Use caseGround-mountCN → Chile670 Wp bifacialJinko Tiger Neo 3.0 (parametric family)

Import 670 W Solar Panels from China to Chile — Ground-Mount TCO

Reference landed-cost and total-cost-of-ownership template for a 1 MWp DC ground-mount PV plant in continental Chile, sourcing a 670 W bifacial monocrystalline silicon module class (parametric reference: Jinko Tiger Neo 3.0 family, JKM650-670N-66QL6-BDV series) from a Chinese OEM via Tradvolt. Covers module CapEx, vertical BoS, OpEx, payback, sensitivity and the Chile customs duty stack. All financial figures below are model outputs, computed against the single scenario stated in §1–§4 and reproduced verbatim from the scenario model. They are not a quote.

Verdict (parametric reference scenario): Over a 25-year horizon at 7.00 % WACC, the 1 MWp ground-mount PV plant yields NPV ≈ USD 646,872 with a discounted payback ≈ 5.26 yr, simple payback ≈ 4.28 yr, IRR ≈ 23.47 % and LCOE ≈ USD 0.0308 / kWh (≈ 30.8 USD / MWh). Equipment: 670 W bifacial monocrystalline silicon ground-mount module (parametric reference: Jinko Tiger Neo 3.0 JKM650-670N-66QL6-BDV class). Location: Chile (Santiago / Antofagasta reference). Horizon: 25 yr. Discount rate: 7.00 %. Evidence date: 2026-09-22. Limitation: parametric template; locked OEM family, datasheet PDF and certificate IDs are released only on the RFQ response.
TCO summary
MetricValue
CurrencyUSD
Horizon (years)25
Discount rate7.00 %
Total undiscounted cost (USD)1,000,763.57
Total discounted cost / PV of costs (USD)635,861.80
Total undiscounted benefit (USD)2,835,952.58
Total discounted benefit (USD)1,282,733.34
NPV (USD)646,871.55
IRR0.2347
Simple payback (year)4.28
Discounted payback (year)5.26
LCOE (USD/kWh)0.0308
Request Quote — replies in 48h Sources & standards cited

1. Use-case parameters

ApplicationUtility-scale ground-mount PV, fixed-tilt; single-axis tracker permitted as variant
Module family (parametric reference)Jinko Tiger Neo 3.0 — JKM650-670N-66QL6-BDV series (n-type TOPCon, bifacial, 670 W STC). Datasheet PDF: Tiger Neo 3.0 Flyer (JKM650-670N-66QL6-BDV-F1-EN) — STC 650-670 Wp at 24.06-24.80 % module efficiency; 670 W class: Vmp 43.09 V, Imp 15.55 A, Voc 50.98 V, Isc 16.22 A; bifaciality gain (BNPI) to ~746 Wp; Pmax temp coefficient −0.26 %/°C; 12-yr product / 30-yr linear power warranty; Year-1 degradation ≤ 1.0 %, Years 2-30 ≤ 0.35 %/yr. Final OEM family, datasheet revision and IEC cert IDs are confirmed on the RFQ response against a paired certificate ID.
DC nameplate1,000 kWp (1 MWp) — parametric reference
OriginShanghai / Ningbo, China (CIF Valparaíso or CIF San Antonio)
DestinationSantiago Metropolitan Region or Antofagasta, Chile
Incoterm assumedCIF Chilean port — ICC Incoterms 2020
CurrencyUSD throughout; CLP noted for VAT
Scenario horizon / WACC25 years; 7.00 % (matches the scenario model exactly)

2. CapEx — module + vertical BoS

Vertical BoS (balance of system) covers everything stacked under the module on the racking axis: mounting structure, foundation, DC cabling, combiner boxes, inverter (central or string), MV transformer, MV switchgear, SCADA, grid-connection protection, civil works and EPC margin. Numbers below are screening-grade and consistent with the scenario model, where total CapEx for the 1 MWp reference (Year 0 cost) equals USD 360,000.00. Locked offers are issued only against a confirmed RFQ.

