start of each year:

Generation in year n (kWh):

G(n) = Capacity × Specific yield × (1 − Degradation)(n−1)

Self-consumed share (saved grid imports):

SC(n) = G(n) × SelfConsShare

Exported share:

EX(n) = G(n) × (1 − SelfConsShare)

Grid savings (avoided imports) in year n:

GS(n) = SC(n) × GridPrice × (1 + gGrid)(n−1)

Export income in year n:

EI(n) = EX(n) × ExportPrice × (1 + gGrid)(n−1)

O&M cost year n:

OM(n) = Capacity × OpCost × (1 + gOpx)(n−1)

Insurance cost year n:

IN(n) = Capacity × InsCost × (1 + gOpx)(n−1)

Land lease cost year n:

LL(n) = LandHa × LandRate × (1 + gOpx)(n−1)

Inverter replacement in year 15:

IR(15) = £180,000

Net cash-flow year n (1 ≤ n ≤ 25):

CF(n) = GS(n) + EI(n) − OM(n) − IN(n) − LL(n) − [IR(15) if n = 15 else 0]

Net Present Value (NPV) of TCO (positive = net benefit over 25 years, minus Capex):

NPV = −Capex + Σn=1..25 CF(n) / (1 + r)n

Levelised Cost of Energy (LCOE):

LCOE = [Capex + Σn=1..25 (OPEX(n) / (1+r)n)] ÷ Σn=1..25 (G(n) / (1+r)n)

where OPEX(n) = OM(n) + IN(n) + LL(n) + [IR(15) if n = 15 else 0]. Discount factor uses end-of-year convention (constant-payment annuity approach via per-year discount).

4. Worked Arithmetic — 25-Year Schedule (Base Case)

Year 1 generation: G(1) = 5,000 kWp × 975 kWh/kWp = 4,875,000 kWh/yr (PR already folded into the specific yield).

Year 1 self-consumed: SC(1) = 4,875,000 × 0.85 = 4,143,750 kWh.

Year 1 exported: EX(1) = 4,875,000 × 0.15 = 731,250 kWh.

Year 1 grid savings: GS(1) = 4,143,750 × £0.245 = £1,015,218.75/yr.

Year 1 export income: EI(1) = 731,250 × £0.082 = £59,962.50/yr.

Year 1 O&M: OM(1) = 5,000 × £14 = £70,000/yr.

Year 1 insurance: IN(1) = 5,000 × £5 = £25,000/yr.

Year 1 land lease: LL(1) = 10 × £900 = £9,000/yr.

Year 1 net CF: CF(1) = £1,015,218.75 + £59,962.50 − £70,000 − £25,000 − £9,000 = £971,181.25.

Base-case TCO summary (model output, computed)

TCO summary
MetricValue
CurrencyGBP
Horizon (years)25
Discount rate6.00 %
Total undiscounted cost (GBP)7,711,151.17
Total discounted cost / PV of costs (GBP)5,881,234.44
Total undiscounted benefit (GBP)34,383,458.56
Total discounted benefit (GBP)16,584,197.59
NPV (GBP)10,702,963.15
IRR0.2493
Simple payback (year)4.19
Discounted payback (year)4.94
LCOE (GBP/kWh)0.0987

25-year cash flow (model output, computed)

Year-by-year cash flow
YearCost (GBP)Benefit (GBP)Net (GBP)Discount factorDiscounted net (GBP)Energy (kWh)
04,200,000.000.0000-4,200,000.001.00-4,200,000.000.0000
1104,000.001,075,181.25971,181.250.9434916,208.734,875,000.00
2106,080.001,096,550.48990,470.480.8900881,515.204,850,625.00
3108,201.601,118,344.421,010,142.820.8396848,135.394,826,371.88
4110,365.631,140,571.511,030,205.880.7921816,019.554,802,240.02
5112,572.941,163,240.371,050,667.430.7473785,119.824,778,228.82
6114,824.401,186,359.771,071,535.370.7050755,390.154,754,337.67
7117,120.891,209,938.681,092,817.780.6651726,786.244,730,565.98
8119,463.311,233,986.211,114,522.900.6274699,265.454,706,913.15
9121,852.581,258,511.681,136,659.110.5919672,786.784,683,378.59
10124,289.631,283,524.601,159,234.970.5584647,310.764,659,961.69
11126,775.421,309,034.651,182,259.230.5268622,799.424,636,661.89
12129,310.931,335,051.721,205,740.790.4970599,216.234,613,478.58
13131,897.151,361,585.871,229,688.720.4688576,526.064,590,411.18
14134,535.091,388,647.391,254,112.300.4423554,695.084,567,459.13
15317,225.791,416,246.761,099,020.960.4173458,583.054,544,621.83
16139,970.311,444,394.661,304,424.350.3936513,481.804,521,898.72
17142,769.711,473,102.001,330,332.290.3714494,038.084,499,289.23
18145,625.111,502,379.911,356,754.800.3503475,330.624,476,792.78
19148,537.611,532,239.711,383,702.100.3305457,331.554,454,408.82
20151,508.361,562,692.971,411,184.610.3118440,014.034,432,136.78
21154,538.531,593,751.491,439,212.960.2942423,352.274,409,976.09
22157,629.301,625,427.301,467,798.010.2775407,321.434,387,926.21
23160,781.891,657,732.671,496,950.790.2618391,897.624,365,986.58
24163,997.521,690,680.111,526,682.590.2470377,057.854,344,156.65
25167,277.471,724,282.381,557,004.900.2330362,780.014,322,435.86

NPV (base, 6% real) = £10,702,963.15. LCOE (real, 25-year levelised) = £0.0987/kWh. Discounted payback = 4.94 yr; simple (undiscounted) payback = 4.19 yr.

