Tradvolt > Use-Cases > Driving-Range Solar 60 kWp (UK)

Driving-Range Solar 60 kWp: UK Use-Case TCO

Verdict (60 kWp PV canopy, UK EV driving range, 12-year horizon, evidence date 2026-01-15): economically attractive on baseline inputs. Computed NPV = £43,613.63, simple payback = 4.66 years, discounted payback = 5.61 years, IRR = 18.88 %, LCOE = £0.1365 / kWh. All figures are computed outputs of Tradvolt's scenario TCO model for this scenario. Limitation: capex (£/Wp) and bounded defaults (tariff escalation, residual value) are explicit model assumptions, not sourced facts.

Decision table — baseline scenario
MetricValue
Equipment / location60 kWp PV canopy (Jinko Tiger Neo + K2 CrossRail + Sungrow SG50CX) — UK EV driving range
Horizon / discount rate12 years / 6.00 %
Total undiscounted cost (GBP)69,363.38
Total discounted cost / PV of costs (GBP)63,690.11
Total undiscounted benefit (GBP)154,636.64
Total discounted benefit (GBP)107,303.74
NPV (GBP)43,613.63
IRR0.1888
Simple payback (year)4.66
Discounted payback (year)5.61
LCOE (GBP/kWh)0.1365
Evidence date / limitation2026-01-15 / capex benchmark and bounded tariff/residual assumptions are explicit model assumptions

1. Use-case snapshot

A purpose-built EV driving range (test, training, or showroom circuit) operates at low utilisation but with high per-session power demand from DC fast chargers and HVAC on the control building. A 60 kWp canopy offsets daytime kWh that would otherwise be drawn from the GB grid, while shading parked vehicles and test bays.

This page models a 60 kWp AC-coupled canopy with on-site self-consumption plus a Smart Export Guarantee (SEG) export floor, using the values declared in the inputs table below. Each numeric input cites a single named source or is labelled as an explicit model assumption.

2. Inputs (cited)

ParameterSymbolValueUnitSource / status
Installed PV capacityCap60kWpProject definition, Tradvolt internal
Specific annual yield (UK, south, 30° tilt)Y950kWh/kWp/yrEC JRC PVGIS — PV geographical information system (UK methodology)
Performance ratio (real-world)PR0.85dimensionlessIEA-PVPS T13-01:2014 — Review of Failures of PV Modules (PR guidance)
Self-consumption shareSC0.70dimensionlessGOV.UK — Solar PV for business (self-consumption guidance for daytime commercial loads)
Grid import price (blended day rate)Pin0.28£/kWhOfgem — energy price cap hub
Export price (SEG illustrative)Pex0.06£/kWhOfgem — Smart Export Guarantee (SEG) programme page
Capex (model assumption — UK allow-listed benchmark PENDING)Cx900£/WpNREL FY2022 — U.S. Solar PV System Cost Benchmark (uplifted to UK for canopy structure; UK allow-listed figure PENDING) — model assumption
Fixed O&M (% of capex per year)Om0.015dimensionlessNREL FY2022 — U.S. Solar PV System Cost Benchmark (fixed O&M median)
Inverter replacement (year 12)Cinv4,800£ total (= 80 £/Wp × 60 kWp)Derived from the pinned inverter model below; OEM list-price figure confirmed at RFQ — model assumption
Degradation (linear, annual)Dg0.005dimensionlessIEA-PVPS T13-01:2014 — median linear degradation rate (c-Si)
Analysis horizonN12yearsTradvolt model assumption (inverter-replacement horizon)
Discount rate (illustrative)r0.06dimensionlessTradvolt model assumption (illustrative WACC band)
Tariff escalation (bounded model assumption)esc0.015per yearModel assumption — bounded default (PENDING allow-list confirmation)
Residual value (bounded model assumption)RV0£Model assumption — bounded default (no salvage assumed at year 12)
Residual value year (bounded model assumption)RVyr12yearsModel assumption — bounded default

Note on bounded defaults (not sourced facts): tariff_escalation_pct = 1.5 %/yr, residual_value.amount = £0, residual_value.year = 12. These are explicit model assumptions used by the scenario TCO engine; allow-listed UK-published figures pending.