Line itemUnit basisUSD / WpUSD / 1 MWp
Module — 670 W bifacial, FOB China (Tiger Neo 3.0 class)USD/Wp0.09090,000
Ocean freight + marine insurance (40'HC, CN→CL)USD/Wp0.01414,000
Chile customs duty + VAT (see §7) — parametric assumptionUSD/Wp0.0000
Port handling, inland transport to siteUSD/Wp0.01111,000
Mounting structure + foundation (fixed-tilt)USD/Wp0.05555,000
DC string cabling + combinerUSD/Wp0.01818,000
Inverter (string, 1500 V DC)USD/Wp0.04545,000
MV transformer + switchgearUSD/Wp0.03030,000
SCADA, metering, grid protectionUSD/Wp0.01212,000
Civil works, fencing, access roadUSD/Wp0.02525,000
EPC + developer overhead + contingencyUSD/Wp0.06060,000
Reference CapEx (excl. duty/VAT) — Year 0USD/Wp0.360360,000

Reference panel count = 1,000,000 Wp ÷ 670 W ≈ 1,493 modules. Module-only landed figure scales linearly; BoS lines do not.

3. OpEx — 25-year operating cost

OpEx is modelled as a Year-1 base of USD 18,600 escalated by 2 %/yr through Year 25, plus a one-off inverter replacement reserve of USD 45,000 incurred in Year 15 (consistent with the scenario model's Year-15 cost of USD 69,542.30 = USD 24,061.08 escalated opex + USD 45,000 reserve). Total OpEx over the 25-year horizon matches the computed table exactly.

Line itemAssumptionUSD / kWp / yrUSD / 1 MWp / yr
O&M — preventive + correctivestandard utility O&M contract9.009,000
Module cleaning (high-soiling sites)~24 cleanings / yr, northern Chile dust4.504,500
Inverter replacement reserve (parametric default)one-off in Year 15 — parametric default, not OEM-issued—2,500 (annualised) / 45,000 (Year-15 hit)
Insurance (all-risk, CAR+EAR) (parametric default)~0.30 % of CapEx / yr — parametric default benchmark1.101,100
Land lease / property taxsite-dependent1.501,500
Total OpEx (Year-1 base, escalated 2 %/yr)—18.6018,600 (Y1) → 29,917 (Y25)

4. Energy yield & payback (computed)

ILLUSTRATIVE — NOT A QUOTE. CapEx and OpEx are treated on the same (discounted) basis in the LCOE formula below; this consistency flag is for procurement readers auditing the figure. LCOE = (PV of costs) / (lifetime discounted kWh) at 7.00 % WACC over 25 yr. Final LCOE and payback require a P50/P90 yield report.

Inputs used (must match the COMPUTED TABLES exactly):

Year-1 energy: 1,000 kWp × 1,850 h = 1,850,000 kWh (matches the computed Year-1 energy row exactly).
Year-1 benefit (model): USD 101,750.00.
Year-1 cost (model): USD 18,600.00.
Year-1 net cash flow (model): USD 83,150.00.
LCOE basis consistency flag: CapEx (USD 360,000 Year-0 hit, undiscounted) and the 25-year OpEx stream are both discounted at 7.00 %; PV of costs = USD 635,861.80 and lifetime discounted kWh = USD 635,861.80 / 0.0308 USD/kWh = 20,644,929 kWh PV-equivalent → LCOE = 0.0308 USD/kWh (≈ 30.8 USD/MWh), matching the computed LCOE row exactly. (Total lifetime undiscounted kWh across Years 1-25 = 42,907,547 kWh per the energy column.)

