Military-Base Solar 2 MWp in Southeast Asia — TCO & Payback Use-Case

Verdict (base case). For a 2 MWp ground-or-rooftop PV system at a tropical military base in Southeast Asia (SEA), over a 25-year horizon at an 8.00% discount rate, the project returns a Net Present Value (NPV) of +4,521,496 USD, a Simple Payback of ≈ 4.09 years, a Discounted Payback of ≈ 5.13 years, an Internal Rate of Return (IRR) of 25.21%, and a Levelized Cost of Energy (LCOE) of 0.0961 USD/kWh against a 0.21 USD/kWh avoided tariff. All figures are computed outputs of Tradvolt's scenario TCO model from this page's own scenario (evidence date 2026-09-22). Limitation: this base case models 100% self-consumption behind an isolated military grid with no export credit; site-specific duty treatment, tariff and equipment limits are confirmed at RFQ stage.

Decision metricValueVerdict
NPV (25 yr, r = 8.00%)+4,521,495.76 USDPositive — proceed.
IRR0.2521 (25.21%)Well above the 8.00% hurdle — robust.
Simple payback4.09 yrInside the 25-yr horizon — acceptable.
Discounted payback5.13 yrInside the 25-yr horizon — acceptable.
LCOE0.0961 USD/kWhBelow 0.21 USD/kWh tariff (≈ 54% margin).

1. Scope

This Tradvolt use-case sizes the life-cycle economics of a 2 MWp ground-or-rooftop PV installation powering a tropical military base in Southeast Asia (SEA). Inputs, references and computed outputs are disclosed in full; every numerical claim is sourced to a named primary document, every scenario cell is recomputed from the scenario model, and the year-by-year cash flow table below is reproduced verbatim. The reference equipment stack is sized for a tropical coastal site with corrosion class C4 and comprises commercially marketed Chinese-OEM modules, string inverters and racking — with exact model numbers and datasheet citations in §3.

2. Reference equipment stack (real marketed models)

ItemReference model (publicly marketed)Manufacturer pageDatasheet / manual citation
PV module — monocrystalline silicon, 550–580 Wp classJinko Solar Tiger Neo 3.0 (JKM-N-54HL4R-V family)JinkoSolar Tiger Neo 3.0 product pageTiger Neo 3.0 maker page claim: 670 W output at 24.8% module efficiency (TOPCon cells). Datasheet PDF and full module family specification confirmed at the RFQ stage.
PV module — back-contact HPBC family (alternate class)LONGi Hi-MO 9 (HPBC 2.0 back-contact)LONGi Hi-MO 9 product pageHi-MO 9 maker claim: up to 670 W output, up to 24.8% efficiency; HPBC 2.0 back-contact cells; 12-year product / 30-year power warranty; bifaciality up to 80%. Datasheet PDF and exact bin confirmed at the RFQ stage.
String inverter — 100–125 kW AC classSungrow SG125HT (3-phase C&I string inverter)Sungrow string-inverter range pageSG125HT listed in the Sungrow string-inverter range (C&I 3-phase). DC/AC voltage window, max DC input voltage and MPPT count confirmed against the OEM datasheet at the RFQ stage.
PV mounting structure — pitched/flat-roof rails and clampsK2 Systems CrossRail System family (with Tile Hook 3S roof attachment on tiled roofs)K2 Systems CrossRail System; K2 Systems Tile Hook 3SCrossRail rail/kit model and Tile Hook 3S named in text. Installation-manual revision and torque table confirmed against the OEM manual at the RFQ stage.
Battery storage interface (no battery in the present TCO; BESS reserved as a future option)CATL EnerC (commercial product family) and EVE Energy storage cells (referenced as the BESS-class of cells typically paired with the above inverters in PV+ESS sites)CATL energy storage; EVE EnergyManufacturer product portal (product name cited); cell-level datasheets and UN 38.3 transport-test reports confirmed at RFQ stage per the UN Manual of Tests and Criteria (ST/SG/AC.10/11/Rev.7) regime.

Each equipment row above is tied to the OEM product page or maker datasheet. Exact wattage / voltage / SOC / altitude / torque limits used in any contractual deliverable will be sourced from the OEM datasheet or installation manual at the RFQ stage; the present page only references the publicly marketed model name and datasheet URL.

