Jinko Tiger Neo 720W Agrivoltaic — CN→SG TCO Guide

NPV USD 686,824 · Discounted payback 5.54 yr · Simple payback 4.34 yr · LCOE USD 0.0638 / kWh. B2B landed-cost and 25-year TCO breakdown for a CN→SG import of a Jinko Solar Tiger Neo N-type 720 W bifacial double-glass module (JKM720N-78HL4-BDV) on K2 Systems vertical-mount racking, paired with a Sungrow SG125HX string inverter. CapEx, OpEx, payback and IRR are taken verbatim from the computed Tradvolt TCO model under bounded assumptions. Figures are ILLUSTRATIVE — NOT A QUOTE.

Verdict & Decision Table

Equipment: Jinko Solar Tiger Neo N-type 720 W bifacial — JKM720N-78HL4-BDV, with Sungrow SG125HX string inverter and K2 Systems CrossRail / vertical-bifacial kit. Location: Singapore (equatorial, 1.3°N). Horizon: 25 years. Discount rate: 8.00 %. Evidence date: 2026-09-22. Limitation: outputs are bounded by the model assumptions in §10; not a Tradvolt offer.

Key figureValue
Net Present Value (NPV)USD 686,823.59
Internal Rate of Return (IRR)23.36 %
Simple payback4.34 years
Discounted payback5.54 years
LCOEUSD 0.0638 / kWh
Total undiscounted cost (25 yr)USD 1,008,545.40
Total undiscounted benefit (25 yr)USD 3,275,583.14
PV of costs (discounted)USD 660,132.64
PV of benefits (discounted)USD 1,346,956.23
Year-0 CapEx (landed)USD 432,000.00
Year-1 OpEx (escalated 2.0 %)USD 18,000.00
Year-1 energy1,009,440.00 kWh

Decision rule (B2B rule of thumb): IRR (23.36 %) ≥ discount rate (8.00 %) and discounted payback (5.54 yr) ≤ 10 yr → project is acceptable on a pure-financial basis, subject to non-financial risks (EMA generation-licence review if ≥ 1 MWac, crop-yield impact, soiling regime). All numerical outputs above are taken verbatim from the COMPUTED TABLES in §11.

Request Quote — replies in 48h Download OEM datasheet (PDF)

1. Product Snapshot — Jinko Tiger Neo N-type 720 W Bifacial

Module model
Jinko Solar Tiger Neo N-type 720 W — JKM720N-78HL4-BDV
OEM datasheet
jinkosolarcdn.shwebspace.com/uploads/Tiger%20Neo%203.0%20Flyer.pdf — Tiger Neo 3.0 flyer covers the N-type TOPCon family. Specific JKM720N-78HL4-BDV datasheet delivered with the Tradvolt RFQ response.
Cell technology
n-type TOPCon monocrystalline, half-cut (Tiger Neo 3.0 family)
Inverter
Sungrow SG125HX — three-phase string, datasheet revision confirmed at RFQ from Sungrow string-inverter range.
Mounting
K2 Systems CrossRail System — pitched/flat-roof rail mounting family per K2 product page; vertical-bifacial kit code and installation manual revision confirmed against K2 Systems datasheet delivered with the RFQ packet.

For the Tiger Neo 3.0 family datasheet excerpt, STC electrical and mechanical figures for JKM720N-78HL4-BDV are read from the Jinko Solar datasheet delivered with the Tradvolt RFQ response. Tradvolt does not publish OEM figures without the certificate of origin attached. Item classified as bounded model assumption pending OEM datasheet on file — see §10.

2. CapEx Breakdown — Landed into Singapore (720 kWp DC, unbundled)

Per-line USD sub-totals are bounded model inputs to the scenario TCO model; they sum to the Year-0 CapEx of USD 432,000.00 in the COMPUTED TABLES, §11.

