TradVolt › Use-Cases › Greenhouse + 1 MWp Solar PV — South Africa

Greenhouse + 1 MWp Solar PV: Use-Case & Total Cost of Ownership (South Africa)

Verdict (first 100 words): A 1 MWp grid-tied solar PV array, modelled as LONGi Hi-MO 6 Explorer LR5-54HTH modules with a Sungrow SG125HV string inverter, co-located with a South African greenhouse, returns NPV = ZAR 17,969,658 at a 12.00% discount rate over a 25-year horizon, with IRR = 28.97%, simple payback = 3.97 years, discounted payback = 5.48 years, and LCOE = ZAR 1.01/kWh. Equipment: LONGi Hi-MO 6 LR5-54HTH (LR5-54HTH 515–545 W class HPBC cells) + Sungrow SG125HV three-phase string inverter. Location: South Africa. Horizon: 25 years. Evidence date: 2025-01-15. Limitation: every financial figure below is taken verbatim from the COMPUTED TABLES (computed); equipment performance parameters are model assumptions pending RFQ confirmation.

Decision table — base case
MetricValue
Equipment (DC)LONGi Hi-MO 6 Explorer LR5-54HTH (HPBC cell, mono-Si; product page longi.com/.../hi-mo-x6)
Inverter (AC)Sungrow SG125HV three-phase string inverter (C&I string range, product page sungrowpower.com/.../string-inverter)
LocationSouth Africa (Highveld / Limpopo / Western Cape)
Horizon25 years
Discount rate (WACC)12.00%
NPV (ZAR)17,969,658
IRR28.97%
Simple payback (years)3.97
Discounted payback (years)5.48
LCOE (ZAR/kWh)1.01
Evidence date2025-01-15
LimitationNo certificate issued for the modelled project; model assumes compliant Tier-1 components

1. Use-Case Description

The scenario models a 1 MWp DC ground-mount PV system co-located with a commercial greenhouse in South Africa. The DC side is built from LONGi Hi-MO 6 Explorer LR5-54HTH mono-Si modules (HPBC cell technology, HPBC+ efficiency up to 25.8% per the Hi-MO X6 product page: https://www.longi.com/en/products/modules-series/hi-mo-x6/; module wattage and warranty revision confirmed at RFQ). The AC side uses a Sungrow SG125HV three-phase string inverter from the Sungrow C&I string-inverter range (https://www.sungrowpower.com/en/products/string-inverter; the SG125HV is the 125 kW utility/C&I model listed on this page; exact datasheet revision confirmed at RFQ). The greenhouse load is daytime-aligned (drip fertigation pumps, horizontal airflow fans, LED supplemental lighting, pad-and-fan evaporative cooling, screen motors), giving a high self-consumption ratio.

2. Inputs Table (Cited) & Model Assumptions

Financial figures in the TCO tables below are taken verbatim from the COMPUTED TABLES supplied by TradVolt's scenario model. The numeric inputs driving them are stated here; rows that are not directly published as a single document are flagged as model assumption.

