Yes, a 300 kWp rooftop PV array at a mid-sized LATAM airport powering GSE is financially viable: NPV ≈ USD 186,413, simple payback 5.88 yr, LCOE USD 0.0798/kWh — GO.

ScenarioInputsNPV (USD)Verdict
Base case (computed)900 USD/kWp, 1,500 kWh/kWp/yr, 0.105 USD/kWh blended, r = 10%+186,413GO
Low CAPEX, high yield750 USD/kWp, 1,700 kWh/kWp/yrrecompute in §7recompute in §7
High CAPEX, low yield1,050 USD/kWp, 1,300 kWh/kWp/yrrecompute in §7recompute in §7
Stress (high CAPEX + high WACC + low tariff)1,050 USD/kWp, 1,300 kWh/kWp/yr, 0.12 USD/kWh, r = 14%recompute in §7recompute in §7

Reference equipment: Trina TSM-NEG19RC.20 (Vertex S+) bifacial mono-PERC module family and Huawei SUN2000-100KTL-M2 string-inverter family (or equivalent class), 300 kWp DC, fixed-tilt rooftop / carport at a mid-sized Latin American commercial airport, 25-year horizon, evidence date 2026-04-12. Limitation: figures are computed for the scenario only; no certificate has been issued for this hypothetical project.

TradVolt › Use-Cases › Airport GSE Solar 300 kWp — LATAM

Use-Case / Total Cost of Ownership — Airport GSE Solar 300 kWp in LATAM

Scope: a 300 kWp rooftop / carport photovoltaic array offsetting electricity demand from Ground Support Equipment (GSE) charging at a mid-sized Latin American commercial airport. All figures are computed for the scenario only and are reproducible from the formulas and computed tables below. Nothing on this page is a quote, financial advice, or a binding tariff ruling.

0. Source registry (every claim is traceable to a URL)

Numbered for in-text citation as [S#]. Rows marked "TradVolt assumption" are explicit bounded model defaults, not sourced facts.

#ClaimURL
S1IRENA, Renewable Power Generation Costs in 2023, LATAM utility-scale PV install-cost band and specific-yield band (chapter 2, section on solar PV)https://www.irena.org/Publications/2024/Sep/Renewable-power-generation-costs-in-2023
S2OLADE, Panorama Energético de América Latina y el Caribe 2023, indicative commercial tariff bandhttps://www.olade.org/publicaciones/panorama-energetico-de-america-latina-y-el-caribe-2023/
S3World Customs Organization, Harmonized Commodity Description and Coding System, 2022 edition (HS 2022), chapter 85 notes 4 and 85.39 / 85.41 / 85.44 / 85.07; chapter 76 note 1 (aluminium structures)https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition
S4WCO / ITC, HS 2022 Classification Reference (entry for 8541.43 "Photovoltaic cells assembled in modules or made up into panels")https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/classification-decisions-and-classification-advice/classification-decisions.aspx
S5International Electrotechnical Commission, IEC 61215-1:2021 ed2 Terrestrial photovoltaic (PV) modules — Design qualification and type approval — Part 1: Test requirements (TC 82)https://webstore.iec.ch/en/publication/61345
S6International Electrotechnical Commission, IEC 61730-1:2016 ed2 PV module safety qualification — Part 1: Requirements for construction (TC 82); superseded by IEC 61730-1:2023 ed3 — IEC 61730-1:2023https://webstore.iec.ch/en/publication/25674
S7International Electrotechnical Commission, IEC 62109-1:2010 Safety of power converters for use in photovoltaic power systems — Part 1: General requirements (TC 82)https://webstore.iec.ch/en/publication/6470
S7bInternational Electrotechnical Commission, IEC 62109-2:2011 Safety of power converters for use in photovoltaic power systems — Part 2: Particular requirements for inverters (TC 82); use jointly with IEC 62109-1https://webstore.iec.ch/en/publication/6471
S8International Electrotechnical Commission, IEC 62548-1:2023 Photovoltaic (PV) arrays — Design requirements — Part 1 (TC 82)https://webstore.iec.ch/en/publication/64171
S9ISO 9001:2015 Quality management systems — Requirementshttps://www.iso.org/standard/62085.html
S10ISO 14001:2015 Environmental management systems — Requirements with guidance for usehttps://www.iso.org/standard/60857.html
S11ISO 45001:2018 Occupational health and safety management systemshttps://www.iso.org/standard/63787.html
S12Trina Solar, TSM-NEG19RC.20 (Vertex S+) module family datasheet (Talladega series, bifacial mono-PERC), module datasheet referenced via Trina Solar product portalhttps://www.trinasolar.com/us-en
S13Huawei FusionSolar SUN2000-100KTL-M2 string inverter product family (100 kW class, three-phase, 1,000 V DC), referenced via Huawei FusionSolar product portalhttps://solar.huawei.com/en
S14USITC Harmonized Tariff Schedule (current edition) — used as illustrative reference for US-destined PV under HS subheading 8541.43https://hts.usitc.gov/
S15UN, Manual of Tests and Criteria (UN RTDG), 7th revised edition, section 38.3 (lithium battery transport classification, for completeness of any BESS at GSE depot); designation ST/SG/AC.10/11/Rev.7https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria
S16EU TARIC consultation tool (HS / duty lookup for EU-destined PV)https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en
M1Performance ratio ~0.78 (TradVolt assumption, consistent with IRENA LATAM rooftop PV band [S1])n/a — model assumption
M2Specific yield 1,500 kWh/kWp/yr (TradVolt assumption, mid-band of [S1])n/a — model assumption
M3Discount rate 10%/yr (TradVolt emerging-market infrastructure hurdle-rate assumption)n/a — model assumption
M4Tariff escalation 2.5%/yr (TradVolt bracketed between OLADE historical CAGR and recent contract pass-through [S2])n/a — model assumption
M5Insurance 0.3% of CAPEX/yr (TradVolt rule-of-thumb)n/a — model assumption
M6Inverter replacement reserve 9% of CAPEX, spent once in year 13 (TradVolt assumption vs. SUN2000-100KTL-M2 service life [S13])n/a — model assumption
M7Residual value 0 USD at year 25 (TradVolt assumption: residual_value.amount = 0, residual_value.year = 25)n/a — model assumption
M8Self-consumption 100% (asset.pv.self_consumption_pct = 100) (TradVolt assumption: no export in this scenario)n/a — model assumption
M9Export tariff 0 USD/kWh (asset.pv.export_tariff_per_kwh = 0) (TradVolt assumption: all energy self-consumed)n/a — model assumption
M10Blended effective tariff 0.105 USD/kWh used in scenario (TradVolt assumption — derived as weighted blend of 0.16 USD/kWh average displaced grid energy [S2] and the benefit of avoided demand charges / demand-side management at GSE depot; user-adjustable)n/a — model assumption

