Reference verdict: for one Jinko Solar Tiger Neo N-type 720W bifacial double-glass monocrystalline PV module (JKM-N-720), imported FOB-China to Thailand and ground-mounted on a utility-scale project, the scenario TCO model returns an NPV of USD 448.01, an IRR of 20.21%, a discounted payback of 6.66 years, a simple payback of 5.04 years, and an LCOE of USD 0.0276 / kWh over a 25-year horizon at an 8.00% nominal discount rate. Equipment: Jinko Tiger Neo N-type 720W (JKM-N-720 family). Location: Kingdom of Thailand, import via Laem Chabang. Horizon: 25 years. Evidence date: 2026-09-22. Limitation: figures are model-bound to the explicit bounded assumptions stated in §3 and §4; binding landed cost requires an OEM pro-forma invoice and a Thai Customs lookup at the time of shipment. ILLUSTRATIVE

Compact decision table
Decision fieldValue
Equipment (real, marketed)Jinko Solar Tiger Neo N-type 720 W bifacial double-glass PV module (family JKM-N-720)
Origin / DestinationFOB Shanghai/Ningbo/Shenzhen (CN) → CIF Laem Chabang (TH)
Horizon25 years
Discount rate (nominal)8.00 %
NPVUSD 448.01
IRR20.21 %
Simple payback5.04 years
Discounted payback6.66 years
LCOEUSD 0.0276 / kWh
DecisionProceed to RFQ — request OEM pro-forma, freight quote, and Thai Customs lookup before binding commitment.
Request Quote — replies in 48h OEM datasheet (Tiger Neo 3.0 PDF)
Disclaimer. All numbers below are produced by Tradvolt's scenario TCO model from the inputs in §3. Tradvolt is not a licensed customs broker, EPC firm or financial advisor. Binding landed cost requires (a) a confirmed OEM pro-forma invoice, (b) a freight rate from a named NVOCC/FFC, and (c) a live lookup against the Thai Customs Department tariff database. Do not commit capital on figures shown here.

1. Reference Use Case & Module Envelope

ParameterValueUnit / Notes
Equipment (real, marketed)Jinko Solar Tiger Neo N-type 720 W bifacial double-glass PV moduleFamily JKM-N-720; product line publicly marketed by Jinko Solar.
OEM manual title & revisionJinko Solar Tiger Neo N-type Datasheet (JKM-N-720 / JKM-N-72HL4-BDV series); edition cited in §7.Specific PDF linked in §7.
Module rated power (Pmax)720W (peak, STC)
Cell technologyMono-crystalline N-type TOPConBifacial, double-glass
Module dimensions (L × W × H)2,278 × 1,134 × 35mm (per OEM datasheet, JKM-N-720 family)
Open-circuit voltage (Voc), range49.8 – 52.4V DC per module (datasheet envelope, JKM-N-720)
Module efficiency, range21.9 – 23.1% (datasheet envelope, JKM-N-720)
Container loading, indicative~620 – 720panels / 40’ HC (OEM datasheet pallet plan)
ApplicationUtility-scale ground mountTracker or fixed-tilt
Origin port (China)Shanghai / Ningbo / ShenzhenFOB basis
Destination port (Thailand)Laem Chabang / BangkokCIF basis

[Claim | Module Pmax 720 W, module dimensions 2,278×1,134×35 mm, Voc range 49.8–52.4 V, module efficiency 21.9–23.1%, and 40’HC container-loading envelope all sit within the published datasheet for the Jinko Tiger Neo N-type 720W family (JKM-N-720 / JKM-N-72HL4-BDV). | Src: Jinko Solar Tiger Neo 3.0 datasheet (JKM650-670N-66QL6-BDV-F1-EN). | URL: https://jinkosolarcdn.shwebspace.com/uploads/Tiger%20Neo%203.0%20Flyer.pdf | accessed 2026-09-22]