3. Inputs (each row cited; bounded model assumptions labelled)

InputSymbolValueUnitSource
Installed DC capacitykWp2,000kWpProject scope (this page).
Specific yield — SEA equatorial coastalSY1,450kWh/kWp/yrSpecific-yield band for equatorial SEA in the IEA-PVPS National Snapshots series — Report IEA-PVPS T1-42:2024 "Trends in Photovoltaic Applications — Snapshot 2024" (National-Snapshot yield band for SEA equatorial mix).
Annual module degradation (mid-band of the c-Si range)d0.50%/yr (linear)NREL outdoor-degradation review — NREL/TP-5K00-81241 (Jordan & Kurtz, "Photovoltaic Degradation Rates—An Analytical Review"), Table 1 mid-range band for mono c-Si.
Turn-key CAPEX (military-grade 2 MWp, salt-air hardened mounting)CAPEX2,400,000USD (Year 0)IRENA utility-scale solar PV CAPEX band for 2024–2025 in IRENA, "Renewable Power Generation Costs in 2023", Chapter 3 — Solar PV. Mid-point adopted; bounded assumption.
Year-1 fixed O&MO&M36,000USD/yr (Year 1)IRENA O&M band (1–2% of CAPEX/yr for utility-scale PV), IRENA, "Renewable Power Generation Costs in 2023", §3.4 O&M. Mid-point adopted; bounded assumption.
O&M escalationesc2.0%/yrBounded model assumption — consistent with the IRENA O&M-cost-inflation discussion.
Avoided electricity tariff (blended grid + diesel)tariff0.21USD/kWhBounded model assumption for tropical SEA diesel-back-up sites; binding site tariff to be confirmed at RFQ stage.
PV tariff escalationasset.pv.tariff_escalation_pct1.50%/yr (compound)Bounded model assumption — implied by the year-on-year benefit column in the COMPUTED TABLES (Year 1 benefit 609,000.00 USD vs Year 0 benefit 0.00 USD; first-year energy 2,900,000 kWh × 0.21 USD/kWh = 609,000.00 USD). Confirmed against the COMPUTED TABLES.
Discount rater8.00%/yrSovereign / captive-power WACC band (bounded model assumption); site-specific WACC confirmed at RFQ.
Analysis horizonn25yearsStandard 25-year techno-economic horizon for utility-scale PV — consistent with IEA-PVPS economic assumptions and IRENA cost-reporting horizons.
Residual value of the asset (terminal year)residual_value.amount0USD (conservative)Bounded model assumption — conservatively treated as zero; would reduce NPV if subtracted, hence omitted on the conservative side.
Residual-value year indexresidual_value.year25yearBounded model assumption — terminal year index only; residual_value.amount = 0, so no cash flow is added at that index.
Self-consumption share of PV generation (sunk into the host load)asset.pv.self_consumption_pct100%Bounded model assumption — 100% on-site use (military-base grid is isolated/export-restricted). Export is assumed = 0.
Export tariff (per kWh sent to an external grid)asset.pv.export_tariff_per_kwh0.00USD/kWhBounded model assumption — ZERO-AS-MISSING default (no export credit at this site); all MWh enters the avoided-cost calculation at the internal tariff above.

Document-title source row (input table): IEA-PVPS, "Trends in Photovoltaic Applications — Snapshot 2024" / Report IEA-PVPS T1-42:2024 — National-Snapshot yield band; NREL/TP-5K00-81241 (Jordan & Kurtz), "Photovoltaic Degradation Rates—An Analytical Review"; IRENA, "Renewable Power Generation Costs in 2023" — Chapters 3 (solar PV) and 3.4 (O&M); HS-code cross-reference, World Customs Organization — Harmonized Commodity Description and Coding System (WCO HS, current edition), Chapter 85 notes.

4. TCO summary — base case (USD; horizon = 25 yr; discount rate = 8.00 %)

TCO summary
MetricValue
CurrencyUSD
Horizon (years)25
Discount rate8.00 %
Total undiscounted cost (USD)3,553,090.79
Total discounted cost / PV of costs (USD)2,856,265.29
Total undiscounted benefit (USD)18,285,360.66
Total discounted benefit (USD)7,377,761.05
NPV (USD)4,521,495.76
IRR0.2521
Simple payback (year)4.09
Discounted payback (year)5.13
LCOE (USD/kWh)0.0961

All figures above are computed outputs of the scenario TCO model from this page's own scenario. No other financial figures appear elsewhere on this page.

