| Decision metric | Base case value (computed) | Decision rule |
|---|---|---|
| NPV (USD) | 1,546,849.17 | GO if NPV > 0 |
| IRR | 0.1092 (10.92%) | GO if IRR > hurdle rate (8.00% real) |
| Simple payback (yr) | 8.57 | GO if ≤ project horizon / 3 (≈8.3 yr) — borderline; passes on NPV/IRR |
| Discounted payback (yr) | 15.38 | GO if ≤ 15 yr — borderline; passes on NPV/IRR |
| LCOE (USD/kWh) | 0.0814 | GO if site grid tariff or displaced retail rate > LCOE |
A 6 MWp solar plant installed at a logistics park within 1.5 km of a coastline. The installation combines rooftop on warehouses (~4 MWp) and ground-mount on adjacent paved/logistics yards (~2 MWp), feeding captive load (sortation, cold-chain where applicable, EV forklift charging, lighting, HVAC) and exporting the residual to the grid under a PPA or net-billing scheme.
Sea-exposed sites introduce specific cost uplifts and operational constraints: airborne chloride deposition accelerates corrosion of mounting structures, cabling conduits, inverters, and module frames; salt fog reduces soiling-cleaning intervals; high wind speeds demand enhanced anchoring; humidity shortens DC connector life. These factors increase the OPEX share of TCO relative to inland sites of the same capacity.
| Item | Named OEM model / family | OEM product page (URL) | Sea-site relevance |
|---|---|---|---|
| PV modules (primary) | LONGi Hi-MO 9 (back-contact HPBC 2.0, up to 670 W) | https://www.longi.com/en/products/modules/hi-mo-9/ | Dual-glass, salt-mist testing per IEC 61701 recommended for C5-M; PID resistant per IEC 62804-1. |
| PV modules (alt) | Jinko Solar Tiger Neo 3.0 N-type (JKM650–670N-66QL6-BDV, 650–670 W) | https://jinkosolarcdn.shwebspace.com/uploads/Tiger%20Neo%203.0%20Flyer.pdf | N-type TOPCon, IEC 61215-1:2021 / IEC 61730-1/-2 qualification; IEC 61701 salt-mist dossier on request. |
| String inverter (primary) | Huawei SUN2000-330KTL-H1 (300 kW, 1500 Vdc) | https://solar.huawei.com/en | IP66 enclosure, conformal-coated PCB; C5-M rating per Huawei product manual (revision confirmed at RFQ). |
| String inverter (alt) | Sungrow SG250HX (250 kW, 1500 Vdc) | https://www.sungrowpower.com/en | IP66, C5 corrosion class per Sungrow datasheet (revision confirmed at RFQ). |
| Hybrid/aux inverter (small) | Growatt SPH 3000–6000 TL BH | https://www.growatt.com/ | Auxiliary loads / small office; not the main 6 MWp inverter chain. |
| Storage (optional, paired) | CATL EnerC 372.7 kWh cabinet | https://www.catl.com/en/ess/ | Listed for completeness; not part of the base-case TCO below. |
| Mounting structure (example) | K2 Systems CrossRail System (pitched/flat-roof rail family) | https://k2-systems.com/en-us/product-solutions/crossrail-system/ | C5-M coating selection per ISO 12944-6:2018; manual revision confirmed at RFQ. |
Inverter torque, SOC, and DC voltage limits follow the linked OEM manuals at the cited revision (confirmed at RFQ for each awarded BOM). Module and inverter product pages are maker landing pages (JS-rendered); datasheet PDFs and manual revisions are released with each RFQ response. Site-specific derating (e.g., max DC Voc 1500 V, IP66 rating) is taken from those manuals, not from generic "string inverter" placeholders.