InputValueUnitSource / Citation (specific document URL)
PV system size1,000kWp DCSystem definition (TradVolt use-case brief)
Module familyLONGi Hi-MO 6 Explorer LR5-54HTH (HPBC cell)mono-Sihttps://www.longi.com/en/products/modules-series/hi-mo-x6/ (HPBC cell, Explorer variant; HPBC+ efficiency up to 25.8%; exact wattage class and warranty revision confirmed at RFQ)
Inverter modelSungrow SG125HV (three-phase string)125 kW C&Ihttps://www.sungrowpower.com/en/products/string-inverter (SG125HV listed on this C&I string-inverter page; exact datasheet revision confirmed at RFQ)
Specific yield (Highveld baseline)1,650kWh/kWp/yrEC JRC PVGIS about/method page and SAUER CVYield methodology: https://joint-research-centre.ec.europa.eu/photovoltaic-geographical-information-system-pvgis_en; ZA Highveld zone treated as bounded model assumption
Performance ratio0.80ratioModel assumption (bounded 0.78–0.82 for well-maintained Tier-1 utility-scale ZA PV); methodology reference: IEC 61724-1:2017 PV system performance, Part 1 (TC 82). IEC Webstore catalogue: https://webstore.iec.ch/ — cite designation «IEC 61724-1:2017» in any RFQ response
Module degradation0.50%per year (linear)Model assumption (bounded by LONGi Hi-MO 6 product page; linear performance warranty text confirmed at RFQ)
CapEx — modules4,500,000ZARModel assumption (no allow-listed public ZA large C&I module-price document exists; confirmed at RFQ)
CapEx — inverterincluded in modules lineZARModel assumption
CapEx — BoS + mounting2,200,000ZARModel assumption (K2 Systems N-Rack ground-mount + S-Rack rail family referenced: https://k2-systems.com/en/product-solutions/k2-n-rack-system/; exact rail/kit model + manual revision confirmed at RFQ)
CapEx — EPC + commissioning1,800,000ZARModel assumption (EPC scope per NRS 097-2-1:2017, ed. 2; SABS Webstore catalogue page; exact standard number cited in text)
CapEx — grid-tie + protection900,000ZARModel assumption (NRS 097-2-1:2017 referenced; the technical basis is cited through the SABS Webstore catalogue — confirm at RFQ)
Total CapEx9,400,000ZARSum of above (matches Year 0 outflow)
Fixed O&M (year 1)200,000ZAR/yrModel assumption (year-1 figure is the model input; O&M escalates at 8.0%/yr in the COMPUTED TABLES)
O&M escalation8.0%per yearModel assumption (bounded by long-run ZA CPI)
Inverter replacement (year 12)750,000ZARModel assumption (Sungrow SG125HV replacement; confirmed at RFQ)
Insurance (year 1)included in fixed O&MZAR/yrModel assumption (insurance is bundled with fixed O&M in the COMPUTED TABLES)
Eskom tariff (year 1, base)1.50ZAR/kWhhttps://www.nersa.org.za/electricity/pricing-and-tariffs/ (NERSA Eskom approved-tariff schedule; exact PDF confirmed at RFQ)
Eskom tariff escalation7.0%per yearModel assumption (bounded by NERSA MYPD multi-year approved average); IEA cross-check on ZA electricity market: https://www.iea.org/
Discount rate (WACC)12.00%per yearModel assumption (typical ZA C&I project finance rate)
Project horizon25yearsModule performance warranty term (LONGi Hi-MO 6 product page)
Greenhouse annual load (self-consumed)500,000kWh/yrModel assumption (3 ha greenhouse benchmark)
Self-consumption ratio0.95ratioModel assumption (daytime-aligned load)
Decommissioning reserve (year 25)350,000ZARModel assumption (end-of-life decommissioning)
Residual value (asset end-of-horizon)bounded model defaultZARModel assumption (bounded default): end-of-horizon residual value set to ZAR 0 (asset is fully depreciated over the 25-year horizon in the COMPUTED TABLES; no residual line is added to the benefit stream)
Export tariff (residual kWh)bounded model defaultZAR/kWhModel assumption (bounded default): surplus kWh beyond the self-consumed load are valued at the Eskom Megaflex avoided-cost rate referenced on the NERSA pricing page; the COMPUTED TABLES treat export revenue as part of the benefit stream that escalates with the Eskom tariff, so the exact export rate is implicit in the benefit column

3. TCO Summary (COMPUTED — computed)

TCO summary
MetricValue
CurrencyZAR
Horizon (years)25
Discount rate12.00 %
Total undiscounted cost (ZAR)25,121,187.99
Total discounted cost / PV of costs (ZAR)12,598,844.70
Total undiscounted benefit (ZAR)138,014,079.52
Total discounted benefit (ZAR)30,568,502.56
NPV (ZAR)17,969,657.87
IRR0.2897
Simple payback (year)3.97
Discounted payback (year)5.48
LCOE (ZAR/kWh)1.01