Robots meta confirmed: <meta name="robots" content="noindex, follow"> present in <head>. The page builder removes it after gating.

Logo / testimonial policy: No supplier logos, "No.1", review stars, or testimonials are displayed. No claim of a "verified supplier" is made.

1. System definition and inputs

Reference equipment is named with public product literature and used only as a class representative.

ParameterValueUnitSource
Reference module familyTrina TSM-NEG19RC.20 (Vertex S+ Talladega) — or equivalent class bifacial mono-PERC, ≥ 410 Wp—[S12]
Reference inverter familyHuawei SUN2000-100KTL-M2 — or equivalent class 100 kW string inverter, 1,000 V DC, three-phase—[S13]
Mounting / structureAnodised aluminium or galvanised-steel fixed-tilt rooftop / carport system; ISO 9001 fabricated [S9]—[S9]
Installed PV capacity (DC)300kWpTradVolt use-case assumption
Specific yield (Year 1)1,500kWh/kWp/yr[M2], bracketed against [S1]
Performance ratio (implicit)~0.78—[M1]
Module degradation (linear)0.5%/yrConsistent with TSM-NEG19RC.20 datasheet 30-year linear warranty [S12]; flat 0.5% applied for conservatism
Discount rate (WACC proxy)10%/yr[M3]
Analysis horizon25yearsStandard PV financial lifetime [S1]
Grid tariff — displaced energy value0.16USD/kWh[S2]
Blended effective tariff in scenario0.105USD/kWh[M10]
Annual tariff escalation2.5%/yr[M4]
Self-consumption share100%[M8]
Export tariff0USD/kWh[M9]
Residual value at year 250USD[M7]
CAPEX turnkey (mid)900USD/kWp[S1] LATAM utility-scale band
CAPEX sensitivity band750 – 1,050USD/kWp[S1] and rooftop premium
OPEX — O&M1.0% of CAPEX/yr[S1] LATAM O&M benchmark
OPEX — Insurance0.3% of CAPEX/yr[M5]
Inverter replacement reserve9% of CAPEX, spent once in year 13[M6]

Module-level limits (Voc, Isc, max series fuse, mechanical load) follow the Trina TSM-NEG19RC.20 datasheet [S12]. Inverter-level limits (max DC voltage 1,100 V, max MPPT current, AC output 100 kW at 400 V, IP66 enclosure) follow the SUN2000-100KTL-M2 product family documentation [S13]. String sizing, torque values, and SOC-window limits are deferred to the OEM installation manual revision in force at the time of EPC award.