| Parameter | Value | Unit | Source URL / assumption |
|---|---|---|---|
| Installed capacity (DC) | 6.0 | MWp | TradVolt r9 reference design (model assumption) |
| Capacity factor (sea-site) | 16.5 | % | EU PVGIS-SARAH2, coastal latitude band, tilt 20°, azimuth south |
| Sea-corrosion opex uplift | +35 | % vs. inland | ISO 9223:2012 C5-M class (very high, marine) vs. C3 class, applied to OpEx per NREL/TP-7A20/83880 (2022) |
| Specific yield (year 1) | 1,445 | kWh/kWp/yr | Derived: 0.165 × 8,760 h (PVGIS) |
| Annual generation year 1 (gross) | 8,670,000 | kWh/yr | Derived: 6,000 × 1,445 |
| Self-consumption ratio (SCR) | 70 | % | TradVolt logistics-segment benchmark (model assumption) |
| CapEx (year 0) | 5,700,000 (≈0.95 USD/Wp) | USD | Scenario model input (see §4 cashflow year 0); benchmark band per IRENA (2025), Renewable Power Generation Costs in 2024 |
| Discount rate (WACC) | 8.0 | % real | TradVolt logistics-segment hurdle (model assumption) |
| Project horizon | 25 | years | TradVolt default PV horizon (model assumption) |
| Decommissioning reserve | 5 | % of CapEx | IEA PVPS Task 12, end-of-life reserve convention |
| Inverter replacement | once in yr 13 | — | Year-13 cost spike in the computed cashflow (see §5) |
| Assumption key | Bound used | Type |
|---|---|---|
| asset.pv.degradation_pct_per_year | 0.50 %/yr linear | Model assumption (typical for N-type TOPCon / back-contact modules) |
| asset.pv.tariff_per_kwh | 0.099 USD/kWh (base, displaced retail) | Model assumption — substitute site tariff before procurement |
| asset.pv.tariff_escalation_pct | 1.50 %/yr (real-terms) | Model assumption |
| asset.pv.export_tariff_per_kwh | 0.060 USD/kWh (export/PPA residual) | Model assumption — substitute site PPA before procurement |
| opex.escalation_pct | 2.00 %/yr | Model assumption (consistent with computed cashflow OpEx progression y1→y12, y14→y25) |
| Metric | Value |
|---|---|
| Currency | USD |
| Horizon (years) | 25 |
| Discount rate | 8.00 % |
| Total undiscounted cost (USD) | 9,431,190.54 |
| Total discounted cost / PV of costs (USD) | 7,235,455.01 |
| Total undiscounted benefit (USD) | 21,357,165.73 |
| Total discounted benefit (USD) | 8,782,304.18 |
| NPV (USD) | 1,546,849.17 |
| IRR | 0.1092 |
| Simple payback (year) | 8.57 |
| Discounted payback (year) | 15.38 |
| LCOE (USD/kWh) | 0.0814 |
All figures above were computed by the computed TradVolt TCO model from the input scenario in §3. They are computed for this scenario.
| Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 5,700,000.00 | 0.0000 | -5,700,000.00 | 1.00 | -5,700,000.00 | 0.0000 |
| 1 | 111,900.00 | 756,891.00 | 644,991.00 | 0.9259 | 597,213.89 | 8,670,000.00 |
| 2 | 114,138.00 | 764,403.14 | 650,265.14 | 0.8573 | 557,497.55 | 8,626,650.00 |
| 3 | 116,420.76 | 771,989.84 | 655,569.08 | 0.7938 | 520,411.88 | 8,583,516.75 |
| 4 | 118,749.18 | 779,651.84 | 660,902.67 | 0.7350 | 485,783.19 | 8,540,599.17 |
| 5 | 121,124.16 | 787,389.89 | 666,265.73 | 0.6806 | 453,449.26 | 8,497,896.17 |
| 6 | 123,546.64 | 795,204.73 | 671,658.09 | 0.6302 | 423,258.53 | 8,455,406.69 |
| 7 | 126,017.57 | 803,097.14 | 677,079.57 | 0.5835 | 395,069.42 | 8,413,129.66 |
| 8 | 128,537.93 | 811,067.88 | 682,529.95 | 0.5403 | 368,749.70 | 8,371,064.01 |
| 9 | 131,108.68 | 819,117.73 | 688,009.04 | 0.5002 | 344,175.81 | 8,329,208.69 |
| 10 | 133,730.86 | 827,247.47 | 693,516.61 | 0.4632 | 321,232.38 | 8,287,562.64 |
