Food-Processing Plant Solar 900 kWp — 25-Year TCO (India, Region R9)

Verdict (evidence-date 2026-09-22): For a 900 kWp captive solar plant serving a food-processing facility in Indian Region R9, over a 25-year horizon at a 10.00% discount rate, the base case yields NPV ≈ ₹76,510,691, simple payback ≈ 4.59 yr, discounted payback ≈ 6.29 yr, IRR ≈ 23.63%, and LCOE ≈ ₹5.16/kWh. Recommendation: pursue with a standard EPC contract and a performance guarantee. The same figures are reproduced in the decision table immediately below and originate from the COMPUTED TABLES in §3 (computed). Limitation: this is a base-case scenario — sensitivity ranges in §4 bracket outcomes under ±15% CAPEX, ±10% specific yield, and 2–6% tariff escalation.

Decision table — headline metrics (base case)
MetricValue
Headline NPV₹76,510,691
Simple payback4.59 yr
Discounted payback6.29 yr
IRR23.63%
LCOE₹5.16/kWh
RecommendationPursue (base case)

1. Scope & Site Basis

900 kWp grid-connected captive solar at a food-processing facility in Region R9 (a sample cluster covering parts of Maharashtra/Goa; substitute your DISCOM's tariff order for binding results). The equipment mix and OEM model references below are real, publicly marketed products; cite the OEM manual title and revision before procurement.

2. Inputs Table (cited sources)

ParameterValueUnitSource
Plant DC capacity900kWpTradVolt assumption, brief (2026-09-22)
Module model (exact SKU)Jinko Tiger Neo 3.0 — JKM650-670N-66QL6-BDV-F1 (e.g. JKM670N-66QL6-BDV-F1 at 670 Wp STC, 24.80% module efficiency, Vmp 43.09 V, Imp 15.55 A, Voc 50.98 V, Isc 16.22 A; –0.26 %/°C Pmax; 12-yr product / 30-yr linear power warranty; 1 % + 0.35 %/yr degradation)—JinkoSolar Tiger Neo 3.0 datasheet PDF: jinkosolarcdn.shwebspace.com Tiger Neo 3.0 Flyer
Inverter model (exact SKU)Sungrow SG250HX (250 kW three-phase string inverter, C&I; 4 units ≈ 1,000 kW AC)—Sungrow string-inverter product page (SG250HX belongs to the SG HX C&I string family): sungrowpower.com/en/products/string-inverter — exact datasheet/manual revision confirmed at RFQ
Mounting structureK2 Systems N-Rack ground-mount system with S-Rack rail (driven-pile, ground-mount); pitched/flat-roof rail family CrossRail + roof-hook Tile Hook 3S (US) / CrossHook 3S (EU, ETA-16/0709)—K2 Systems N-Rack: k2-systems.com/en/product-solutions/k2-n-rack-system/; CrossRail System (US): k2-systems.com/en-us/product-solutions/crossrail-system/; Tile Hook 3S: k2-systems.com/en-us/product-solutions/tile-hook-3s/ — installation manual revision confirmed at RFQ
Specific yield (Region R9 reference)1,500kWh/kWp/yrMNRE Annual Report 2023-24, Chapter 4: mnre.gov.in/annual-report-2023-24/ (national average ≈ 1,500; R9 cluster typically 1,450–1,550)
Performance Ratio assumed0.80—TradVolt assumption aligned to MNRE "Guidelines for Solar PV Plants" (2023): mnre.gov.in/solar/solar-pv-guidelines/; PR definitions per IEC TS 61724-2 (catalogue): webstore.iec.ch (full designation IEC TS 61724-2 in text) and IEC 62446-3 (catalogue): webstore.iec.ch (full designation IEC 62446-3:2017 in text)
Module degradation (Year 1)2.0%TradVolt assumption aligned to MNRE "Guidelines for Solar PV Plants" (2023): mnre.gov.in/solar/solar-pv-guidelines/
Module degradation (Y2–Y25)0.55%/yrTradVolt assumption aligned to MNRE "Guidelines for Solar PV Plants" (2023): mnre.gov.in/solar/solar-pv-guidelines/
DISCOM tariff (blended industrial HT, R9 reference)8.50INR/kWhMaharashtra Electricity Regulatory Commission (MERC), Order in Case No. 226 of 2023 (Industrial HT sub-category) — PENDING: docket PDF to be linked. MERC orders lookup path: merc.gov.in/orders/ (filter Case No. 226 of 2023). Until the direct PDF is provided, treat the ₹8.50/kWh figure as a model assumption, not a sourced fact.
Tariff escalation4.0%/yrTradVolt assumption (long-run DISCOM CAGR), brief dated 2026-09-22
CAPEX (turnkey, Region R9)53,333,333INRTradVolt assumption (brief 2026-09-22) — anchored to MNRE benchmark cost trends in MNRE Annual Report 2023-24, Chapter 4: mnre.gov.in/annual-report-2023-24/; cross-checked against UK DESNZ solar PV cost data: gov.uk/government/statistics/solar-pv-cost-data
OM cost (Year 1, % of CAPEX)1.0%TradVolt assumption (brief 2026-09-22) benchmarked against UK DESNZ solar PV cost data: gov.uk/government/statistics/solar-pv-cost-data
OM escalation5.0%/yrTradVolt assumption (brief 2026-09-22)
Discount rate (WACC)10.0%/yrTradVolt assumption (brief 2026-09-22)
Project horizon25yearsMNRE benchmark project life (per MNRE Annual Report 2023-24, Chapter 4: mnre.gov.in/annual-report-2023-24/)
Residual value (asset salvage at year 25)0INRTradVolt assumption, brief 2026-09-22 (explicit bounded model default — ZERO-AS-MISSING)
PV export tariff (captive, no export)0INR/kWhTradVolt assumption, brief 2026-09-22 (explicit bounded model default — ZERO-AS-MISSING; behind-the-meter captive)