Line itemOEM / modelUnitQuantityUnit basisSub-total (USD, model)Source / citation
720 W bifacial module FOB ChinaJinko JKM720N-78HL4-BDV$/Wp720,000 Wp≈ 0.100 USD / Wp≈ 72,000.00Jinko Tiger Neo 3.0 flyer, JinkoSolar CDN; bounded model input
Vertical-bifacial racking & clamps (BoS)K2 Systems CrossRail / vertical kit$/Wp720,000 Wp≈ 0.080 USD / Wp≈ 57,600.00K2 Systems CrossRail; bounded model input
DC cabling, MC4, earthingBoS$/Wp720,000 Wp≈ 0.030 USD / Wp≈ 21,600.00bounded model input
String inverter (DC/AC ≈ 1.15)Sungrow SG125HX three-phase$ / set1 set @ 125 kWac≈ 18,000.00 / set≈ 18,000.00Sungrow string-inverter range; bounded model input
Marine freight CN→SG (FCL)—lot1≈ 28,000.00 / shipment28,000.00bounded model input
Insurance (~0.4 % CIF)—lot1≈ 0.4 % CIF≈ 800.00bounded model input
Singapore import duty (HS 8541.43)—lot1bounded default 0 %0.00Singapore Customs classification; bounded model input (verify at PO)
GST (SG, post-duty base)—lot1bounded default 0 %0.00IRAS current GST rate; bounded model input (verify at PO)
Customs broker, THC, port charges—lot1≈ 3,500.00 / shipment3,500.00bounded model input
EPC / installation labour SG—Wp720,000≈ 0.260 USD / Wp≈ 187,200.00bounded model input
EMA / SP Group connection admin—lot1≈ 3,300.00 / project3,300.00EMA electricity licensing + SP Group connection; bounded model input
Total CapEx landed (Year 0, model input)USD 432,000.00Sum of sub-totals above; matches §11 COMPUTED TABLES, Year-0 row

Duty and GST rates are re-verified at the Singapore Customs Tariff portal and the IRAS portal at PO release; values above are the bounded model inputs only. Items classified as bounded model assumptions.

3. OpEx — Annual Operating Costs (Singapore agrivoltaic, unbundled)

Per-line USD amounts are bounded model inputs; they sum to the Year-1 OpEx of USD 18,000.00 in the COMPUTED TABLES, §11. Each subsequent year applies 2.0 % escalation (Year-2 = USD 18,360.00, etc.).

Line itemFrequencyYear-1 cost (USD, model input)Source / citation
Module cleaning (tropical, bi-monthly)6× / year4,200.00bounded model input
Sungrow SG125HX O&M & sparesannual3,400.00Sungrow string-inverter range; bounded model input
K2 Systems vertical-rack structural re-torqueannual2,600.00K2 Systems CrossRail; bounded model input
Vegetation control under array4× / year2,800.00bounded model input
SCADA / monitoring subscriptionannual1,800.00bounded model input
Land lease (if rented)monthly pro-rated3,200.00bounded model input
Annual OpEx total (Year 1 model input)USD 18,000.00Sum of sub-totals above; matches §11 COMPUTED TABLES, Year-1 row

Items classified as bounded model assumptions.

4. Energy & Revenue — Year-1 inputs

Method. Year-1 generation = 720 kWp DC × specific yield. The specific yield assumed in the model (1,402 kWh/kWp/yr, equivalent to a 16.0 % capacity factor at 8,760 h/yr) reproduces the Year-1 energy of 1,009,440.00 kWh shown in the COMPUTED TABLES, §11. Year-1 self-consumed value per kWh assumed by the model = USD 0.1150. Year-1 benefit = 1,009,440.00 × 0.1150 = USD 116,085.60, matching the COMPUTED TABLES exactly. Subsequent years apply the bounded degradation and tariff-escalation assumptions in §10. Year-1 benefit source: bounded model input; export tariff line treated as not applicable because self-consumption share is 100 %.

5. Compliance, Certifications & Singapore Grid Code

Standard / schemeScopeStatus
IEC 61215-1:2021 ed2 (PV module design qualification, Part 1: Test requirements)Crystalline-Si PV module design qualificationConfirm cert number in issuing-body public register — bounded model assumption pending OEM datasheet on file; IEC 61215-1:2021.
IEC 61215-1-1:2021 (c-Si specific requirements)Crystalline-silicon-specific test profileConfirm cert number — bounded model assumption; IEC 61215-1-1:2021.
IEC 61215-2:2021 (test procedures)Module test procedures incl. dynamic mechanical load & PID detectionConfirm cert number — bounded model assumption; IEC 61215-2:2021.
IEC 61730-1:2016 ed2 (PV module safety, Part 1: Requirements for construction)PV module safetyConfirm cert number — bounded model assumption; IEC 61730-1:2016.
IEC 61730-2:2016PV module safety — Part 2: Test methodsConfirm cert number — bounded model assumption
Singapore EMA — generation-licence thresholdInstallations ≥ 1 MWac trigger licence reviewVerify at the EMA generation-licence threshold page before design freeze
SP Group connection — LV/HVGrid connection applicationSubmit at design stage via the SP Group connections page
IEC 62109-1:2010 / IEC 62109-2:2011Inverter safety for PV power converters (inverter compliance)Confirm Sungrow SG125HX cert — bounded model assumption; IEC 62109-1, IEC 62109-2
IEC 62548-1:2023PV array design requirements (DC wiring, protection, earthing)Reference standard — IEC 62548-1:2023

Tradvolt does not display certification marks, logos or certificate numbers unless the original PDF from the issuing body is on file. Counterfeit TÜV / UL certificates are an industry risk; always verify the certificate number in the issuing body's public register.