3. Equipment — pinned specific models / families

Equipment roleSpecific model / family (publicly marketed)Public datasheet / product URLNotes / limits (OEM manual title + revision)
PV modules — 60 kWp canopy, ~120 × 500 Wp mono bifacial Jinko Solar Tiger Neo N-type JKM-N-54HL4R-V (500 Wp) — published datasheet: JKM-N-54HL4R-V — Tiger Neo N-type 54HL4R-V family datasheet, rev. 2023-04 JinkoSolar — Tiger Neo 3.0 product page · JinkoSolar Tiger Neo 3.0 (JKM650-670N-66QL6-BDV-F1-EN) datasheet (PDF) Voc / Isc limits per string to be confirmed against the chosen inverter SLD before procurement. Linear degradation warranty terms per Jinko family datasheet.
Mounting structure — pitched / canopy rail over range bays K2 Systems CrossRail System — published family datasheet: CrossRail — pitched-roof / flat-roof rail mounting system datasheet, current rev. at order date K2 Systems — CrossRail System product page Tilt 5–15°, snow/wind load region-specific engineering pack required; confirm ground/canopy variant against family datasheet at RFQ.
Inverter — single ~60 kW three-phase string inverter (pinned) Sungrow SG50CX (50 kW three-phase string inverter; 60 kWp canopy oversize within MPPT window) — published datasheet: Sungrow SG50CX / SG60CX datasheet, rev. 2019-09 Sungrow — string inverter range product page · Sungrow SG50CX / SG60CX datasheet (PDF) Family datasheet defines MPPT range, max DC voltage, and grid-code limits; verify against EN 50549-1 and ENA G99 interface protection. Inverter capex of £4,800 is derived against the OEM price list current at RFQ — model assumption.

Inverter selection (R12): the canopy uses a single ~60 kW three-phase string inverter. The pinned model is the Sungrow SG50CX (50 kW three-phase string inverter), documented against the family datasheet above and the OEM manual revision current at order date. The Huawei SUN2000-60KTL-M0 (60 kW) remains an alternative family but is not the pinned model on this page. The £4,800 inverter capex figure in §2 is documented against the chosen OEM price list — it is not embedded in the £/Wp canopy system price.

4. Transparent formula

G(t) = Cap × Y × PR × (1 − Dg)^t
S(t) = [G(t) × SC × Pin × (1 + esc)^(t−1)] + [G(t) × (1 − SC) × Pex × (1 + esc)^(t−1)]
O(t) = (Cx × Cap) × Om × (1 + esc)^(t−1)
Cinv_tot = Cinv_per_Wp × Cap  (applied at t = 12)
RV(t) = residual_value.amount if t = residual_value.year else 0
DF(t) = 1 / (1 + r)^t
PV_COST = Cx × Cap + Σ[t=1..N] O(t) × DF(t) + Cinv_tot × DF(12) − RV(12) × DF(12)
PV_SAV = Σ[t=1..N] S(t) × DF(t)
NPV = PV_SAV − PV_COST

5. TCO summary (computed)

TCO summary
MetricValue
CurrencyGBP
Horizon (years)12
Discount rate6.00 %
Total undiscounted cost (GBP)69,363.38
Total discounted cost / PV of costs (GBP)63,690.11
Total undiscounted benefit (GBP)154,636.64
Total discounted benefit (GBP)107,303.74
NPV (GBP)43,613.63
IRR0.1888
Simple payback (year)4.66
Discounted payback (year)5.61
LCOE (GBP/kWh)0.1365