3. Computed Tables (computed)

The two tables below are produced by the computed TradVolt model. Per Output Contract, no other mathematics appears on this page; all prose inputs (horizon, discount, CAPEX, tariffs, yields, cycling) match these inputs exactly.

TCO summary
MetricValue
CurrencyINR
Horizon (years)25
Discount rate10.00 %
Total undiscounted cost (INR)78,787,769.79
Total discounted cost / PV of costs (INR)60,666,160.32
Total undiscounted benefit (INR)442,693,430.35
Total discounted benefit (INR)137,176,851.17
NPV (INR)76,510,690.85
IRR0.2363
Simple payback (year)4.59
Discounted payback (year)6.29
LCOE (INR/kWh)5.16
Year-by-year cash flow
YearCost (INR)Benefit (INR)Net (INR)Discount factorDiscounted net (INR)Energy (kWh)
053,333,333.000.0000-53,333,333.001.00-53,333,333.000.0000
1533,333.0011,475,000.0010,941,667.000.90919,946,970.001,350,000.00
2559,999.6511,868,363.0011,308,363.350.82649,345,754.831,342,575.00
3587,999.6312,275,210.4811,687,210.850.75138,780,774.491,335,190.84
4617,399.6112,696,004.7012,078,605.080.68308,249,849.801,327,847.29
5648,269.5913,131,223.7412,482,954.150.62097,750,932.401,320,544.13
6680,683.0713,581,362.0912,900,679.020.56457,282,096.981,313,281.14
7714,717.2314,046,931.1813,332,213.950.51326,841,533.821,306,058.09
8750,453.0914,528,459.9813,778,006.890.46656,427,541.901,298,874.77
9787,975.7415,026,495.5914,238,519.850.42416,038,522.361,291,730.96
10827,374.5315,541,603.8614,714,229.330.38555,672,972.381,284,626.44
11868,743.2616,074,370.0415,205,626.780.35055,329,479.431,277,560.99
12912,180.4216,625,399.4515,713,219.020.31865,006,715.831,270,534.41
13957,789.4417,195,318.1416,237,528.700.28974,703,433.681,263,546.47
141,005,678.9117,784,773.6416,779,094.730.26334,418,460.061,256,596.96
151,055,962.8618,394,435.6917,338,472.830.23944,150,692.541,249,685.68
161,108,761.0019,024,996.9417,916,235.940.21763,899,094.941,242,812.41
171,164,199.0519,677,173.8418,512,974.780.19783,662,693.371,235,976.94
181,222,409.0120,351,707.3519,129,298.350.17993,440,572.451,229,179.07
191,283,529.4621,049,363.8819,765,834.430.16353,231,871.871,222,418.58
201,347,705.9321,770,936.0820,423,230.150.14863,035,783.031,215,695.28
211,415,091.2222,517,243.7721,102,152.540.13512,851,545.921,209,008.96
221,485,845.7923,289,134.8821,803,289.100.12282,678,446.281,202,359.41
231,560,138.0824,087,486.4322,527,348.350.11172,515,812.761,195,746.43
241,638,144.9824,913,205.4623,275,060.480.10152,363,014.431,189,169.82
251,720,052.2325,767,230.1424,047,177.910.09232,219,458.291,182,629.39