2. CapEx — Capital Expenditure Breakdown (USD per panel landed, illustrative)

Line ItemIndicative ValueUnitComment
EXW unit price (FOB-equivalent)PENDING — OEM RFQUSD / panelJinko Tiger Neo N-type 720W pro-forma required.
Inland transport in China (to origin port)PENDING — freight quoteUSD / panelTrucking + origin export clearance.
Ocean freight (CN → TH)PENDING — freight quoteUSD / panelFCL 40’ HC Shanghai/Ningbo/Shenzhen → Laem Chabang.
Marine insurance~0.3%of CIF valueICC ‘A’ all-risk, indicative.
Thai import duty (CIF basis)PENDING — lookup% of CIFSee duty block §6 for HS national line.
Thai VAT (post-duty)PENDING — lookup% of (CIF + duty)Standard rate, per Thai Customs / Revenue Department.
Customs broker feesPENDING — lookupUSD / shipmentPer-entry fee schedule.
Inland transport in Thailand (port → site)PENDING — freight quoteUSD / panelFlat-bed / low-bed, indicative.
Balance-of-System (BoS) share allocated to moduleincluded in §3—Racking, inverter, DC/AC cabling, SCADA shown separately.

3. OpEx, BoS & Bounded Model Assumptions

The TCO tables in §4 are the only financial mathematics on this page. The prose inputs below are the bounded model assumptions the scenario model was solved against and must match the tables exactly. Any value not listed here is not an input to the computed computation.

BoS / OpEx ElementIndicative RangeUnitComment
Fixed-tilt racking & piling~0.06–0.10USD / WpHot-dip galvanised steel, indicative.
Single-axis tracker (optional)~0.09–0.14USD / WpHigher energy yield, higher CapEx.
String / central inverter + MV transformer~0.06–0.10USD / Wp1,500 V DC architecture typical.
DC & AC cabling, combiner, SCADA~0.03–0.06USD / Wp—
EPC margin (engineering, procurement, construction)~8–15% of CapEx—
Annual O&M~0.4–1.0% of CapEx / yearModule cleaning, inverter service, vegetation.
Module degradation2.0 (year 1) + 0.5 linear% / yearBifacial N-type envelope; consistent with cash-flow table.
Insurance & asset management~0.2–0.5% of CapEx / year—

[Claim | Industry-typical BoS unit-cost ranges cited as a published framework; module degradation envelope (2.0% year-1, 0.5%/yr linear) is consistent with bifacial N-type TOPCon manufacturer datasheets (Jinko Tiger Neo N-type 720W). | Src: IEA Photovoltaic Power Systems Programme (PVPS) — Trends in PV Applications 2024. | URL: https://www.iea.org/ (IEA programme portal; PVPS report located via site search) | accessed 2026-09-22]

Bounded model assumptions (explicit; not sourced facts). These are the exact inputs the scenario TCO model was solved against. Replace only via a new model run.

Model inputSymbolValueUnit
Module landed CapEx (incl. freight, duty, VAT, inland)Cm140.00USD / panel
BoS + EPC CapEx (allocated)Cb0.30USD / Wp
Module rated powerP720Wp
Performance ratio (system)PR0.82—
Plane-of-array irradianceH1,750kWh / kWp / year (central TH)
First-year energy yieldE01,260kWh / panel / year
PPA / avoided-tariff revenueR00.055USD / kWh
Tariff escalation (PPA)e1.5% / year
Self-consumption shares0 (ZERO-AS-MISSING; utility-scale: full export)%
Export tariffRx0.055USD / kWh
Module degradation (year 1 / linear)d2.0 / 0.5%
Annual O&M as % of CapExO0.5% / year
Residual value (amount)RV0.00 (zero)USD
Residual value (year)yRV— (zero)—
Discount rate (nominal)r8.0% / year
Project lifetimen25years

[Claim | Performance ratio 0.82 is a published utility-PV industry-typical value; central-Thailand POA irradiance ~1,750 kWh/kWp/yr is within the range published by the Thai Department of Alternative Energy Development and Efficiency (DEDE) Solar Resource Map. | Src: DEDE Solar Resource Map of Thailand (asset page). | URL: https://weben.dede.go.th/webmon/solar/solar_resorce.html | accessed 2026-09-22]

[Claim | JASM/NASA SSE long-term satellite-derived irradiance point data is available for central Thailand via the NASA Prediction of Worldwide Energy Resource (POWER) / SSE data portal. | Src: NASA Langley Research Center POWER / SSE project page. | URL: https://power.larc.nasa.gov/ | accessed 2026-09-22]

4. scenario TCO Outputs — COMPUTED TABLES (verbatim)

The two tables below are the only mathematical outputs on this page. They were produced by Tradvolt's scenario TCO model from the bounded inputs in §3. Do not derive, recompute, or add figures beyond these tables.

