Tradvolt › Use Cases › Factory Solar 5 MWp — AU R9

Factory Solar 5 MWp — Australia Use-Case & TCO

Indicative TCO brief · Slug /use-cases/factory-solar-5mwp-au-r9/ · Equipment: LONGi Hi-MO 5m + Huawei SUN2000-330KTL-H1 + K2 Systems N-Rack · Location: AU rooftop/industrial · Horizon: 25 yr · WACC: 7.00% · Evidence date: 2026-09-22.

noindex internal R9

Verdict (answer first)

Proceed to RFQ. NPV = 11,380,668 AUD over 25 years at 7.00% WACC; IRR = 25.73%; simple payback = 4.09 years; discounted payback = 4.94 years; LCOE = 0.0646 AUD/kWh. Equipment family: 5 MWp of LONGi Hi-MO 5m (LR5 series, bifacial mono-PERC) with Huawei SUN2000-330KTL-H1 string inverters on a K2 Systems N-Rack roof mount. Location: Australian industrial rooftop. Horizon: 25 years. Evidence date: 2026-09-22. Limitation: figures are the COMMITTED COMPUTED TABLES in §3–§4; tariff escalator, self-consumption ratio, avoided tariff, capex per Wp and export tariff below are bounded model assumptions, not sourced facts.

Decision summary
Decision pointValueReading
NPV @ 7% WACC, 25 yr11,380,667.80 AUDStrongly positive
IRR25.73%Well above 7% hurdle
Simple payback4.09 yrInside capex-recovery window
Discounted payback4.94 yrInside capex-recovery window
LCOE0.0646 AUD/kWhBelow typical AU C&I grid tariff band
Total undiscounted cost (AUD)7,906,446.70—
PV of costs (AUD)6,129,904.12—
Total discounted benefit (AUD)17,510,571.93—
VerdictProceed to RFQ subject to PR measurement & HS-code verification (see §6)

Request pricing: Submit an RFQ via the Tradvolt RFQ form (canonical site path).

1. Equipment (named, publicly marketed)

Table E-1 — Named equipment with manufacturer page
LineModel / familyRoleManufacturer page
ModulesLONGi Hi-MO 5m (LR5-72HBD / LR5-54HTH, bifacial mono-PERC)DC generator, ~5 MWpLONGi Hi-MO 5m family page
String invertersHuawei SUN2000-330KTL-H1 (330 kW, 1500 V DC, 8 MPPT)DC-AC conversion, C&I 3-phaseHuawei SUN2000-330KTL-H1 product page
Mounting structureK2 Systems N-Rack system (driven-pile / roof-adapted rail)Module support, ballast/fixingK2 Systems N-Rack system page

Module/inverter datasheets and the K2 installation manual (revision confirmed at RFQ) define the torque limits, max system voltage, MPPT operating window and module bifaciality assumptions. Exact SKU is locked at RFQ award; the family names above are bounded model assumptions until then.

2. Inputs (sourced + explicit bounded assumptions)

Table I-1 — Cost & performance inputs
ParameterValueUnitSource / status
Nameplate capacity5.0MWpSite brief
Year-1 generation (PVGIS-SARAH2, AU industrial rooftop reference)8,500,000.00kWhEC JRC PVGIS + EU PVGIS calculator
Specific yield (derived from year-1 generation)1700kWh/kWp/yrDerived from PVGIS year-1 figure ÷ 5.0 MWp
Performance Ratio (PR)0.82dimensionlessPR band: IEA-PVPS Trends in PV Applications 2024
Module degradation0.5%/yrp.a.PR band: IEA-PVPS Trends in PV Applications 2024
Avoided tariff (model input)0.18AUD/kWhModel assumption: explicit bounded default; cross-check against AU industrial tariff band before commit
Tariff escalator3.0%/yrp.a.Model assumption: explicit bounded default
Self-consumption ratio0.70dimensionlessModel assumption: explicit bounded default for continuous-load factory
System capex (model input)0.95AUD/WpModel assumption: explicit bounded default; UK C&I benchmark: DESNZ solar PV cost data
O&M1.4% of capexp.a.Model assumption: bounded default
Insurance0.3% of capexp.a.Model assumption: bounded default
Inverter replacement (mid-life)~12% of capex (single line at Y12)one-offModel assumption: bounded default, consistent with Huawei SUN2000-330KTL-H1 string-inverter mid-life refresh convention
Decommission reserve (Y25)~6% of capexend-of-lifeModel assumption: bounded default
WACC7.00%/yrp.a.Model assumption: bounded default; AU reference rates: RBA
Horizon25yearsStandard industrial-PV horizon
Residual valueexplicit bounded default = 0 AUD; recognised at end-of-horizonAUDModel assumption
Residual value year25yearsModel assumption
PV export tariff (kWh exported beyond self-consumption)0.00 AUD/kWhAUD/kWhModel assumption: explicit bounded default; AU behind-the-meter export compensation is scheme- and DNSP-dependent; verify with DNSP before commit

3. Computed TCO summary (SCENARIO OUTPUTS)

TCO summary
MetricValue
CurrencyAUD
Horizon (years)25
Discount rate7.00 %
Total undiscounted cost (AUD)7,906,446.70
Total discounted cost / PV of costs (AUD)6,129,904.12
Total undiscounted benefit (AUD)40,858,638.58
Total discounted benefit (AUD)17,510,571.93
NPV (AUD)11,380,667.80
IRR0.2573
Simple payback (year)4.09
Discounted payback (year)4.94
LCOE (AUD/kWh)0.0646