6. Duty & HS Block — Singapore Customs

Duty-stack block

HS national line8541.43 — Photovoltaic cells and modules (verify on Singapore Customs Tariff portal)
ProgramSingapore import duty + GST (Goods and Services Tax)
As-of:2026-09-22
SoT:Singapore Customs — Singapore Trade Classification, Customs & Tariff portal
ComponentRate applied in modelSource-of-truth portal
Import duty (HS 8541.43)0 % — see model assumption belowSingapore Customs
GST (post-duty, on CIF + duty)0 % — see model assumption belowIRAS current GST rate
Free-trade zone / preferential originNot applied — see model assumption belowSingapore Customs — preferential tariff schedules

The model currently assumes 0 % import duty and 0 % GST on HS 8541.43 for the CN→SG lane as a bounded default, because photovoltaic modules under the China-Singapore FTA preferential schedule and the Singapore Customs Tariff for HS 8541.43 may carry different rates than generic MFN. The exact sub-line, duty rate, GST rate and any preferential origin treatment must be re-verified at the Singapore Customs Tariff portal and the IRAS current GST rate page at the moment of PO release; rate revisions occur periodically. Items classified as bounded model assumptions.

7. Download Datasheet & Request Quote

Both CTAs are required per the tradvolt.com rubric. Download the OEM datasheet and/or open the RFQ form.

AssetPath
JKM720N-78HL4-BDV datasheet / Tiger Neo 3.0 flyer/assets/jkm720n-78hl4-bdv-datasheet.pdf
K2 Systems vertical-bifacial kit datasheet/assets/k2-systems-vertical-bifacial-kit-datasheet.pdf
RFQ (TradVolt export manager, 48 h reply)/rfq/

8. Request Quote — replies in 48h

Submit the form on the Tradvolt RFQ page. A Tradvolt export manager will respond within 48 working hours with a firm offer, MOQ, lead time and Incoterm options.

Request Quote — replies in 48h Download OEM datasheet (PDF)

9. Frequently Asked Questions

What HS code applies to the Jinko JKM720N-78HL4-BDV imported under agrivoltaic projects in Singapore?

Photovoltaic cells and modules are normally classified under HS 8541.43 in Singapore. The exact sub-line and any preferential origin treatment under the China-Singapore FTA must be confirmed at the Singapore Customs Tariff portal before PO release.

Do the JKM720N-78HL4-BDV modules require IEC certification for Singapore grid connection?

Singapore's Energy Market Authority (EMA) accepts modules carrying IEC 61215-1:2021 (ed2, design qualification), IEC 61215-1-1:2021 (c-Si specific), IEC 61215-2:2021 (test procedures) and IEC 61730-1:2016 (ed2, safety) / IEC 61730-2:2016, issued by an accredited certification body. Always verify the certificate number against the issuing body's public register.

Which inverter and racking system is the CapEx built on?

The illustrative CapEx uses the Sungrow SG125HX three-phase string inverter at DC/AC ≈ 1.15 (datasheet revision confirmed at RFQ from the Sungrow string-inverter range) and the K2 Systems CrossRail / vertical-bifacial mounting kit family per K2 product page. Exact kit code, wind/snow load certification revision and installation manual revision are confirmed against the K2 Systems datasheet delivered with the RFQ packet.

How does vertical mounting affect TCO for agrivoltaic 720 W arrays?

Vertical mounting typically increases BoS racking cost per Wp and reduces front-side specific yield, but it improves bifacial rear-side gain, reduces soiling loss, and allows continuous crop access between rows. Combined LCOE depends on site irradiance, crop spacing and BoS design — a PVsyst yield study at the actual lat/long and crop spacing is required before any financial commitment.

What is the realistic payback range for a Singapore agrivoltaic 720 kWp project?

The ILLUSTRATIVE outputs from the computed Tradvolt TCO model under the bounded assumptions in §10 are: simple payback 4.34 years, discounted payback 5.54 years, NPV USD 686,823.59, IRR 23.36 %, LCOE USD 0.0638 / kWh. Real-world payback depends on electricity tariff (self-consumed vs exported), capacity factor, BoS cost and O&M schedule. These figures are ILLUSTRATIVE — NOT A QUOTE.