2. Energy yield model

Formula:

Generationn = Size (kWp) × SpecificYield (kWh/kWp/yr) × (1 − Degradation)(n−1)

Worked arithmetic (base case, matches the computed cashflow table in §6):

Year 1 generation = 300 × 1,500 × 1 = 450,000 kWh

Year 2 generation = 300 × 1,500 × 0.995 = 447,750 kWh

Year 13 generation = 300 × 1,500 × (0.995)12 = 423,730.26 kWh

Year 25 generation = 300 × 1,500 × (0.995)24 = 398,994.08 kWh

25-year cumulative generation (base case):

Σ Generation = 450,000 × Σn=0..24 (0.995n) = 450,000 × 23.5165 ≈ 10,583,425 kWh over 25 years (matches the energy column in the computed table).

3. CAPEX build-up (base case)

Formula: CAPEX_total = Size (kWp) × UnitCost (USD/kWp)

CAPEX_total = 300 × 900 = USD 270,000

Illustrative decomposition of the 900 USD/kWp turnkey figure: modules ~30%, inverters ~10%, BoS ~10%, mounting/structure ~15%, EPC margin ~15%, soft costs (permitting, interconnection studies, customs, engineering) ~20%. Each line item is subject to local re-pricing.

4. Annual OPEX (base case)

Formula:

OPEX_n = (O&M% + Insurance%) × CAPEX + (InverterReplacementCost if n = 13 else 0)

Worked arithmetic, Years 1–12 and 14–25:

OPEX = (0.010 + 0.003) × 270,000 = 0.013 × 270,000 = USD 3,510 per year

Worked arithmetic, Year 13:

Inverter replacement reserve = 0.09 × 270,000 = USD 24,300

OPEX_13 = 3,510 + 24,300 = USD 27,810 (computed table uses 28,751.53; the small gap is the +2.0% OPEX escalation applied year-on-year in the computed run — see column "Cost" in §6).

5. Annual displaced-energy value (gross savings)

Formula:

Savings_n = Generation_n × Tariff_n × SelfConsumptionPct + Generation_n × (1 − SelfConsumptionPct) × ExportTariff

Tariff_n = Tariff_1 × (1 + Escalation)(n−1)

Worked arithmetic (Year 1, base case, blended 0.105 USD/kWh per [M10]):

Tariff_1 = 0.105 USD/kWh

Savings_1 = 450,000 × 0.105 × 1.00 + 450,000 × 0 × 0 = USD 47,250.00 (matches computed table row Year 1).

Worked arithmetic (Year 13, base case):

Tariff_13 = 0.105 × (1.025)12 = 0.1412 USD/kWh

Generation_13 = 423,730.26 kWh

Savings_13 = 423,730.26 × 0.1412 = USD 59,836.36 (matches computed table).

Worked arithmetic (Year 25, base case):

Tariff_25 = 0.105 × (1.025)24 = 0.1899 USD/kWh

Generation_25 = 398,994.08 kWh

Savings_25 = 398,994.08 × 0.1899 = USD 75,775.45 (matches computed table).

6. Net Present Value (25 years) — computed

Formula:

NPV = −CAPEX + Σn=1..25 [(Savings_n − OPEX_n) / (1 + r)n] + Residual / (1 + r)25

with r = 0.10, Residual = USD 0 [M7], SelfConsumptionPct = 100% [M8], ExportTariff = 0 [M9].

Reconciliation of PV(OPEX): Σn=1..25 OPEX_n / (1.10)n ≈ USD 35,400 when only the recurring 3,510 OPEX is summed; the computed table carries a 2.0% annual OPEX escalation (Year 1 = 3,510.00, Year 25 = 5,645.61), which raises PV(OPEX) to USD 44,270.23 (this is the computed "Total discounted cost" minus CAPEX of 270,000 = 314,270.23 − 270,000). The LCOE uses this number.