4. Year-by-Year Cash Flow (COMPUTED — computed)

Year-by-year cash flow
YearCost (ZAR)Benefit (ZAR)Net (ZAR)Discount factorDiscounted net (ZAR)Energy (kWh)
09,400,000.000.0000-9,400,000.001.00-9,400,000.000.0000
1200,000.002,355,375.002,155,375.000.89291,924,441.961,650,000.00
2216,000.002,507,649.992,291,649.990.79721,826,889.341,641,750.00
3233,280.002,669,769.572,436,489.570.71181,734,245.151,633,541.25
4251,942.402,842,370.172,590,427.770.63551,646,263.681,625,373.54
5272,097.793,026,129.402,754,031.610.56741,562,711.501,617,246.68
6293,865.623,221,768.672,927,903.050.50661,483,366.801,609,160.44
7317,374.863,430,056.013,112,681.140.45231,408,018.871,601,114.64
8342,764.853,651,809.133,309,044.280.40391,336,467.481,593,109.07
9370,186.043,887,898.593,517,712.550.36061,268,522.411,585,143.52
10399,800.934,139,251.233,739,450.310.32201,204,002.921,577,217.80
11431,785.004,406,853.833,975,068.830.28751,142,737.301,569,331.72
121,216,327.804,691,756.933,475,429.130.2567892,056.091,561,485.06
13503,634.024,995,079.014,491,444.990.22921,029,323.271,553,677.63
14543,924.755,318,010.874,774,086.130.2046976,872.611,545,909.24
15587,438.725,661,820.275,074,381.550.1827927,070.541,538,179.70
16634,433.826,027,856.955,393,423.130.1631879,784.141,530,488.80
17685,188.536,417,557.915,732,369.380.1456834,887.161,522,836.35
18740,003.616,832,453.026,092,449.410.1300792,259.621,515,222.17
19799,203.907,274,171.116,474,967.210.1161751,787.571,507,646.06
20863,140.217,744,446.286,881,306.060.1037713,362.741,500,107.83
21932,191.438,245,124.737,312,933.300.0926676,882.271,492,607.29
221,006,766.748,778,172.047,771,405.300.0826642,248.441,485,144.26
231,087,308.089,345,680.868,258,372.780.0738609,368.451,477,718.53
241,174,292.739,949,879.138,775,586.400.0659578,154.091,470,329.94
251,618,236.1510,593,138.828,974,902.670.0588527,933.451,462,978.29

Notes on the COMPUTED TABLES: Year 0 is the CapEx outflow. The Year 12 cost line of ZAR 1,216,327.80 combines the Sungrow SG125HV inverter replacement (ZAR 750,000) with that year's escalated fixed O&M. The Year 25 cost line includes the ZAR 350,000 decommissioning reserve on top of the final-year O&M. All discount factors in the cash-flow table are at the 12.00% base WACC.

5. Sensitivity Table

Each row holds the time basis (25-year horizon, year-by-year cash-flow basis) constant and varies a single input. CapEx- and yield-adjusted rows reuse the same O&M, inverter-replacement, and decommissioning lines as the base case; only CapEx and/or annual generation scale linearly. The LCOE, NPV, IRR, payback, and discount factor figures quoted below are illustrative scenario ratings for the decision table; the only computed TCO figures are those in the COMPUTED TABLES above.

ScenarioCapEx (ZAR)Yield (kWh/kWp/yr)WACCLCOE (ZAR/kWh)Discounted payback (yrs)Verdict
Base case9,400,0001,65012.00%1.015.48GO — viable; NPV = ZAR 17.97M, IRR = 28.97%
Low tariff escalation (5.0%)9,400,0001,65012.00%1.01 (cost unchanged)lengthensCAUTION — cost LCOE unchanged; benefit stream compresses
High tariff escalation (12.0%)9,400,0001,65012.00%1.01 (cost unchanged)shortensGO — strongly favourable upside
Low specific yield (coastal cloud belt)9,400,0001,40012.00%rises vs. baselengthens vs. baseCAUTION — thin margin; verify on-site yield via PVGIS methodology: https://joint-research-centre.ec.europa.eu/photovoltaic-geographical-information-system-pvgis_en
CapEx +20%11,280,0001,65012.00%rises vs. baselengthens vs. baseCAUTION — borderline vs. tariff; secure fixed-price EPC
CapEx −10%8,460,0001,65012.00%falls vs. baseshortens vs. baseGO — highly competitive
Low yield + high CapEx (worst)11,280,0001,40012.00%rises materiallylengthens materiallyNO-GO without subsidy
High yield + low CapEx (best)8,460,0001,80012.00%falls materiallyshortens materiallyGO — excellent
WACC 16% (stressed)9,400,0001,65016.00%rises vs. baselengthens vs. baseCAUTION — negotiate blended green finance

6. Verdict by Scenario

7. Standards & Certification Block

Disclaimer: no certificate has been issued for the modelled project. The model assumes compliant Tier-1 components per the standards listed below; certificate numbers and issuing bodies are confirmed at RFQ award.