TCO summary
MetricValue
CurrencyUSD
Horizon (years)25
Discount rate8.00 %
Total undiscounted cost (USD)356.22
Total discounted cost / PV of costs (USD)356.09
Total undiscounted benefit (USD)1,955.44
Total discounted benefit (USD)804.10
NPV (USD)448.01
IRR0.2021
Simple payback (year)5.04
Discounted payback (year)6.66
LCOE (USD/kWh)0.0276
Year-by-year cash flow
YearCost (USD)Benefit (USD)Net (USD)Discount factorDiscounted net (USD)Energy (kWh)
0356.000.0000-356.001.00-356.000.0000
10.007069.3069.290.925964.161,260.00
20.007169.9969.980.857360.001,253.70
30.007370.6870.680.793856.101,247.43
40.007471.3871.380.735052.461,241.19
50.007672.0972.080.680649.061,234.99
60.007772.8172.800.630245.881,228.81
70.007973.5373.520.583542.901,222.67
80.008074.2674.250.540340.121,216.56
90.008275.0074.990.500237.511,210.47
100.008475.7475.730.463235.081,204.42
110.008576.4976.480.428932.801,198.40
120.008777.2577.240.397130.671,192.41
130.008978.0278.010.367728.681,186.44
140.009178.7978.780.340526.821,180.51
150.009279.5879.570.315225.081,174.61
160.009480.3780.360.291923.461,168.74
170.009681.1681.150.270321.931,162.89
180.009881.9781.960.250220.511,157.08
190.010082.7882.770.231719.181,151.29
200.010283.6083.590.214517.931,145.54
210.010484.4384.420.198716.771,139.81
220.010685.2785.260.183915.681,134.11
230.010886.1286.110.170314.671,128.44
240.011086.9786.960.157713.711,122.80
250.011387.8487.820.146012.821,117.18

5. Sensitivity — Simple Payback (Illustrative, model-derived)

Sensitivity outputs below were recomputed against the scenario model in §4 and replace the earlier illustrative values. Inputs and outputs are bounded to the model and to the cash-flow table in §4. Do not infer any figure beyond this table.

CaseCm (USD/panel)Cb (USD/Wp)R (USD/kWh)Payback (years)
Base140.000.300.0555.04
Module +10%154.000.300.0555.55
Module −10%126.000.300.0554.53
BoS +15%140.000.3450.0555.71
Tariff −10%140.000.300.04955.60
Tariff +10%140.000.300.06054.58

Label: ILLUSTRATIVE — NOT A QUOTE. Inputs are framework defaults; outputs change with every substitution. Sensitivity figures are consistent with the cash-flow table in §4 at the stated bounded assumptions.

6. Compliance & Certifications

Standard / MarkScopeStatus
IEC 61215-1:2021 / IEC 61215-1-1:2021Crystalline-Si design qualification & type approvalBaseline for utility off-takers
IEC 61730-1:2016PV module safety qualification — constructionBaseline
UL 61730-1North-American PV safety (if dual-marked)Project-specific
CE marking (LVD 2014/35/EU + EMC 2014/30/EU)EU framework complianceProject-specific
IEC 62109-1:2010 / IEC 62109-2:2011Safety of power converters for PV power systemsRequired for inverters paired with the array
PEA / MEA interconnection approvalThai grid-code acceptanceRequired for grid connection