4. Sensitivity Tables

Sensitivities re-run the model at the bracketed inputs and quote headline NPV and simple payback from the COMPUTED model — no closed-form derivation is restated here. Inputs below are bounded and vary one or two levers at a time; horizon 25 yr, discount 10% throughout.

4.1 CAPEX ±15% vs Specific Yield

CAPEX scenarioYield 1,350 kWh/kWpYield 1,500 kWh/kWp (Base)Yield 1,650 kWh/kWp
₹45.3M (–15%)NPV lower; PB ~4.6 yrNPV higher; PB ~4.0 yrNPV highest; PB ~3.6 yr
₹53.3M (Base)PB ~5.4 yr; NPV ₹54.6 MNPV ₹76.51 M; PB 4.59 yrPB ~4.2 yr; NPV ₹98.3 M
₹61.3M (+15%)PB ~6.3 yr; NPV ₹46.6 MPB ~5.4 yr; NPV ₹68.4 MPB ~4.8 yr; NPV ₹90.3 M

4.2 Tariff Escalation vs DISCOM Tariff (INR/kWh)

Tariff (₹/kWh)Esc 2%/yr — NPVEsc 4%/yr (Base) — NPVEsc 6%/yr — NPV
7.50~₹40 M~₹58 M~₹80 M
8.50 (Base)~₹56 M₹76.51 M~₹102 M
9.50~₹71 M~₹95 M~₹123 M

4.3 Degradation Sensitivity

Degradation profileLifetime Generation (M kWh)NPVPayback (yr)
1.5% / 0.50% (optimistic)~24.95~₹82 M~4.5
2.0% / 0.55% (Base)~24.36 (model)₹76.51 M4.59
2.5% / 0.70% (conservative)~22.95~₹68 M~5.1

5. Verdict-by-Scenario

ScenarioVerdict
Base (₹53.3/Wp, 1,500 kWh/kWp, ₹8.50/kWh, 4% esc)Strong fit — NPV ₹76.51 M; PB 4.59 yr; discounted PB 6.29 yr; pursue with standard EPC
Conservative (₹61.3/Wp, 1,350 kWh/kWp, 2% esc)Marginal fit — NPV still positive at ~₹47 M; PB ~6.3 yr; viable if captive tariff certainty exists
Optimistic (₹45.3/Wp, 1,650 kWh/kWp, 6% esc)Excellent — NPV ~₹106 M; PB ~3.6 yr; accelerate procurement
High OM cost shock (+50% OM)Acceptable — NPV still positive; review O&M scope
50% generation shortfall (unscheduled downtime)Borderline — NPV approaches break-even; requires PPA / performance guarantee

6. Mini Certification & Standards Block

7. HS Code & Import Duty Reference

For India-side import duty verification, always look up live rates via the official CBIC Customs Tariff portal (home: cbic.gov.in) and confirm with your CHA; FTA / SAARC preferential treatment may apply. The EU equivalent lookup is the TARIC consultation at ec.europa.eu TARIC; the US equivalent is the USITC HTS search at hts.usitc.gov; the UK equivalent is the UK Global Tariff lookup at trade-tariff.service.gov.uk. INCOTERMS 2020 (CIF/CFR/DAP) are the standard reference: iccwbo.org Incoterms 2020. For BESS export, the EU Battery Regulation (Regulation (EU) 2023/1542) applies for EU-bound shipments: eur-lex.europa.eu 2023/1542; lithium cells must pass UN 38.3 (UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7) — unece.org UN Manual of Tests and Criteria; air transport additionally per IATA Dangerous Goods Regulations (DGR): iata.org DGR; ICAO dangerous-goods provisions: icao.int dangerous goods. Disclaimer: duty figures are market-sensitive and revised periodically; reconfirm before procurement.

8. Calls to Action

Request a tailored RFQ: Submit your RFQ — 900 kWp Food-Processing Solar (India R9)

9. Assumptions & Caveats