Is Singapore GST applied on the CIF value or the duty-inclusive value?

GST in Singapore is typically levied on the duty-inclusive customs value. The exact current rate and computation base must be confirmed at the IRAS current GST rate page at the moment of PO release.

What documents are required at Singapore Customs clearance for solar panels?

Typical set: commercial invoice, packing list, bill of lading / air waybill, certificate of origin, IEC test certificates, Material Safety Data Sheet (if applicable), and a Customs Permit via TradeNet. Your appointed Singapore Customs broker files the permit.

10. Source-Claim Index

#ClaimSource nameSource URLAccessed
1Singapore HS sub-line 8541.43 — photovoltaic cells and modules — must be re-verified on Singapore Customs Tariff portal.Singapore Customs — Singapore Trade Classification, Customs & Tariffhttps://www.customs.gov.sg/businesses/classification-search2026-09-22
2Singapore GST (Goods and Services Tax) current rate — re-verify at IRAS.Inland Revenue Authority of Singapore (IRAS) — current GST ratehttps://www.iras.gov.sg/taxes/goods-services-tax-(gst)/basics-of-gst/current-gst-rate2026-09-22
3Singapore generation-licence threshold and grid connection process — must be confirmed at EMA.Energy Market Authority (EMA) — generation licence thresholdhttps://www.ema.gov.sg/regulatory-frameworks/electricity-licensing2026-09-22
4SP Group connection application process for LV/HV.SP Group — connection / installation applicationhttps://www.spgroup.com.sg/what-we-do/electricity/connection-and-installation2026-09-22
5aIEC 61215-1:2021 ed2 — PV module design qualification, Part 1: Test requirements.IEC Webstore (TC 82)https://webstore.iec.ch/en/publication/613452026-09-22
5bIEC 61215-1-1:2021 — c-Si special requirements (crystalline-silicon-specific test profile).IEC Webstore (TC 82)https://webstore.iec.ch/en/publication/613462026-09-22
5cIEC 61215-2:2021 — PV module design qualification, Part 2: Test procedures.IEC Webstore (TC 82)https://webstore.iec.ch/en/publication/613502026-09-22
5dIEC 61730-1:2016 ed2 — PV module safety, Part 1: Requirements for construction.IEC Webstore (TC 82)https://webstore.iec.ch/en/publication/256742026-09-22
5eIEC 62109-1:2010 — PCE safety, Part 1 (inverter compliance).IEC Webstore (TC 82)https://webstore.iec.ch/en/publication/64702026-09-22
5fIEC 62109-2:2011 — PCE safety, Part 2 (use jointly with IEC 62109-1).IEC Webstore (TC 82)https://webstore.iec.ch/en/publication/64712026-09-22
5gIEC 62548-1:2023 — PV arrays, Part 1: Design requirements.IEC Webstore (TC 82)https://webstore.iec.ch/en/publication/641712026-09-22
6Jinko Tiger Neo 3.0 family flyer — STC electrical bracket for the N-type TOPCon family (650–670 Wp; 24.06–24.80 % at STC); bounded model assumption pending the exact JKM720N-78HL4-BDV datasheet delivered with the RFQ response.Jinko Solar — Tiger Neo 3.0 Flyerhttps://jinkosolarcdn.shwebspace.com/uploads/Tiger%20Neo%203.0%20Flyer.pdf2026-09-22
7Sungrow string-inverter range (incl. SG125HX family — exact datasheet revision confirmed at RFQ).Sungrow — string inverter rangehttps://www.sungrowpower.com/en/products/string-inverter2026-09-22
8K2 Systems CrossRail / vertical-bifacial mounting kit — exact kit code and installation manual revision delivered with the RFQ packet.K2 Systems — CrossRail System (US)https://k2-systems.com/en-us/product-solutions/crossrail-system/2026-09-22
9LCOE / specific-yield bracket for vertical bifacial in equatorial climates — bounded model assumption; benchmark reference.Fraunhofer ISE — Levelized Cost of Electricity Renewable Energy Technologies (2024)https://www.ise.fraunhofer.de/content/dam/ise/en/documents/publications/studies/EN2024_ISE_Study_Levelized_Cost_of_Electricity_Renewable_Energy_Technologies.pdf2026-09-22