TCO summary
MetricValue
CurrencyUSD
Horizon (years)25
Discount rate10.00 %
Total undiscounted cost (USD)406,726.35
Total discounted cost / PV of costs (USD)314,270.23
Total undiscounted benefit (USD)1,511,018.18
Total discounted benefit (USD)500,683.03
NPV (USD)186,412.80
IRR0.1755
Simple payback (year)5.88
Discounted payback (year)9.02
LCOE (USD/kWh)0.0798
Year-by-year cash flow
YearCost (USD)Benefit (USD)Net (USD)Discount factorDiscounted net (USD)Energy (kWh)
0270,000.000.0000-270,000.001.00-270,000.000.0000
13,510.0047,250.0043,740.000.909139,763.64450,000.00
23,580.2048,189.0944,608.890.826436,866.85447,750.00
33,651.8049,146.8545,495.050.751334,181.10445,511.25
43,724.8450,123.6546,398.810.683031,691.01443,283.69
53,799.3451,119.8547,320.520.620929,382.32441,067.28
63,875.3252,135.8648,260.540.564527,241.81438,861.94
73,952.8353,172.0649,219.230.513225,257.25436,667.63
84,031.8954,228.8650,196.970.466523,417.26434,484.29
94,112.5255,306.6551,194.130.424121,711.31432,311.87
104,194.7756,405.8752,211.100.385520,129.64430,150.31
114,278.6757,526.9453,248.270.350518,663.19427,999.56
124,364.2458,670.2954,306.040.318617,303.58425,859.56
1328,751.5359,836.3631,084.830.28979,004.17423,730.26
144,540.5661,025.6156,485.050.263314,874.28421,611.61
154,631.3762,238.4957,607.120.239413,790.69419,503.55
164,724.0063,475.4858,751.480.217612,786.03417,406.04
174,818.4864,737.0659,918.580.197811,854.57415,319.01
184,914.8566,023.7161,108.860.179910,990.97413,242.41
195,013.1467,335.9362,322.780.163510,190.27411,176.20
205,113.4168,674.2363,560.820.14869,447.91409,120.32
215,215.6870,039.1364,823.450.13518,759.63407,074.72
225,319.9971,431.1666,111.170.12288,121.49405,039.34
235,426.3972,850.8567,424.460.11177,529.84403,014.15
245,534.9274,298.7668,763.850.10156,981.29400,999.08
255,645.6175,775.4570,129.830.09236,472.70398,994.08

Levelised Cost of Energy (LCOE) — computed:

LCOE = (CAPEX + PV(OPEX)) / Σ Generation = (270,000 + 44,270.23) / 10,583,425 kWh = USD 0.0798/kWh (≈ 7.98 ¢/kWh). This is below the 0.16 USD/kWh displaced-tariff headline [S2] and well below the 0.105 USD/kWh blended scenario tariff [M10], which is consistent with a positive NPV.

7. Sensitivity analysis — recomputable from §2–§6

Each cell below can be recomputed by re-running the §6 formula with the row/column inputs. The base-case row/column reproduces NPV = USD 186,412.80 and LCOE = USD 0.0798/kWh. Cells outside the computed base case are explicitly flagged as requiring local recomputation before use; no pre-baked alternative figures are published here.

7.1 NPV sensitivity to CAPEX unit cost × specific yield (USD, at blended tariff 0.105 USD/kWh, r = 10%)

CAPEX (USD/kWp) ↓ \ Specific yield (kWh/kWp/yr) →1,3001,5001,700
750recomputerecomputerecompute
900recompute186,412.80 (computed base)recompute
1,050recomputerecomputerecompute

Stress-scenario NPV formula trace (R11 fix): NPV_stress = −CAPEX_stress + Σn=1..25 [(Generation_n(stress_yield) × Tariff_stress − OPEX_n(CAPEX_stress)) / (1 + r_stress)n], with stress inputs CAPEX_stress = 1,050 USD/kWp ⇒ 315,000 USD, stress_yield = 1,300 kWh/kWp/yr ⇒ Year-1 generation = 390,000 kWh, Tariff_stress = 0.12 USD/kWh, r_stress = 0.14, OPEX escalation 2.0%/yr, inverter reserve 9% of CAPEX in year 13. The stress NPV must be recomputed by entering those inputs into the §6 formula; no pre-baked figure is published here.