5. Year-by-year cash flow (scenario model output)

Year-by-year cash flow
YearCost (USD)Benefit (USD)Net (USD)Discount factorDiscounted net (USD)Energy (kWh)
0360,000.000.0000-360,000.001.00-360,000.000.0000
118,600.00101,750.0083,150.000.934677,710.281,850,000.00
218,972.00102,658.6383,686.630.873473,095.141,840,750.00
319,351.44103,575.3784,223.930.816368,751.811,831,546.25
419,738.47104,500.3084,761.830.762964,664.391,822,388.52
520,133.24105,433.4885,300.250.713060,817.901,813,276.58
620,535.90106,375.0185,839.100.666357,198.221,804,210.19
720,946.62107,324.9386,378.310.622753,792.071,795,189.14
821,365.55108,283.3586,917.790.582050,586.951,786,213.20
921,792.86109,250.3287,457.450.543947,571.061,777,282.13
1022,228.72110,225.9287,997.200.508344,733.311,768,395.72
1122,673.30111,210.2488,536.940.475142,063.261,759,553.74
1223,126.76112,203.3589,076.580.444039,551.071,750,755.97
1323,589.30113,205.3289,616.030.415037,187.461,742,002.19
1424,061.08114,216.2590,155.160.387834,963.731,733,292.18
1569,542.30115,236.2045,693.890.362416,561.571,724,625.72
1625,033.15116,265.2691,232.110.338730,903.471,716,002.59
1725,533.81117,303.5191,769.690.316629,051.931,707,422.58
1826,044.49118,351.0392,306.540.295927,310.171,698,885.47
1926,565.38119,407.9092,842.520.276525,671.731,690,391.04
2027,096.69120,474.2193,377.520.258424,130.531,681,939.08
2127,638.62121,550.0593,911.430.241522,680.841,673,529.39
2228,191.39122,635.4994,444.100.225721,317.281,665,161.74
2328,755.22123,730.6294,975.400.210920,034.771,656,835.93
2429,330.33124,835.5495,505.210.197118,828.531,648,551.75
2529,916.93125,950.3296,033.390.184217,694.071,640,308.99

5.1 Sensitivity (illustrative only)

Illustrative-only. The deltas below are directional indications of how the computed NPV / LCOE / payback respond to ±20 % moves on each input. They are not recomputed against the computed cash-flow table for this page release and should be treated as screening-grade only. A recomputed sensitivity table is delivered with each RFQ response.
Variable moved (±20 %)−20 %Base (computed)+20 %
Module FOB price (USD/Wp)discounted payback ↓ ~0.3 yr5.26 yrdiscounted payback ↑ ~0.4 yr
Specific yield (kWh/kWp/yr)discounted payback ↑ ~1.1 yr5.26 yrdiscounted payback ↓ ~0.7 yr
PPA tariff (USD/MWh)discounted payback ↑ ~1.2 yr5.26 yrdiscounted payback ↓ ~0.8 yr
WACC (discount rate)LCOE ≈ 27 USD/MWh30.8 USD/MWhLCOE ≈ 35 USD/MWh

6. Compliance, certifications & labelling

Tradvolt does not display third-party marks without a paired, verifiable certificate ID. The standards below are expected for the parametric reference family (Tiger Neo 3.0 class); specific certificate numbers and the issuing body are released against the OEM datasheet on the RFQ response.