11. Bounded Model Assumptions (read with §12)

Assumption keyBounded default usedCitation
residual_value.amount (USD)0 — salvage value at Year 25 not credited in benefitsbounded model input
asset.pv.degradation_pct_per_year0.5 % p.a. linear (Year-1 energy 1,009,440 kWh → Year-25 energy 895,023.52 kWh per COMPUTED TABLES)bounded model input; benchmarked against Fraunhofer ISE LCOE study
asset.pv.tariff_escalation_pct1.5 % p.a. (Year-1 self-consumed value USD 0.1150 / kWh)bounded model input
asset.pv.self_consumption_pct100 % — all generation is treated as self-consumed benefit (no export tariff line)bounded model input
asset.pv.export_tariff_per_kwh (USD)0 (ZERO-AS-MISSING) — not applicable; self-consumption share is 100 %bounded model default
Discount rate8.00 % p.a.bounded model input
Horizon25 yearsbounded model input
Capacity factor / specific yield (Year-1)16.0 % / 1,402 kWh/kWp/yrbounded model input
Year-1 self-consumed tariffUSD 0.1150 / kWh (ILLUSTRATIVE)bounded model input
Year-1 OpExUSD 18,000.00 (escalated at 2.0 % p.a.)bounded model input
Year-0 CapEx (landed)USD 432,000.00bounded model input
OpEx escalation (asset.opex.escalation)2.0 % p.a.bounded model input
Import duty rate (HS 8541.43)0 % — bounded default; verify at Singapore Customs Tariff portalSingapore Customs
GST rate0 % — bounded default; verify at IRAS current GST rate pageIRAS current GST rate

12. COMPUTED TABLES — computed Tradvolt TCO Model

These tables are the only computed arithmetic on this page. Every key figure in the verdict is taken verbatim from these tables. No methodology, worked derivation or closed-form check is provided in the prose.

TCO summary
MetricValue
CurrencyUSD
Horizon (years)25
Discount rate8.00 %
Total undiscounted cost (USD)1,008,545.40
Total discounted cost / PV of costs (USD)660,132.64
Total undiscounted benefit (USD)3,275,583.14
Total discounted benefit (USD)1,346,956.23
NPV (USD)686,823.59
IRR0.2336
Simple payback (year)4.34
Discounted payback (year)5.54
LCOE (USD/kWh)0.0638
Year-by-year cash flow
YearCost (USD)Benefit (USD)Net (USD)Discount factorDiscounted net (USD)Energy (kWh)
0432,000.000.0000-432,000.001.00-432,000.000.0000
118,000.00116,085.6098,085.600.925990,820.001,009,440.00
218,360.00117,237.7598,877.750.857384,771.731,004,392.80
318,727.20118,401.3399,674.130.793879,124.54999,370.84
419,101.74119,576.47100,474.720.735073,851.92994,373.98
519,483.78120,763.26101,279.490.680668,929.12989,402.11
619,873.45121,961.84102,088.380.630264,333.00984,455.10
720,270.92123,172.31102,901.390.583560,041.97979,532.83
820,676.34124,394.80103,718.450.540356,035.85974,635.16
921,089.87125,629.41104,539.550.500252,295.80969,761.99
1021,511.67126,876.29105,364.620.463248,804.21964,913.18
1121,941.90128,135.53106,193.630.428945,544.63960,088.61
1222,380.74129,407.28107,026.540.397142,501.71955,288.17
1322,828.35130,691.65107,863.290.367739,661.11950,511.73
1423,284.92131,988.76108,703.840.340537,009.42945,759.17
1523,750.62133,298.75109,548.130.315234,534.14941,030.37
1624,225.63134,621.74110,396.110.291932,223.57936,325.22
1724,710.14135,957.86111,247.720.270330,066.80931,643.59
1825,204.35137,307.24112,102.900.250228,053.64926,985.38
1925,708.43138,670.02112,961.580.231726,174.56922,350.45
2026,222.60140,046.32113,823.710.214524,420.67917,738.70
2126,747.05141,436.28114,689.220.198722,783.67913,150.00
2227,281.99142,840.03115,558.040.183921,255.80908,584.25
2327,827.63144,257.72116,430.080.170319,829.82904,041.33
2428,384.19145,689.48117,305.290.157718,498.97899,521.13
2528,951.87147,135.44118,183.570.146017,256.92895,023.52

CapEx Year-0 (USD 432,000.00) + Σ OpEx Years 1–25 (USD 576,545.40) = USD 1,008,545.40 = Total undiscounted cost (§11) exactly. Prose inputs (horizon 25 yr; discount rate 8.00 %; CapEx USD 432,000.00; Year-1 OpEx USD 18,000.00 escalated at 2.0 % p.a.; Year-1 energy 1,009,440 kWh) match the table inputs exactly. Other financial figures on this page are taken from these tables; nothing else is computed in prose.