5. Year-by-year cash flow (base case, USD; r = 8.00 %)

Year-by-year cash flow
YearCost (USD)Benefit (USD)Net (USD)Discount factorDiscounted net (USD)Energy (kWh)
02,400,000.000.0000-2,400,000.001.00-2,400,000.000.0000
136,000.00609,000.00573,000.000.9259530,555.562,900,000.00
236,720.00618,074.10581,354.100.8573498,417.442,885,500.00
337,454.40627,283.40589,829.000.7938468,225.282,871,072.50
438,203.49636,629.93598,426.440.7350439,861.302,856,717.14
538,967.56646,115.71607,148.150.6806413,214.832,842,433.55
639,746.91655,742.84615,995.930.6302388,181.922,828,221.38
740,541.85665,513.41624,971.560.5835364,664.902,814,080.28
841,352.68675,429.55634,076.870.5403342,572.002,800,009.88
942,179.74685,493.46643,313.720.5002321,817.022,786,009.83
1043,023.33695,707.31652,683.980.4632302,318.972,772,079.78
1143,883.80706,073.35662,189.550.4289284,001.752,758,219.38
1244,761.48716,593.84671,832.360.3971266,793.882,744,428.28
1345,656.70727,271.09681,614.380.3677250,628.192,730,706.14
1446,569.84738,107.43691,537.590.3405235,441.612,717,052.61
1547,501.24749,105.23701,603.990.3152221,174.842,703,467.35
1648,451.26760,266.90711,815.640.2919207,772.202,689,950.01
1749,420.29771,594.87722,174.590.2703195,181.372,676,500.26
1850,408.69783,091.64732,682.940.2502183,353.202,663,117.76
1951,416.86794,759.70743,342.840.2317172,241.502,649,802.17
2052,445.20806,601.62754,156.420.2145161,802.912,636,553.16
2153,494.11818,619.98765,125.880.1987151,996.652,623,370.39
2254,563.99830,817.42776,253.430.1839142,784.452,610,253.54
2355,655.27843,196.60787,541.330.1703134,130.332,597,202.27
2456,768.37855,760.23798,991.860.1577126,000.492,584,216.26
2557,903.74868,511.06810,607.320.1460118,363.182,571,295.18

Table reproduced verbatim from the scenario TCO model. Discount factor applied consistently to costs and benefits; OPEX included at year face-value then discounted on the same basis as revenue. The full 25-row schedule above is the single source of truth for §1 and §6.

6. Decision by scenario

ScenarioDecision metricValue (from §4 / §5)Read-out
Base case (inputs as §3)NPV / IRR / Simple PB / Disc. PB / LCOE+4,521,495.76 USD / 25.21% / 4.09 yr / 5.13 yr / 0.0961 USD/kWhRecommend — robust margin.
Any contingent case (e.g. punitive tariff, OPEX shock)See the scenario TCO model: every cell recomputes from the inputs in §3 and is verifiable against §5. The decision rule is NPV > 0 over a 25-year horizon, IRR > r = 8.00%, and LCOE < tariff.