IEC 61215-1:2021 / IEC 61215-1-1:2021 / IEC 61215-2:2021 (ed. 2)Crystalline-silicon PV module design qualification — LONGi Hi-MO 6 Explorer LR5-54HTH assumed compliant. Reference (IEC 61215-1-1:2021 c-Si special requirements, TC 82): https://webstore.iec.ch/en/publication/61346; full family IEC 61215-1:2021 / IEC 61215-1-1:2021 / IEC 61215-2:2021 cited by designation. IEC Webstore catalogue: https://webstore.iec.ch/
IEC 61730-1:2016 / IEC 61730-2:2016 (ed. 2)PV module safety qualification — LONGi Hi-MO 6 Explorer LR5-54HTH assumed compliant. Reference: IEC Webstore catalogue https://webstore.iec.ch/ (cite designation IEC 61730-1:2016 / IEC 61730-2:2016 in any RFQ response); UL counterpart UL 61730-1: https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1
IEC 62109-1:2010 (ed. 1)Safety of power converters for use in PV power systems, Part 1: General requirements (TC 82). Reference: https://webstore.iec.ch/en/publication/6470. Sungrow SG125HV assumed compliant.
IEC 62109-2:2011 (ed. 1)Safety of power converters for use in PV power systems, Part 2: Particular requirements for inverters; used jointly with IEC 62109-1. Reference: https://webstore.iec.ch/en/publication/6471. Sungrow SG125HV assumed compliant.
NRS 097-2-1:2017 (ed. 2)ZA grid-tie compliance for small/medium generators — assumed compliant; certificate issued at grid-tie commissioning.
SANS 10142-1:2017 (ed. 3.1)Wiring of premises — assumed compliant; CoC issued at commissioning.
SAPVIA PV GreenCardInstaller certification programme — installer-level, not project-level; certificate issued to the EPC.

8. HS Code Block — Duty Lookup

Duty rates below are lookup placeholders only. The computed rates are obtained by querying the official tariff pages cited for each row.

HS code (2022)DescriptionDuty rateLookup
8541.43Photovoltaic cells assembled in modulesLookupSARS Customs & Excise Tariff landing page: https://www.sars.gov.za/customs-and-excise/tariff/ — Schedule 1, Part 1, Chapter 85
8504.40Static converters (inverters)LookupSARS Customs & Excise Tariff landing page: https://www.sars.gov.za/customs-and-excise/tariff/ — Schedule 1, Part 1, Chapter 85
7610.90Aluminium mounting structuresLookupSARS Customs & Excise Tariff landing page: https://www.sars.gov.za/customs-and-excise/tariff/ — Schedule 1, Part 1, Chapter 76
8544.49DC cables, other conductorsLookupSARS Customs & Excise Tariff landing page: https://www.sars.gov.za/customs-and-excise/tariff/ — Schedule 1, Part 1, Chapter 85

Duty rate disclaimer: TradVolt does not assert any specific rate as fact. SARS publishes the official South African Customs and Excise Tariff at https://www.sars.gov.za/customs-and-excise/tariff/; consult a licensed clearing agent or SARS customs ruling before any import decision. Possible ITAC import-control measures or Section 12B Income Tax Act renewable-energy allowance apply but require independent verification against the ITAC import-control page: https://www.itac.org.za/import-control/.

9. Cross-Border Reference (Incidental)

If the equipment is sourced via a non-ZA port of entry, the EU TARIC consultation tool (https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en), USITC HTS (https://hts.usitc.gov/), UK Global Tariff (https://www.trade-tariff.service.gov.uk/), and ICC Incoterms 2020 (https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/) are the cited cross-border lookups. Wood packaging must comply with IPPC ISPM 15 (https://www.ippc.int/en/core-activities/standards-setting/ispms/). Lithium-bearing components fall under UN Manual of Tests and Criteria, UN 38.3 (ST/SG/AC.10/11/Rev.7) — reference: https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria (cite designation «ST/SG/AC.10/11/Rev.7» verbatim).