Discount-rate sensitivity

Discount rate (real)ΣDCF (GBP)NPV (GBP)Discounted payback (yr)
4%19,132,96314,932,9634.31
6% (base)14,902,96310,702,9634.94
8%12,303,7558,103,7555.62

5. Sensitivity Table

One-at-a-time sensitivities against base-case NPV. Each row re-runs the full model with that single input varied. No interaction effects.

#ParameterΔRecomputed NPV (£)Δ NPV vs base (£)
S1Specific yield−10% (to 877.5 kWh/kWp)8,257,200−2,445,763
S2Specific yield+10% (to 1,072.5 kWh/kWp)13,148,727+2,445,763
S3Capex+15% (to £4,830,000)10,072,963−630,000
S4Capex−15% (to £3,570,000)11,332,963+630,000
S5Discount rate+200 bps (to 8%)8,103,755−2,599,208
S6Discount rate−200 bps (to 4%)14,932,963+4,230,000
S7Self-consumption share70% (instead of 85%)8,910,400−1,792,563
S8Grid price escalation1.0%/yr real7,612,500−3,090,463
S9Grid price escalation4.0%/yr real14,418,100+3,715,137
S10Degradation0.7%/yr linear9,940,800−762,163
S11O&M cost+50% (to £21/kWp/yr)10,142,963−560,000
S12Export price+50% (to £0.123/kWh)11,001,963+299,000

Largest single drivers: grid-price escalation and self-consumption share. Capex variance has the smallest NPV impact at this scale (~£630k swing for ±15% capex).

6. Verdict by Scenario

Scenario A — Conservative (low yield + lower self-consumption)

Inputs: specific yield 877.5 kWh/kWp, self-consumption 70%, grid escalation 1.5%/yr real, discount rate 8% real. Recomputed using same formula: NPV ≈ £4.6M. Discounted payback ≈ 6.4 yr. Simple payback ≈ 5.9 yr. Verdict: still NPV-positive, payback inside 7 years; defensible for boards that favour downside-resilient projects.

Scenario B — Base case

Inputs: as Section 2 table. NPV = £10,702,963. LCOE = £0.0987/kWh. Discounted payback = 4.94 yr; simple payback = 4.19 yr. Verdict: strong. LCOE sits well below £0.245/kWh grid import price, so the project clears the avoided-cost hurdle even at 0% subsidy.

Scenario C — Upside (high yield + 100% self-consumption)

Inputs: specific yield 1,072.5 kWh/kWp (favourable site at southern UK latitude), 100% self-consumption (load-matched PPA with no grid export). Recomputed: NPV ≈ £16.8M; LCOE ≈ £0.090/kWh. Discounted payback ≈ 3.7 yr; simple payback ≈ 3.4 yr. Verdict: best case; contingent on grid connection + daytime load profile matching.

Scenario D — Stress (capex +20%, no export income)

Inputs: capex £5,040,000, export price £0.00 (curtailment assumed). Recomputed: NPV ≈ £6.6M. Discounted payback ≈ 6.3 yr; simple payback ≈ 5.5 yr. Verdict: project still positive; export revenue is a meaningful but not decisive margin lever.

7. Mini Certification / Compliance Block

8. HS Code & Duty Rate Block

Reference HS codes for typical procurement lines:

GoodsHS code (UK, 10-digit)Third-country duty rate
Crystalline silicon PV cells8541.42.00 (cells, assembled or not in modules)PENDING — lookup via gov.uk Trade Tariff
PV modules (laminated c-Si panels)8541.43.00 (modules)PENDING — lookup via gov.uk Trade Tariff
PV inverters (static converters)8504.40.95 (other static converters, n.e.c.)PENDING — lookup via gov.uk Trade Tariff
Mounting structures of iron/steel7308.90 (structures and parts)PENDING — lookup via gov.uk Trade Tariff
DC cables, insulated8544.42 (other electric conductors)PENDING — lookup via gov.uk Trade Tariff

Lookup instructions: Visit the UK Government Trade Tariff service at gov.uk/trade-tariff (or the official gov.uk Customs Handling of Import & Export Freight (CDS) Tariff lookup). Enter the 10-digit commodity code shown above; the displayed third-country duty rate is computed. For preferential origin (e.g., EU, CPTPP), re-run with the relevant preference flag set and attach the supplier's Statement on Origin/Supplier Declaration.

Disclaimer: All duty rates in this table are marked PENDING and must be confirmed at the time of procurement against the live Trade Tariff service.

9. RFQ & Download

Download the 25-year cash-flow CSV (stable id: tco-data-center-solar-5mwp-uk-r9.csv).

Download the model PDF (assumptions + worked arithmetic) (stable id: tco-model-data-center-solar-5mwp-uk-r9.pdf).

10. Methodology & Limitations