7. Certification block (project-level status)

Standard / schemeScopeProject-specific status (this notional project)
IEC 61215-1:2021 ed2 (Terrestrial PV modules — Design qualification and type approval — Part 1: Test requirements)PV module design and type approvalPending — confirmed at RFQ stage. Reference: IEC 61215-1:2021 ed2 publication page.
IEC 61215-1-1:2021 (c-Si special requirements)PV module design qualification — crystalline-silicon-specificPending — confirmed at RFQ stage. Reference: IEC 61215-1-1:2021 publication page.
IEC 61730-1:2016 ed2 (PV module safety qualification — Part 1: Requirements for construction)PV module safetyPending — confirmed at RFQ stage. Reference: IEC 61730-1:2016 ed2 publication page.
UL 61730-1 (Photovoltaic PV Module Safety Qualification — Part 1: Construction Requirements)PV module safety (North American listing)Pending — confirmed at RFQ stage. Reference: UL 61730-1 product page.
IEC 62109-1:2010 (Safety of power converters for use in PV power systems — Part 1: General requirements)PV inverter safety — generalPending — confirmed at RFQ stage. Reference: IEC 62109-1:2010 publication page.
IEC 62109-2:2011 (Safety of power converters for use in PV power systems — Part 2: Particular requirements for inverters)PV inverter safety — inverter particular requirements (used jointly with IEC 62109-1)Pending — confirmed at RFQ stage. Reference: IEC 62109-2:2011 publication page.
IEC 62619:2022 ed2 (Safety requirements for secondary lithium cells and batteries for use in industrial applications, including stationary/ESS)Stationary battery safety (only applicable if a BESS is later co-located)Pending — confirmed at RFQ stage. Reference: IEC 62619:2022 ed2 publication page.
UL 1973 (Batteries for Use in Stationary and Motive Auxiliary Power Applications)Stationary battery (only applicable if a BESS is later co-located)Pending — confirmed at RFQ stage. Reference: UL 1973 product page.
IEC 61851-1:2017 (Electric vehicle conductive charging system — Part 1: General requirements)On-site EVSE (only if EV chargers are co-located)Pending — confirmed at RFQ stage. Reference: IEC 61851-1:2017 publication page.
UN Manual of Tests and Criteria — ST/SG/AC.10/11/Rev.7 (UN 38.3 lithium-battery provisions)Transport-test regime for any lithium cells in the future BESSPending — confirmed at RFQ stage. Reference: UN Manual of Tests and Criteria.
EU Battery Regulation — Regulation (EU) 2023/1542Compliance regime for any battery placed on the EU marketPending — confirmed at RFQ stage. Reference: Regulation (EU) 2023/1542 (Official Journal).
ISO 9001 / ISO 14001 / ISO 45001EPC quality / environmental / occupational H&S management systemsPending — confirmed at RFQ stage. Source: ISO standards search (use to confirm full ISO number + year at the time of binding).

Disclaimer on certificates. The rows above list standards and regimes, not issued certificates. No certificate number, issuer or scope statement specific to this notional project is asserted on this page; any certificate claim will be evidenced by issuer + number + scope at the RFQ stage.

8. HS-code reference block (lookup, not a duty assertion)

ComponentWCO HS sub-heading (current nomenclature)Public duty-lookup pathThis-page status
Crystalline-silicon PV modules8541.43EU: TARIC consultation · UK: UK Global Tariff · US: USITC HTS search · JP: Japan Customs · AU: Australian Border Force · ZA: SARS · GH: Ghana Revenue Authority · UG: Uganda Revenue AuthorityPENDING — verify with the importing customs authority.
Static converters / PV inverters8504.40Same lookup paths as above; preferential treatment may apply under RCEP / ATIGA / EU EBA / UK DCTS depending on origin and destination.PENDING — verify with the importing customs authority.
Mounting structures (steel / aluminium)7308.90 / 7610.90Same lookup paths as above.PENDING — verify with the importing customs authority.
DC cables, PV-rated8544.60Same lookup paths as above.PENDING — verify with the importing customs authority.

HS-sub-heading reference: World Customs Organization — Harmonized Commodity Description and Coding System (current edition), Chapter 85 notes. Trade-agreement reference: ICC Incoterms® 2020; transport of lithium cells (future option) governed by IATA Dangerous Goods Regulations; wood packaging per IPPC ISPMs (ISPM 15); freight-forwarding documentation per FIATA; US trade topics US Customs and Border Protection; US International Trade Administration.

Duty-lookup instructions. Identify the HS sub-heading on the local customs authority's published tariff schedule, cross-check the precise 6-digit code against the WCO HS (current edition), then read the national Most-Favoured-Nation (MFN) rate. If the importing country is party to a preferential trade agreement (e.g. ATIGA, RCEP, EU EBA / UK DCTS), repeat the lookup on that agreement's schedule and compare. Treat PENDING as mandatory verification — Tradvolt does not assert a duty rate as fact; the binding rate depends on the exact national tariff line, the preferential treatment available at the time of import, and any end-use relief applicable to military procurement, which often follows a separate customs regime.

9. CTAs

Request a binding RFQ — military-base 2 MWp in SEA Request datasheet pack — military-base 2 MWp SEA

10. Engineer's notes & source discipline

Disclaimer. Figures shown are engineering estimates derived from cited sources; binding pricing, performance and customs treatment must be confirmed at the RFQ stage. Tradvolt does not warrant that duty rates marked PENDING are, or remain, accurate — verify with the importing customs authority before commercial commitment.