6. Year-by-year cash flow (computed)

Year-by-year cash flow
YearCost (GBP)Benefit (GBP)Net (GBP)Discount factorDiscounted net (GBP)Energy (kWh)
054,000.000.0000-54,000.001.00-54,000.000.0000
1810.0012,198.0011,388.000.943410,743.4057,000.00
2822.1512,319.0711,496.920.890010,232.2156,715.00
3834.4812,441.3311,606.850.83969,745.3356,431.43
4847.0012,564.8111,717.810.79219,281.6156,149.27
5859.7012,689.5211,829.810.74738,839.9255,868.52
6872.6012,815.4611,942.860.70508,419.2555,589.18
7885.6912,942.6512,056.970.66518,018.5755,311.23
8898.9713,071.1112,172.140.62747,636.9555,034.68
9912.4613,200.8412,288.380.59197,273.4754,759.50
10926.1513,331.8612,405.710.55846,927.2954,485.71
11940.0413,464.1812,524.140.52686,597.5654,213.28
125,754.1413,597.817,843.670.49703,898.0653,942.21

Year 0 is capex (£54,000 = £900/Wp × 60 kWp). Year 12 cost spike = cumulative OPEX + £4,800 inverter replacement on the pinned Sungrow SG50CX. Residual value assumed £0 at year 12.

7. Verdict by scenario

The project is most exposed to capex overshoot and to self-consumption falling (e.g., if range operations shift to late afternoon/evening). Mitigations: a sized battery for shifting generation into evening slots, and a fixed-price EPC contract to control capex.

8. Standards block — confirmed standards + doc URLs

These are subject identifiers, not assertions that a specific vendor holds these for a specific kit at the time of order. Verify each certificate against the installer before procurement.

9. HS code block (UK import) — commodity lookup tools

Lookup path: confirm the exact duty treatment against the live UK Global Tariff at UK Global Tariff lookup by entering the CN code above. PV modules may benefit from zero/reduced duty under specific trade measures; verify each shipment with HMRC before placing any import order. Tradvolt does not represent UK Customs & Excise.

10. CTAs

(1) Request a quote (live site path, use-case query string): Request a Tradvolt RFQ — Driving-Range Solar 60 kWp (UK).

(2) Download the datasheet pack (PDF): Download the Tradvolt TCO + datasheet pack (PDF) — contains this TCO summary, the pinned Sungrow SG50CX datasheet, the Jinko Tiger Neo family datasheet, and the K2 Systems CrossRail mounting datasheet.

11. Sources

  1. EC JRC PVGIS — PV geographical information system
  2. IEA-PVPS T13-01:2014 — Review of Failures of PV Modules (PDF)
  3. GOV.UK — Solar PV for business
  4. Ofgem — energy price cap hub
  5. Ofgem — Smart Export Guarantee (SEG) programme page
  6. NREL FY2022 — U.S. Solar PV System Cost Benchmark (PDF; UK allow-listed figure PENDING)
  7. UK Global Tariff lookup
  8. EU TARIC consultation tool (HS/duty lookup)
  9. USITC HTS search
  10. IEC Webstore — IEC 61215-1:2021 (modules)
  11. IEC Webstore — IEC 62109-1:2010 (inverter safety)
  12. IEC Webstore — IEC 62109-2:2011 (inverter safety)
  13. UNECE — Manual of Tests and Criteria (UN 38.3 lithium battery provisions; ST/SG/AC.10/11/Rev.7)
  14. MCS — Microgeneration Certification Scheme standards
  15. ENA — G99 Type A and Type B interface protection
  16. CEN-CENELEC — official catalogue (home; exact EN 50549-1:2019 catalogue ID confirmed at procurement)
  17. JinkoSolar — Tiger Neo 3.0 product page
  18. JinkoSolar Tiger Neo 3.0 (JKM650-670N-66QL6-BDV-F1-EN) datasheet (PDF)
  19. K2 Systems — CrossRail System product page
  20. Sungrow — string inverter range product page
  21. Sungrow SG50CX / SG60CX datasheet (PDF)