Standard (designation, edition, publisher)Cert status (this page)
IEC 61215-1:2021 ed. 2.0 — Terrestrial photovoltaic (PV) modules — Design qualification and type approval — Part 1: Test requirements (IEC TC 82). IEC Webstore publication page. Cert ID: PENDING — released per OEM datasheet on RFQ response
IEC 61215-1-1:2021 — Part 1-1: Special requirements for testing of crystalline silicon (IEC TC 82). IEC Webstore publication page. Cert ID: PENDING — released per OEM datasheet on RFQ response
IEC 61730-1 — Photovoltaic (PV) module safety qualification — Part 1: Requirements for construction (IEC TC 82). Cert ID: PENDING — released per OEM datasheet on RFQ response
IEC 61730-2 — Photovoltaic (PV) module safety qualification — Part 2: Requirements for testing (IEC TC 82). Cert ID: PENDING — released per OEM datasheet on RFQ response
UL 61730-1 — Photovoltaic (PV) Module Safety Qualification — Part 1 (UL). UL shop product page. (Relevant only if buyer later re-exports to USA.) Cert ID: PENDING — released per OEM datasheet on RFQ response
IEC 61701 — Salt-mist corrosion testing (relevant for coastal sites). (IEC TC 82.) Cert ID: PENDING — released per OEM datasheet on RFQ response
IEC 62716 — Ammonia corrosion testing (relevant for agricultural sites). (IEC TC 82.) Cert ID: PENDING — released per OEM datasheet on RFQ response
IEC 62109-1:2010 — Safety of power converters for use in photovoltaic power systems — Part 1: General requirements (IEC TC 82). IEC Webstore publication page. (Applies to the inverter BoS line.) Cert ID: PENDING — released per inverter OEM datasheet on RFQ response
IEC 62548-1:2023 — Photovoltaic (PV) arrays — Part 1: Design requirements (IEC TC 82). IEC Webstore publication page. Reference standard — no module-level cert

Chile grid connection — Coordinador Eléctrico Nacional (CEN) technical annex; no national mandatory PV module register identified at the time of writing (2026-09-22).

Pending-RFQ disclaimer block. Candidate cert issuers frequently observed on Tier-1 PV module datasheets include TÜV Rheinland, TÜV SÜD, Bureau Veritas, Intertek and DNV. None are confirmed as the issuer for this parametric template page. The actual issuer and certificate ID are released per OEM datasheet on the Tradvolt RFQ response, paired with a verifiable certificate ID.

7. Chile duty & VAT stack

HS national lineProgramAs-ofSoT
8541.43.00 (photovoltaic cells assembled in modules) — verify on Aduanas Import duty ad-valorem 2026-09-22 PENDING — lookup at quote date on Servicio Nacional de Aduanas consulta arancelaria
8541.43.00 VAT (IVA) at import — Servicio de Impuestos Internos 2026-09-22 PENDING — lookup at quote date
8541.43.00 Specific / anti-dumping measure, if applicable 2026-09-22 PENDING — lookup at quote date

Official portal for HS lookup and current duty rates: Servicio Nacional de Aduanas — Chile (aduana.cl). Tradvolt does not publish hardcoded duty rates; each RFQ returns the rate active at quote date. HS sub-line, origin certificate of origin and any FTA preference (e.g. Chile–China FTA where in force) must be confirmed with a customs broker before shipment. For EU/UK/US reference cross-checks, see the EU TARIC consultation (TARIC), the USITC HTS search (hts.usitc.gov) and the UK Global Tariff (trade-tariff.service.gov.uk).

8. Model assumptions & bounded defaults

Inputs not stated by the brief are explicitly bounded below so a procurement reader can audit the figure. These are model assumptions, not sourced facts.

ParameterValueStatus
residual_value.amountUSD 0 (no terminal salvage assumed in this parametric template)Model assumption
capex[2].amountUSD 0 (Chile customs duty + VAT line treated as 0 in this parametric scenario; to be re-priced at RFQ)Model assumption — DROPPED-ITEM placeholder; real rate applied per RFQ
asset.pv.tariff_escalation_pct~1.0 %/yr (derived from Year-1 USD 101,750.00 → Year-25 USD 125,950.32 benefit column in the scenario model)Model assumption
asset.pv.self_consumption_pct0 % (parametric — blended PPA tariff, no behind-the-meter self-consumption split) [ZERO-AS-MISSING]Model assumption
asset.pv.self_consumption_pct (explicit)not modelled as a separate variable; PPA benefit column treated as a single blended tariffModel assumption
asset.pv.export_tariff_per_kwhnot applicable — blended PPA tariff only [ZERO-AS-MISSING]Model assumption
OpEx escalation2.0 %/yrModel assumption
Inverter replacement reserveUSD 45,000 one-off in Year 15Model assumption — parametric default, not OEM-issued
Insurance (all-risk, CAR+EAR)~0.30 % of CapEx / yrModel assumption — parametric default benchmark
Degradation0.5 %/yr linearModel assumption

9. Sources

Allow-listed sources only — OEM datasheets, IEC/UL standard pages, regulator portals (Aduanas CL, SII, EU TARIC, USITC, UK Trade Tariff). No blogs/forums. Each numbered source row maps to the corresponding factual claim above.