4. Year-by-year cash flow (SCENARIO OUTPUTS)

Year-by-year cash flow
YearCost (AUD)Benefit (AUD)Net (AUD)Discount factorDiscounted net (AUD)Energy (kWh)
04,750,000.000.0000-4,750,000.001.00-4,750,000.000.0000
180,750.001,198,500.001,117,750.000.93461,044,626.178,500,000.00
282,365.001,228,282.731,145,917.730.87341,000,888.928,457,500.00
384,012.301,258,805.551,174,793.250.8163958,981.248,415,212.50
485,692.551,290,086.871,204,394.320.7629918,826.668,373,136.44
587,406.401,322,145.531,234,739.130.7130880,351.948,331,270.76
689,154.521,355,000.841,265,846.320.6663843,486.858,289,614.40
790,937.621,388,672.611,297,735.000.6227808,164.148,248,166.33
892,756.371,423,181.131,330,424.760.5820774,319.328,206,925.50
994,611.501,458,547.181,363,935.690.5439741,890.648,165,890.87
1096,503.721,494,792.081,398,288.350.5083710,818.898,125,061.42
1198,433.801,531,937.661,433,503.860.4751681,047.368,084,436.11
12670,402.481,570,006.31899,603.840.4440399,434.868,044,013.93
13102,410.521,609,020.971,506,610.440.4150625,189.778,003,793.86
14104,458.741,649,005.141,544,546.400.3878599,001.737,963,774.89
15106,547.911,689,982.921,583,435.010.3624573,909.727,923,956.02
16108,678.871,731,978.991,623,300.120.3387549,867.917,884,336.23
17110,852.451,775,018.671,664,166.230.3166526,832.417,844,914.55
18113,069.491,819,127.881,706,058.390.2959504,761.127,805,689.98
19115,330.881,864,333.211,749,002.330.2765483,613.727,766,661.53
20117,637.501,910,661.891,793,024.390.2584463,351.587,727,828.22
21119,990.251,958,141.841,838,151.590.2415443,937.667,689,189.08
22122,390.062,006,801.671,884,411.610.2257425,336.517,650,743.14
23124,837.862,056,670.691,931,832.830.2109407,514.117,612,489.42
24127,334.622,107,778.951,980,444.340.1971390,437.917,574,426.97
25129,881.312,160,157.262,030,275.950.1842374,076.677,536,554.84

Tables §3 and §4 are the COMPUTED TABLES. No other financial figure is asserted in this document; all narrative refers back to these cells.

5. Certification & compliance pointers (verify with EPC)

Table C-1 — Indicative certification pointers
ItemStandard / scheme (designation, edition, issuer)Issuer / registerStatus
PV modules (LONGi Hi-MO 5m family)UL 61730-1 (Photovoltaic (PV) Module Safety Qualification — Part 1)UL Standards & Engagementnone claimed; verify with EPC at RFQ
PV modules (design qualification)IEC 61215-1:2021 ed2 (design qualification test requirements for c-Si & thin-film flat-plate PV modules, TC 82)IEC Webstorenone claimed; verify with EPC at RFQ
String inverter (Huawei SUN2000-330KTL-H1)IEC 62109-1:2010 (Safety of power converters for use in PV power systems — Part 1: General requirements, TC 82); use jointly with IEC 62109-2:2011 (Part 2: Particular requirements for inverters)IEC Webstore (62109-1) · IEC Webstore (62109-2)none claimed; verify with EPC at RFQ
Designer / installer accreditation (AU)CEC accreditation (Clean Energy Council, designer/installer)Clean Energy Council Products Program (verify accreditation register before contract award)none claimed; verify with EPC at RFQ
Module / inverter listing (AU)CEC approved product list (modules & inverters)Clean Energy Council Products Program (verify listing before contract award)none claimed; verify with EPC at RFQ

No certification numbers are asserted. Listing/accreditation registers must be checked at RFQ award against the exact SKU shipped.

6. HS-code block & customs lookup path

Table H-1 — Indicative classification (duty rates PENDING)
ItemHS code (suggested)Description basisAU duty
PV modules8541.43WCO HS Nomenclature 2022 edition — photovoltaic cells & panelsPENDING
String inverters8504.40WCO HS 2022 — static convertersPENDING
Mounting structure7308.90WCO HS 2022 — other structures & partsPENDING
DC cabling8544.49WCO HS 2022 — other electric conductorsPENDING

Mandatory customs lookup before any entry:

  1. Open the Australian Border Force Working Tariff (free online) and confirm the 10-digit customs tariff for each line above via the current tariff / tariff-classification page.
  2. For origin-based preferences, consult the relevant free-trade-agreement text on the DFAT FTA index for the specific HS subheading.
  3. If GST applies to the import, factor it on top of (Duty + Customs Value); GST is not a duty.

Disclaimer. Duty figures are marked PENDING by policy. Tradvolt does not assert a duty rate as fact. Any final duty payable depends on (a) the exact HS subheading, (b) the country of origin, (c) any FTA preference at the time of import, and (d) the Customs Value calculated under section 161 of the Customs Act 1901. Confirm with the importer of record or a licensed customs broker before procurement contracts are signed.

7. Calls to action

Submit an RFQ via the Tradvolt RFQ form (canonical site path; supply the use-case slug factory-solar-5mwp-au-r9 in the form's use-case field).

Cross-reference reading: EU PVGIS for AU-adjusted year-1 yield, and DESNZ solar PV cost data as a C&I capex benchmark.