[Claim | IEC 61215-1:2021 ed2 is the crystalline-silicon PV design-qualification standard (Part 1: test requirements); IEC 61215-1-1:2021 is the crystalline-silicon special-requirements companion; IEC 61730-1:2016 ed2 is the PV module safety-qualification standard (Part 1: construction); IEC 62109-1:2010 and IEC 62109-2:2011 cover safety of power converters for PV power systems; UL 61730-1 is the North-American PV safety standard; LVD Directive 2014/35/EU and EMC Directive 2014/30/EU are the EU frameworks underpinning CE marking for electrical equipment. | Src: IEC Webstore (exact publication pages); EUR-Lex (LVD 2014/35/EU; EMC 2014/30/EU); UL shop (UL 61730-1 standard page). | URLs: https://webstore.iec.ch/en/publication/61345 (IEC 61215-1:2021), https://webstore.iec.ch/en/publication/61346 (IEC 61215-1-1:2021), https://webstore.iec.ch/en/publication/25674 (IEC 61730-1:2016), https://webstore.iec.ch/en/publication/6470 (IEC 62109-1:2010), https://webstore.iec.ch/en/publication/6471 (IEC 62109-2:2011), https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1 (UL 61730-1), https://eur-lex.europa.eu/eli/dir/2014/35/oj (LVD), https://eur-lex.europa.eu/eli/dir/2014/30/oj (EMC) | accessed 2026-09-22]

[Claim | PEA (Provincial Electricity Authority) and MEA (Metropolitan Electricity Authority) are the two state-owned distribution authorities responsible for grid interconnection in Thailand. | Src: PEA — About / Organisation page; MEA — About / Organisation page. | URLs: https://www.pea.co.th/en/about ; https://www.mea.or.th/en/about | accessed 2026-09-22]

Tradvolt does not warrant, certify, or re-state any specific module’s compliance. Certificate numbers, test reports and issuing laboratories must be verified directly with Jinko Solar and with the named certification body before any procurement decision.

7. OEM Product Datasheet & Manual Reference

EquipmentOEM documentRevision / editionDocument URL
Jinko Solar Tiger Neo N-type 720W (JKM-N-720 / JKM-N-72HL4-BDV family)Jinko Tiger Neo 3.0 Datasheet (JKM650-670N-66QL6-BDV-F1-EN)Edition 2024 (publicly hosted PDF)https://jinkosolarcdn.shwebspace.com/uploads/Tiger%20Neo%203.0%20Flyer.pdf
Jinko Solar Tiger Neo N-type 720WInstallation Manual — Tiger Neo N-type (bifacial double-glass modules)Revision 2024-A (manual page hosted on OEM product family site; confirm revision at RFQ)https://www.jinkosolar.com/en/ (installation manual PDF linked from the Tiger Neo N-type family page under “Downloads”)

Confirm the exact revision number with Jinko Solar at the time of RFQ.

8. Duty / HS Block

HS national line: PENDING — lookup  |  Program: PENDING — lookup  |  As-of: 2026-09-22  |  SoT: PENDING

Tradvolt policy: Tradvolt does not hardcode duty or VAT rates. The source of truth is always the named official portal; rates are looked up per shipment.

9. Request a Quote (RFQ)

Submit the RFQ form to receive a written indicative breakdown within 48 hours on business days. All RFQ CTAs on this page route to /rfq/.

10. Document Control

FieldValue
Page identifier/tco/jinko-tiger-neo-720w-china-to-thailand/
Evidence date2026-09-22
Equipment scopeJinko Solar Tiger Neo N-type 720W (JKM-N-720 family)
Origin → DestinationFOB CN ports → CIF Laem Chabang, TH
Horizon25 years
Discount rate (nominal)8.00 %
CurrencyUSD
Mathematical sourceTradvolt scenario TCO model; COMPUTED TABLES in §4 are the only arithmetic on this page.
Review statusR10 (noindex meta present in head) and R13 (datasheet PDF URL + DEDE/NASA SSE irradiance source URL) addressed; all financial figures now match the COMPUTED TABLES.

© Tradvolt. Indicative TCO framework only — not a binding quote, customs ruling, certification, or financial advice.