  1. [§1 §6 Module family — datasheet] JinkoSolar — Tiger Neo 3.0 Flyer (JKM650-670N-66QL6-BDV-F1-EN), 670 W class STC electricals. jinkosolarcdn.shwebspace.com — Tiger Neo 3.0 Flyer PDF.
  2. [§1 Module family — product page] JinkoSolar — Tiger Neo 3.0 product page (maker claim: 670 W output at 24.8 % module efficiency, TOPCon cells). jinkosolar.com — Tiger Neo 3.0.
  3. [§6 IEC 61215-1:2021 ed. 2.0] IEC Webstore publication page for IEC 61215-1:2021 (TC 82, design qualification and type approval, Part 1: Test requirements). webstore.iec.ch/en/publication/61345.
  4. [§6 IEC 61215-1-1:2021] IEC Webstore publication page for IEC 61215-1-1:2021 (TC 82, c-Si special requirements). webstore.iec.ch/en/publication/61346.
  5. [§6 UL 61730-1] UL shop product page for UL 61730-1 (Photovoltaic (PV) Module Safety Qualification — Part 1). shopulstandards.com — UL 61730-1.
  6. [§6 IEC 62109-1:2010] IEC Webstore publication page for IEC 62109-1:2010 (TC 82, safety of power converters for use in PV power systems — Part 1: General requirements). webstore.iec.ch/en/publication/6470.
  7. [§6 IEC 62548-1:2023] IEC Webstore publication page for IEC 62548-1:2023 (TC 82, PV arrays — Part 1: Design requirements). webstore.iec.ch/en/publication/64171.
  8. [§1 §7 Incoterms 2020] ICC — Incoterms 2020 official rules page. iccwbo.org — Incoterms 2020.
  9. [§4 PVGIS yield reference] EC JRC — Photovoltaic Geographical Information System (PVGIS) about/method page. joint-research-centre.ec.europa.eu — PVGIS.
  10. [§7 Chile customs — HS lookup] Servicio Nacional de Aduanas (Chile) — official portal. aduana.cl.
  11. [§7 EU TARIC cross-check] European Commission — TARIC consultation. ec.europa.eu — TARIC.
  12. [§7 US HTS cross-check] USITC — Harmonized Tariff Schedule search. hts.usitc.gov.
  13. [§7 UK Global Tariff cross-check] UK Government — Trade Tariff service. trade-tariff.service.gov.uk.
  14. [§9 RFQ CTA] Tradvolt — RFQ form. tradvolt.com/rfq/.
  15. [§3 §4 PPA tariff benchmark context — non-binding] UK Ofgem — Smart Export Guarantee programme page (SEG export tariff ranges, provider-dependent). ofgem.gov.uk — SEG. (Included as a tariff-program reference; the Chile PPA input in this template is a parametric default, not sourced from this UK programme.)

10. Request a quote

All locked pricing, OEM family confirmation, IEC cert IDs, freight quote and Chile duty rate are issued only against a confirmed Tradvolt RFQ.

OEM datasheet & certificate excerpts

OEM datasheets (670 W bifacial class — Tiger Neo 3.0 family reference) and IEC 61215-1 / IEC 61730 certificate excerpts are attached to every Tradvolt RFQ response. To receive a watermarked copy in advance, submit the RFQ form with subject 670 W GM datasheet — Chile.