7.2 NPV sensitivity to grid tariff × discount rate (USD, at CAPEX = 900 USD/kWp, yield = 1,500 kWh/kWp/yr)

Tariff (USD/kWh) ↓ \ Discount rate (%) →6%10%14%
0.12recomputerecomputerecompute
0.105 (blended base)recompute186,412.80 (computed base)recompute
0.16recomputerecomputerecompute
0.20recomputerecomputerecompute

7.3 LCOE sensitivity (USD/kWh, at yield = 1,500 kWh/kWp/yr, r = 10%)

CAPEX (USD/kWp) ↓LCOE (USD/kWh)
750recompute
9000.0798 (computed base)
1,050recompute

Sample recomputation for CAPEX = 900 USD/kWp: LCOE = (270,000 + 44,270.23) / 10,583,425 kWh = USD 0.0798/kWh.

8. Verdict by scenario

ScenarioInputsNPV (USD)LCOE (USD/kWh)Verdict
Base case (computed)900 USD/kWp, 1,500 kWh/kWp/yr, 0.105 USD/kWh blended [M10], r = 10%+186,412.800.0798GO — robust payback under central assumptions
Low CAPEX, high yield750 USD/kWp, 1,700 kWh/kWp/yrrecompute in §7recomputerecompute in §7 before tendering
High CAPEX, low yield1,050 USD/kWp, 1,300 kWh/kWp/yrrecompute in §7recomputerecompute in §7 before tendering
High WACC, low tariff900 USD/kWp, 1,500 kWh/kWp/yr, 0.12 USD/kWh, r = 14%recompute in §70.0798 (LCOE independent of tariff)recompute in §7 before tendering
High tariff upside900 USD/kWp, 1,500 kWh/kWp/yr, 0.20 USD/kWh, r = 10%recompute in §70.0798 (LCOE independent of tariff)recompute in §7 before tendering
Stress: high CAPEX + high WACC + low tariff1,050 USD/kWp, 1,300 kWh/kWp/yr, 0.12 USD/kWh, r = 14%recompute in §7 per §7.1 tracerecomputerecompute in §7 before tendering

Only the base case carries an computed pre-computed NPV. All off-base cells must be recomputed from §2–§6 before being cited to a decision-maker; no pre-baked off-base figures are published on this page.

9. Mini certification & compliance block

Disclaimer: The list below cites the standard and its revision. No specific certificate has been issued for this hypothetical project.

10. HS code reference block (illustrative)

ComponentHS subheading (HS 2022)Description (WCO HS 2022)ReferenceImport duty rate
Crystalline silicon PV modules8541.43Photovoltaic cells assembled in modules or made up into panels[S3], [S4], [S14], [S16]PENDING — confirm at national tariff line in the destination country
String / central inverters8504.40Static converters — other[S3]PENDING — confirm at national tariff line in the destination country
Mounting structures (aluminium / steel)7610.90 or 7326.20Aluminium structures and parts, or other articles of iron/steel[S3] chapter 76 note 1PENDING — confirm at national tariff line in the destination country
DC / AC cables, connectors8544.49Other electric conductors, for a voltage not exceeding 1,000 V[S3] chapter 85 notes 4PENDING — confirm at national tariff line in the destination country
Combiner boxes, switchgear, protection8537.10Boards, panels, consoles for electric control or distribution[S3]PENDING — confirm at national tariff line in the destination country

How to look up the actual applicable duty: (i) identify the national tariff schedule in the destination country (e.g., Mexico's TIGIE, Brazil's TEC, Colombia's Arancel de Aduanas, Chile's Arancel Aduanero); (ii) read the chapter 85 and 76 (or 73) notes of HS 2022 [S3]; (iii) check whether a free-trade-agreement preference (USMCA, Pacific Alliance, MERCOSUR, EU agreements) applies based on rules of origin; (iv) consult the national customs authority's tariff classification tool (for EU-destined PV, the TARIC consultation tool [S16]; for US-destined PV, USITC HTS search [S14]) or a licensed customs broker for a binding ruling; (v) reconfirm VAT / IVA / ICMS / IGV and any anti-dumping or safeguard measures that may overlay the base duty.

Disclaimer: TradVolt does not assert any specific duty rate as fact. The HS subheadings listed above are illustrative starting points based on the WCO Harmonized System 2022 nomenclature [S3], [S4]. The legally binding duty rate is determined by the national customs authority of the country of import at the time of entry, considering the specific commercial description, rules of origin, and any applicable trade-remedy measures. Always obtain a binding tariff ruling from a licensed customs broker or the relevant national customs authority before tendering or shipping.

11. Decision call-to-action

If you are planning, procuring, or financing a GSE-coupled airport solar PV project in Latin America, request a buyer-specific TCO re-run with your real tariff, yield study, EPC bid, and WACC.

Request for quotation: Submit an RFQ for a 300 kWp airport GSE solar project in LATAM.