| 11 | 136,405.48 | 835,457.90 | 699,052.43 | 0.4289 | 299,811.60 | 8,246,124.83 |
| 12 | 139,133.59 | 843,749.82 | 704,616.24 | 0.3971 | 279,812.80 | 8,204,894.21 |
| 13 | 573,916.26 | 852,124.04 | 278,207.78 | 0.3677 | 102,296.42 | 8,163,869.74 |
| 14 | 144,754.58 | 860,581.37 | 715,826.79 | 0.3405 | 243,711.13 | 8,123,050.39 |
| 15 | 147,649.67 | 869,122.64 | 721,472.97 | 0.3152 | 227,438.37 | 8,082,435.14 |
| 16 | 150,602.67 | 877,748.68 | 727,146.02 | 0.2919 | 212,246.99 | 8,042,022.96 |
| 17 | 153,614.72 | 886,460.34 | 732,845.62 | 0.2703 | 198,065.42 | 8,001,812.84 |
| 18 | 156,687.01 | 895,258.46 | 738,571.44 | 0.2502 | 184,826.79 | 7,961,803.78 |
| 19 | 159,820.76 | 904,143.90 | 744,323.14 | 0.2317 | 172,468.65 | 7,921,994.76 |
| 20 | 163,017.17 | 913,117.53 | 750,100.35 | 0.2145 | 160,932.69 | 7,882,384.79 |
| 21 | 166,277.51 | 922,180.22 | 755,902.70 | 0.1987 | 150,164.42 | 7,842,972.86 |
| 22 | 169,603.06 | 931,332.86 | 761,729.79 | 0.1839 | 140,112.96 | 7,803,758.00 |
| 23 | 172,995.13 | 940,576.33 | 767,581.21 | 0.1703 | 130,730.81 | 7,764,739.21 |
| 24 | 176,455.03 | 949,911.55 | 773,456.53 | 0.1577 | 121,973.58 | 7,725,915.51 |
| 25 | -105,015.87 | 959,339.43 | 1,064,355.30 | 0.1460 | 155,414.93 | 7,687,285.94 |
Year 0 cost is the as-spent CapEx of USD 5,700,000. Year 13 carries the inverter-replacement spike in computed costs. Year 25 cost is negative due to the release of the decommissioning reserve (5% × CapEx = USD 285,000) net of the year-25 OpEx line. The computed cashflow is the only financial arithmetic on this page; any apparent recompute or alternative figure is model drift and must be ignored.
Submit your site coordinates, load profile, and grid-tariff context. TradVolt returns a sea-rated BOM (LONGi / Jinko modules, Huawei / Sungrow inverters, C5-M BoS) and an LCOE band in 5 business days.
Certification status is project-specific. TradVolt provides the test-report dossier with each RFQ response; actual certificate scope must be verified against the awarded BOM.
| HS / HTS code | Description | Duty indicator |
|---|---|---|
| 8541.43 (CN / EU TARIC) | Photovoltaic cells assembled in modules | Verify current duty and CBAM/Carbon Border status at EU TARIC consultation before import commitment |
| 8541.40 (US HTSUS) | Photosensitive semiconductor devices (incl. PV cells) | Verify per USITC HTS; duty depends on chapter notes |
| 8504.40 (HTSUS / CN) | Static converters (inverters) | Verify per USITC HTS and EU TARIC |
| 7308.20 | Towers, lattice masts — steel structures (mounting) | Verify per USITC HTS |
| 7610.90 | Aluminum structures and parts (mounting) | Verify per USITC HTS |
| 8544.42 | Electric conductors, fitted with connectors (DC cabling) | Verify per USITC HTS |
| 8507.60 (storage only) | Lithium-ion accumulators (CATL EnerC cabinets) | Verify per USITC HTS; transport per UN Manual of Tests and Criteria, Rev.7 (ST/SG/AC.10/11/Rev.7), §38; and Regulation (EU) 2023/1542 if EU-destined |
| Any destination | — | Lookup via UK Global Tariff, Japan Customs, Australian Border Force, South African Revenue Service, Ghana Revenue Authority, Uganda Revenue Authority, Turkey Ministry of Trade as applicable |
Sea-corrosion uplift (+35% OpEx base) maps ISO 9223 C5-M class to logistics-park context per NREL/TP-7A20/83880 (2022). Validate against local corrosion surveys before procurement commitment.